Site Final | 4/29/2020 | 4/29/2020 | 4/30/2020 | P | PASS |
Andy J. Long
|
|
|
Site stabilized and cleaned up. All temporary BMPs have been removed
|
General Inspection | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Michael Zawacki
|
|
|
Building exterior completed, crew on site paving parking lot. Work on sprinkler system, still mneeds landscaping. Still lots of interior work.
|
General Inspection | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PART |
Michael Zawacki
|
|
|
Stockpile is east of work area and past the end of installed BMPs. Masons on site, mortar mixer has secondary containment, some slurry from saw cutting on ground. Parking area is gravel, entrance installed. No trackout, inlet protection installed.
|
General Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Andy J. Long
|
|
|
BMPs installed, permit posted at entrance. No trackout or discharges. Minimal activity at site at time of inspection.
|
Site Preparation | 10/10/2019 | 10/11/2019 | 10/11/2019 | A | PASS |
Andy J. Long
|
|
|
Phone #: 2085591460 >> Inspection requested via mobile web by Aaron Carroll
Permit sign posted, perimter sediment controls installed, heavy duty construction entrance installed, MS4 inlet protection installed. Water truck onsite for dust control.
Approved.
|