Information based on query as of Saturday, May 4, 2024.
Permit Information
Permit NumberFIR18-00001
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameMicron BLDG-39
Customer Number 
ePlanReviewYes
Description
[Micron Building 39 CUP - C29420]
The fire sprinkler scope of work consists of protecting one level of a mechanical building. The system layout is a 4”x4”x2 ½” grid.

• The underground in under permit FIR17-00502.

[BLD17-01950]
Plan modification 1 for all related mechanical, plumbing, electrical and interior improvements to finish out the building. The cup 3 building (b39) will be located south of the new B51 R&D expansion project. This permit is for structural only for building and utility trestle footings, foundations and structural steel components of the total design. The proposed new CUP B39 is 68,000 square feet with a 9,319 sq. ft. equipment platform and is type IIB construction. Building occupancy groups consist of F1, H3, and H4. All work per the approved plans and attached engineering. Special inspections are required. This building is fully fire sprinklered for area increase. CDM

Alternative Materials and Methods:

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/25/20197/26/20197/26/2019APASS
DetailsJim Page
Previously noted items that were notated on the city approved drawings has been corrected, final fire sprinkler inspection for area of work complete.

Clarence Phone #: ###-####
INSP-Final Inspection6/25/20196/25/20196/25/2019PFAIL
DetailsJim Page
Dillon has the city approved drawings that have been notated, numerous areas has no sway bracing, sway bracing is shown on the city approved drawings, sway bracing needs to be installed or removed from the city approved drawings. Numerous heads under duct work and piping has been added but the approved drawings do not reflect the install. City approved drawings have been notated where corrections need to be made.

Dillon Phone #: ###-####
INSP-Final Inspection6/18/20196/19/20196/19/2019ACANC
DetailsJim Page
Inspection request cancelled per conversation with point of contact, city approved drawings/small documents could not be located, city approved drawings and small documents are required for inspection.

Dillion Phone #: ###-####
INSP-Final Inspection4/12/20194/12/20194/12/2019PCANC
DetailsJim Page
Per conversation with my supervisor, Adele Schaffeld-Griffin, notes entered reading "Final fire sprinkler sign off of inspections for this permit will be completed at the same time as the life safety inspection is completed under the building permit." Please coordination with the general contractor to schedule the final inspections. Onsite inspection request for today will need to be rescheduled until coordinated inspections for the life safety can be scheduled.

Clarence Phone #: ###-####
INSP-Final Inspection7/30/20187/31/20187/31/2018PPART
DetailsJim Page
Final fire sprinkler inspection complete, fire sprinkler permit will remain in issued status until project is complete due to possible obstructions needing coverage.

Chris Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro6/15/20186/18/20186/18/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.

Chris Phone #: ###-####