INSP-Final Inspection | 5/13/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection complete.
George Jess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Supply line flush | 5/13/2019 | 5/14/2019 | 5/13/2019 | P | CANC |
Jim Page
|
|
|
George Jess is the contact. Thank you for your hard work! Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 5/10/2019 | 5/13/2019 | 5/13/2019 | P | FAIL |
Jim Page
|
|
|
Provide dry sidewall under combustible over-hang above west exit. Replace upright fire sprinkler head that was painted in the south room behind habitat exhibit. Replace exposed CPVC to steel pipe. Change upright head in restroom to the required pendant head. Replace pendant head that is in FACP room with an upright head as discussed.
George Jess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/6/2019 | 5/7/2019 | 5/7/2019 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans or small documents on site. I noted that several branchline restraints are missing, chrome heads are missing in the Croc Display, FDC is not connected, FDC is too high, PIV is too high, need tags and signage, need sprinkler protection under the stairs as discussed, outside alarm bell is not at the FDC, PIV tamper is not working correctly. ......ect.
George Jess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.
George Jess is the contact, he wants this to be a 200 lbs hydro only inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 4/22/2019 | 4/23/2019 | 4/23/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, will be rescheduled for a later date.
George Jess is the contact. He requests that this be a 200 lbs hydro only inspection. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler pipingt in otter and monkey exhibit complete, monkey and otter exhibit approved for cover.
George Jess is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|