Permit Information
Permit NumberFIR18-00298
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 8001 W FAIRVIEW AVE
Project NamePlayhouse Boise
Customer Number 
ePlanReviewYes
Description
[Playhouse Boise]
The fire sprinkler scope of work consists of a small grid system supplied from 6” underground, 3” riser with 3” backflow preventer. The grid is 2 ½”x 1 ½”x1 ¼”. The piping is CPVC.

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

[BLD18-]
There does not seem to be an associated building permit at this time.

Alternative Materials and Methods:

There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/21/20191/23/20191/23/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Contact Leroy Anderson ###-#### 30 Min prior to Fire Final Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in11/13/201811/14/201811/14/2018PPASS
DetailsTroy Cobbley
The additional hangers have been added. Will verify the 4 way brace at the riser during the final. All piping can be covered. Still need submittals verifying the calculations still work and all of the final items such as tags, signs, fire alarm panel.
INSP-Sprinkler Rough-in11/12/201811/13/201811/13/2018PPART
DetailsTroy Cobbley
The rough-in for the most part is passed. It appeears additional hangers are needed for the cpvc piping. Also as-builts need to be approved showing all of the additional fittings that have been added including the two 90's at the base of the riser and the 90's added on the cpvc piping grid lines.

Contact Scott Powada ###-#### 30 min prior to RTC Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Final Inspection11/1/201811/1/201811/1/2018PCANC
DetailsTroy Cobbley
Can't perform final until a rough-in inspection has been performed. As per previous inspection note the ceiling tile needs to be removed so that the piping can be inspected.

Contact Scotty Powada ###-#### 30 min prior to Fire Final Insp Start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro8/21/20188/22/20188/22/2018PDONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.

Contact Scott Powada ###-#### 30 min prior to RTC Hydro Insp start please

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in/Hydro8/16/20188/21/20188/21/2018PCANC
DetailsJim Page
Contact Scott Powada ###-#### 30 min prior to RTC Hydro Insp start please.

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
INSP-Sprinkler Rough-in8/16/20188/17/20188/17/2018AFAIL
DetailsJim Page
Phone number provided was not the correct point of contact, building is locked and secure with no access, inspection will need to be rescheduled.

Contact Brad Westbrook ###-#### 30 min prior to RTC Insp start please.

Thank YOU Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Sprinkler Rough-in8/15/20188/16/20188/16/2018PCANC
DetailsTroy Cobbley
To be rescheduled when ceiling tile has been removed

Contact Scott Powada ###-#### 30 min prior to RTC Insp Start please, he would like to schedule at the same time as the UG RTC.

Thanks Phone #: ###-#### Inspection requested via web by Teri Cruickshank
INSP-Supply line flush8/6/20188/7/20188/7/2018ACANC
DetailsTroy Cobbley
Contact Scotty Powada 30 Min prior to Flush Start, Suez water would like to t schedule for 10:30 AM of possilbe...

Thank YOU Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank