Information based on query as of Thursday, May 16, 2024.
Permit Information
Permit NumberFIR18-00566
StatusFinaled
Name APEX INTEGRATED SECURITY SOLUTIONS
Site Address 12311 W BRADDOCK DR
Project NameSpalding STEM Academy
Customer Number 
ePlanReviewYes
Description
Spalding STEM Academy - Existing Building Control Panel/Voice Evacuation Panel is being installed. This work is associated with building permit BLD18-01191. Plan modification 10-2-18. Change wall mount notification to ceiling mount. Add 57 more smoke detectors for door release. Plan modification 10-16-18. Modify design for door holder release. Some areas will use corridor full coverage instead of added detection at the corridor side of the door.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/27/201812/28/201812/28/2018APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection12/18/201812/18/201812/18/2018PCANC
DetailsTroy Cobbley
Not ready per Nathan and will be rescheduled.

Call prior to going Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
INSP-Conference12/6/201812/6/201812/6/2018PDONE
DetailsTroy Cobbley
Went over strobe spacing with the electrian. I noted several strobes that will need to be relocated or increased candella. I'm questioning the placement and function of smoke detector 81 in the Gymnasium.
INSP-Alarm Testing11/21/201811/21/201811/21/2018PDONE
DetailsTroy Cobbley
The low air switch has been replaced and tested. The strobe in Room 9 has been replaced and tested. The fire alarm system in the existing school is complete except for some of the doors do not swing shut when the door mag released. To final project the doors will need to be addressed, as-builts and the new portion of the school will need to be completed.

Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
INSP-Alarm Testing11/19/201811/20/201811/20/2018ADONE
DetailsTroy Cobbley
Today we tested the interconnection of the existing fire alarm devices with the new panel. All devices on the existing risers functioned except the "low air" pressure switch on the System #1 did not function. It will need to be replaced asap as discussed.

Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
INSP-Alarm Testing11/19/201811/19/201811/19/2018ADONE
DetailsTroy Cobbley
We tested the smoke detectors and notification devices today. All functioned except for the strobe in the back of Room 9. I also noted several doors that did not swing shut when the door mags released.

Phone #: 2088301311 >> Inspection requested via mobile web by Nathan Price
INSP-Alarm Testing11/16/201811/16/201811/16/2018PDONE
DetailsTroy Cobbley
For todays inspection I only verified device locations. I noted smoke detectors needing centered on the door on the classroom side. Per a later phone call from Lee these detectors are ok to be deleted as long as the distance from the header to the ceiling does not exceed 24". I also noted many strobes that are overspaced in nearly every classroom and atleast one in the main corridor. I noted that the communication means being used is not what is shown on the approved plans. As-builts will be required but possibly for plan mods.