Description
[Ash Street Townhomes - East Building]
The fire sprinkler scope of work consists of protecting a three level apartment building. The bottom and top level are a side feed design; the middle level is gridded. The project utilizes residential sprinklers and CPVC piping. There are floor control valves for each level.

[BLD17-04464]
There are three building permits under this Eplan (BLD17-04464, BLD17-04465 and BLD18-00248). Permit to build the East Building, a 23,742 sq ft multi-family R2 apartment building. This project consists of two 3-story, multi-family residential buildings and one single-story detached carport, and related site work. The two multi-family buildings are of Type VB construction and fully sprinklered with an NFPA 13 system for building area increase. Separate fire sprinkler and fire alarm permits are required as regulated by Boise Fire Department. **JAR**

Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.

• There are no AMM at this time.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/17/20196/17/20196/17/2019PPASS
DetailsJim Page
Final fire sprinkler inspection complete.

Johnathon Phone #: ###-####
INSP-Supply line flush3/13/20193/14/20193/14/2019ADONE
DetailsJim Page
Underground main line flush complete.

Johnathon Phone #: ###-####
INSP-Sprinkler Rough-in3/12/20193/12/20193/12/2019PPART
DetailsJim Page
Rough to cover iospection for overhead fire sprinkler piping/tenting in units 102 and 112 complete, approved for cover.

Jonathan Phone #: ###-####
INSP-Sprinkler Rough-in2/26/20192/27/20192/27/2019APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/tenting/insulation complete in units 106, 108, 110, 202 and 204, approved for cover.

johnathon Phone #: ###-####
INSP-Sprinkler Rough-in2/22/20192/25/20192/25/2019AFAIL
DetailsJim Page
Insulation below the attic deflectors in numurous locations, insulation needs to be raised above the deflector around all of the atic heads to include truss pockets next along the upright protection.

Jonathan Phone #: ###-####
INSP-Sprinkler Rough-in2/8/20192/8/20192/8/2019APART
DetailsJim Page
Rough in inspection is complete, cover is not approved until the insulation is installed and a follow up inspection is performed to verify attic coverage is still correct.
INSP-Sprinkler Rough-in2/1/20192/1/20192/1/2019PCANC
DetailsTroy Cobbley
No city approved plans on site, no inspetion. Johnathon Phone #: ###-####