General Inspection | 6/24/2020 | 6/24/2020 | 7/1/2020 | | PASS |
Andy J. Long
|
|
|
WIP on landscaping and site stabilization. Parking lot is now paved. Concrete washout pan onsite. No corrections requested.
|
Tracking Control | 4/23/2020 | 4/24/2020 | 4/28/2020 | A | FAIL |
Michael Zawacki
|
|
|
Still tracking. Talked to PM and said they have a sweeper scheduled. Around 800' of curbing to still be installed, washout on site. Expect to start paving lot in 7-10 days
|
General Inspection | 4/23/2020 | 4/23/2020 | 4/23/2020 | | PART |
Andy J. Long
|
|
|
Some trackout occuring due to the recent rain and concurrent haul in of material for parking lot. Construction entrance installed.
Follow up tracking control inspection scheduled
|
Tracking Control | 12/18/2019 | 12/20/2019 | 12/20/2019 | A | FAIL |
Michael Zawacki
|
|
|
No corrections made. Reinspection fee issued, will add all trades hold if not corrected. RP notified.
|
General Inspection | 12/17/2019 | 12/17/2019 | 12/17/2019 | P | FAIL |
Michael Zawacki
|
|
|
Message sent to RP. Construction entrances have been tracked over and compacted, lots of dirt in gutter and a boulder on street. Washout pans have over flowed and need to be serviced before any more pours. Giant mountain of backfill on site. Perimeter wattles in good shape.
|
General Inspection | 10/30/2019 | 11/12/2019 | 11/13/2019 | P | FAIL |
Andy J. Long
|
|
|
Construction entrances installed are not long or wide enough, using round rocks with no scraping edges.
Evidence of trackout and clean up with water being done on the street.
Notified RP that entrance need to be lengthen and rock added needs to be crushed/angular.
RP states that trackout occured by drivers avoiding trackpad yesterday. Corrections to make an entrance and exit route (enter west entrance, leave east entrance) and the exit trackout pad will have more rock and length added.
|
Site Preparation | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Andy J. Long
|
|
|
Perimter sediment control wattles are installed, rock construction entrance and trackpad installed on south boundary.
Grading crew has water truck on site for any dust control needed. For now, will wait to see where stormwater flows to see if we should install inlet protection at allumbaugh and whisperwood roundabout.
Plan is to use ecopan washouts for concrete washout, and to get paving done after foundation and prior to going vertical.
RP Ben onsite, provide ESC permit signs for posted. Issued warning/reminder regarding scheduling ESC site preparation inspections at start of project.
|