General Inspection | 7/31/2020 | 7/31/2020 | 8/3/2020 | | PASS |
Michael Zawacki
|
|
|
WIP, site is contained.
|
General Inspection | 7/16/2020 | 7/16/2020 | 7/16/2020 | | PASS |
Michael Zawacki
|
|
|
Home framed, site is clean.
|
General Inspection | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PASS |
Michael Zawacki
|
|
|
Silt fence has been retrenched and fixed.
|
General Inspection | 6/18/2020 | 6/19/2020 | 6/24/2020 | P | PASS |
Michael Zawacki
|
|
|
Home is framed and lot is trash free. Lots of bare area on lot, no runoff.
|
General Inspection | 6/8/2020 | 6/10/2020 | 6/18/2020 | P | PEND |
Andy J. Long
|
|
|
follow up on corrections
Corrections were made but were not effective
|
General Inspection | 6/8/2020 | 6/8/2020 | 6/8/2020 | P | FAIL |
Andy J. Long
|
|
|
Runoff from back side of home and stockpile area ran down to sidewalk and gutter. Erosion controls wattle and permiter sediment control had been damaged by vehicle access for project.
Notified RP.
New perimter controls and rear construction entrance from Arrow Villa are to be installed.
Follow up scheduled.
|
General Inspection | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing. Site is clean. Site has been stripped all down back and to road, has gator guard. Few piles of fill in back yard.
|
General Inspection | 4/14/2020 | 4/14/2020 | 4/14/2020 | P | PASS |
Michael Zawacki
|
|
|
Brooks on site doing backfill. They plan on finishing today. Will repair entrance and make sure everything clean when they leave.
|
BMP Violation | 2/25/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Michael Zawacki
|
|
|
Swept clean
|
General Inspection | 2/25/2020 | 2/25/2020 | 2/25/2020 | P | FAIL |
Michael Zawacki
|
|
|
Mud and rocks tracked onto road and sidewalk. Pictures sent to RP Clive. Follow up scheduled.
|
Site Preparation | 2/11/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Andy J. Long
|
|
|
Permit posted. Initial track pad rock installed. Excavation in progress. Needs to sweep up trackout on sidewalk and gutter before the end of the week
|