Permit Information
Permit NumberESC20-00264
StatusIssued
Name STUART JAMES
Site Address 181 W HIGHLAND VIEW DR
Project NameFlatiron Ridge - Stuart
Customer Number 
ePlanReviewNo
Description
Hillside SFH. ESC site plan prepared. Install controls per ESC site plan and scheduled ESC Site Preparation inspection. Note: this will also cover activity under BLD20-00341
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/16/20206/16/20206/16/2020PPASS
DetailsMichael Zawacki
Inspected both homes and met with both RPs. No flow off of front of sites. Some rilling on rear hill, verry small. All followed fall line and went to wattles. Will clean up hill when dry enough to walk on without causing damage. Grass is starting to grow on hillside.
General Inspection5/21/20205/22/20205/26/2020APASS
DetailsMichael Zawacki
Foundation has been poured, backfill still not replaced. No esc issues, no issues on hillside.
General Inspection4/30/20204/30/20205/1/2020PPASS
DetailsMichael Zawacki
No hydroseeding yet. Hillside has no issues from rain. Talked to builder about flattening stockpiles. Will use topsoil to bring site to grade once foundation poured.
General Inspection4/14/20204/14/20204/14/2020PPASS
DetailsMichael Zawacki
Lot is stripped to grade. Topsoil is stored on site. No esc issues.
Complaint Inspection3/31/20203/31/20203/31/2020PPASS
DetailsMichael Zawacki
No issues with hillside. All water absorbed, no ruts or rills. No dirt leaving out bottom of site.
General Inspection3/24/20203/25/20203/25/2020PPASS
DetailsMichael Zawacki
Topsoil is stockpiled in front portion of lot. Spiers on site working on grading of lot and hillside. No issues.
Site Preparation3/16/20203/16/20203/16/2020PPASS
DetailsMichael Zawacki
Met with owner/builder and did site walk. Will begin with stripping topsoil and will keep it stockpiled. Will provide entrance for when hauling fill.
Will do lifts on rear hill. Currently only grading approved, will not build yet.