INSP-Final Inspection | 9/18/2018 | 9/19/2018 | 9/19/2018 | P | PASS |
Tim Frost
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus
__________________
Ok on the units I checked, Troy checked the rest.
|
DOC - Permit Finaled | | | 9/19/2018 | | PASS |
Tim Frost
|
|
|
|
INSP-Final Inspection | 9/17/2018 | 9/18/2018 | 9/18/2018 | P | FAIL |
Tim Frost
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus
_________________
Four lights too close to the sprinklers units 205, 205 and two in 202/
|
INSP-Final Inspection | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PART |
Troy Cobbley
|
|
|
Sprinkler work complete in the 07's and 08 apartments (south end). Tampers and flow switches tested. Need test papers.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 8/28/2018 | 8/29/2018 | 8/29/2018 | A | CANC |
Troy Cobbley
|
|
|
Could not perform this inspection due to fire alarm issues.
partial final Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2018 | 8/16/2018 | 8/16/2018 | A | PASS |
Troy Cobbley
|
|
|
overhead Hydro for the 1st, 2nd, 3rd and FDC passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 8/1/2018 | 8/2/2018 | 8/2/2018 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for soffits on levels 1 and 2 north side complete, approved for cover.
Full RTC Soffits Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler pendant spacing off from the drop ceilings/soffits in the rooms was verified in the first ans second floor apartments in the south half of the building.
Soffits Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/9/2018 | 7/9/2018 | 7/10/2018 | P | PART |
Troy Cobbley
|
|
|
The preliminary hydro test for the 1st, 2nd and 3rd floors passed. Another overhead hydro will be required when the drops have been cut.
|
INSP-Sprinkler Rough-in | 6/19/2018 | 6/20/2018 | 6/20/2018 | P | PASS |
Troy Cobbley
|
|
|
The piping in rooma 103, 104, 203, 204, 303, 304 is ok to cover. Two dry sidewalls still need to be installed and a cap put on the vertical shaft that the supply piping is in.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for tomorrow morning.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 6/18/2018 | 6/19/2018 | 6/19/2018 | P | PASS |
Troy Cobbley
|
|
|
The main underground supply line flush and the three breeze way supply flushes passed.
Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 6/15/2018 | 6/18/2018 | 6/18/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/13/2018 | 6/15/2018 | 6/15/2018 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Supply line flush | 6/13/2018 | 6/15/2018 | 6/14/2018 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/4/2018 | 6/5/2018 | 6/5/2018 | P | PASS |
Troy Cobbley
|
|
|
The piping in apartments 105, 205, 305, 106, 206 306 is ok for cover.
Robert Chambers is the contact for this inspection. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/4/2018 | 6/5/2018 | 6/4/2018 | A | CANC |
Troy Cobbley
|
|
|
Robert Chambers is the contact for the rough-in for the 24-plex. Thank you. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/1/2018 | 6/4/2018 | 6/4/2018 | P | CANC |
Troy Cobbley
|
|
|
Tenting is not done yet. To be rescheduled for tomorrow afternoon per Colton.
Colton Cox is the contact for this inspection. He is requesting a rough-in for the next 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 5/23/2018 | 5/29/2018 | 5/30/2018 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for Units 107, 207, 307, 108, 208, 308. A plan mod will be needed showing the changes in the remote area and pipe routing changes in the other Units.
Colton Cox is the contact for this rough-in on 6 units. Thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
|