Permit Information
Permit NumberESC19-00509
StatusIssued
Name GLENN L WILLIAMS
Site Address 3157 E BARBER VALLEY DR
Project NameMulti-Tenant Office Building
Customer Number 
ePlanReviewNo
Description
New Construction of a 2-story, 5800 SF Office building on Lot 6 of Block 2 ( .38 acres) which is located within OMR sub zone of the Barber Valley specific plan zone. The owner will occupy the top floor and lease out the bottom floor to one or possibly 2 tenants.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection7/27/20207/27/20207/27/2020 PASS
DetailsMichael Zawacki
WIP on framing, site is clean.
General Inspection6/9/20206/9/20206/9/2020 PASS
DetailsAndy J. Long
Permit posted, trash contained, lined washout pit behind building next to portapot. No trackout or discharges occuring. Approved.
General Inspection4/24/20204/24/20204/24/2020PPASS
DetailsMichael Zawacki
WIP on framing. Site is clean, using trash trailer with a cover.
Lined washout on site, no loose trah.
General Inspection3/11/20203/11/20203/11/2020PPASS
DetailsAndy J. Long
No trackout. No activity at time of inspection. Concrete washout utilized. Permit sign posted. No loose trash. Approved
General Inspection1/29/20201/29/20201/29/2020PPASS
DetailsMichael Zawacki
Met with foreman on site. Hoping to get plumbing done and inspected so they can pour floor. Washout on site, no issues.
General Inspection12/16/201912/16/201912/16/2019PPASS
DetailsMichael Zawacki
Ground is frozen. Plan on doing some trench work. Washout on site, will have another pour. No issues.
General Inspection11/20/201911/21/201911/21/2019PPASS
DetailsMichael Zawacki
Concrete crew setting forms and bar, have inspection scheduled for afternoon. Washout on location, not lined, box of poly is right in front of washout. Site is clean.
Site Preparation10/22/201910/22/201910/23/2019APASS
DetailsMichael Zawacki
Series of connected ponds dug for dewatering. All water staying on lot, have permission to use neighboring parcel. No discharges.
Plan on doing tap today and being done after one day.
Site Preparation7/29/20197/29/20197/29/2019APASS
DetailsMichael Zawacki
Met with foreman and excavator. Will acces site from rear. Biggest concern in sewer tap will need dewatering, excavator knows they will need dewatering plan.