Permit Information
Permit NumberFIR18-00021
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 301 N 29TH ST
Project NameWhittier Elementary School
Customer Number 
ePlanReviewYes
Description
[Whittier Elementary School]
The fire sprinkler scope of work consists of a 6” supply to a 3” riser with backflow preventer to supply two wet pipe sprinkler system in a two level new elementary school. The systems are a combination tree and grid type layouts. The mains are 3” and 2½” with 1½” branch lines.

• The underground piping is under permit FIR17-00729.

Fire Protection Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.
[BLD17-03016]
Permit for the construction of a new 68,458 sq. ft. elementary school to replace the existing school that is to be demolished when the new school is completed. Work will include..........

Alternative Materials and Methods:

• There are no AMM at this time which pertain to fire sprinkler protection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/17/20191/18/20191/18/2019APASS
DetailsJim Page
Final fire sprinkler inspection complete.

George Jess is the contact for this final inspection. Thank you.
Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro1/8/20191/9/20191/9/2019PDONE
DetailsJim Page
Hydrostatic test for overehad fire sprinkler piping witnessed, no pressure loss observed on both wet systems.

Overhead Hydro and the contact is George. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro1/7/20191/8/20191/8/2019ACANC
DetailsJim Page
Cancelled per conversation woith point of contact.

200lb hydro. George is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in1/7/20191/8/20191/8/2019APASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping complete, approved for cover.

overhead RTC. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/20/201812/21/201812/21/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping in kitchen complete, kitchen area approved for cover. Fire sprinkler heads around kitchen cooking hood will be changed to 200 degree heads before final inspection.

George is the contact. He asked for an inspection for a RTC in the Kitchen area. Thank you for your help! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in12/11/201812/12/201812/12/2018APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with yellow highlighter/red ink areas inspected and approved for cover. Temporary FDC will be installed by fire sprinkler riser room due to access, permenant location currently has portable buildings that will be removed in the future so a temp FDC will be required for occupancy until permenant location can be accessed by fire truck.

George Jess is the contact for this rough to cover inspection on the 2nd floor. Thank you for your help. Have a nice day. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in11/28/201811/29/201811/29/2018PPART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with pink highlighter/red ink areas inspected and approved for cover.

George Jess is the contact for this rough to cover inspection. He is hoping for an appointment in the PM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in11/1/201811/2/201811/2/2018APART
DetailsJim Page
Partial rough to cover inspection for overhead fire sprinkler piping complete, notated city approved drawings with pink highlighter/red ink areas approved for cover. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in10/10/201810/11/201810/11/2018PPART
DetailsJim Page
Notated city approved drawings with pink highlighter/red ink hardlids approved for cover.

Hard lid inspection Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in9/17/20189/18/20189/19/2018APASS
DetailsAdele J Schaffeld-Griffin
Forrest inspection comments-Inspection for cover completed at first floor below stairs sheetrock ceilings (3 locations). Be aware of possible obstructions to coverage due to surface mounted light fixtures not yet installed. Hard lids need to be inspected only. Phone #: ###-#### >> Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in8/9/20188/10/20188/10/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located above hardlids on level 1 complete, notated the city approved drawings with pink highlighter areas approved for cover.

George Jess is the contact for this inspection. He is request a Hard Lid inspection in the bathrooms. He is hoping for an appointment in the AM. We appreciate your help with this. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush7/2/20187/3/20187/3/2018ADONE
DetailsJim Page
Underground main line flush complete.

George Jess is the contact for this underground Hydro and Flush. An appointment has been scheduled with Jim Page for 10AM and with Gus with Suez. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro7/2/20187/3/20187/3/2018ADONE
DetailsJim Page
Underground hydrostatic test witnessed, no pressure loss observed at contractor provided gauge.

George Jess is the contact for this Underground Hydro ; Flush. It has been discussed with Jim Page ; Gus with Suez. The appointment time is for 10AM., thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Supply line flush6/29/20187/2/20187/2/2018ACANC
DetailsJim Page
Inspection request cancelled per conversation with installing contractors office, request will be rescheduled for a later date.

George Jess is the contact for this underground flush and underground hydro inspection. We visited with Jim and scheduled an appointment for 10AM. Thank you for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/29/20187/2/20187/2/2018ACANC
DetailsJim Page
George Jess is the contact for this underground Hydro and Flush. We talked to Jim Page to schedule and coordinate with Stacey @ Suez. The appointment that was made was for 10 AM. Thank you for your help. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus