INSP-Final Inspection | 5/9/2019 | 5/15/2019 | 5/15/2019 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, final fire sprinkler inspection is complete.
Austin Farnworth is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
need the interconnections with the fire alarm tested. Need ceiling at the ground floor north apartment repaired. All other areas the work appears complete.
Gerardo Arce is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/11/2018 | 12/12/2018 | 12/12/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for level 2 completed with anit-freeze, no pressure loss observed.
Gerarrdo is the contact and he would like a hydro on the 2nd floor. please. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2018 | 12/4/2018 | 12/4/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test for levels 1 and 3 witnessed, no pressure loss observed at riser gauges, hydro was completed with glycerine anitfreeze. Level 2 to be completed at a later date.
Gerarrdo is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 12/4/2018 | 12/4/2018 | 12/4/2018 | A | PART |
Jim Page
|
|
|
Tenting inspection complete for level 3, level 3 overhead fire sprinkler piping approved for cover. Where piping crosses breezeway freeze protection will be required, rough in will not be signed off until freeze protection is inspected.
|
INSP-Sprinkler Rough-in | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | PART |
Jim Page
|
|
|
Tenting inspection for overhead fire sprinkler piping on level 3, 2 north units complete, approved for cover, remaining units on level 3 still require tenting to be installed and inspected.
Gerarrdo is the contact. he would like a rough to cover on the 3rd floor. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 11/21/2018 | 11/26/2018 | 11/26/2018 | A | FAIL |
Jim Page
|
|
|
Cover material was installed before tenting inspection of fire sprinkler piping was complete, as noted before cover is not approved until tenting inspection is complete and passed, cover material installed needs to be removed on level 3 for tenting inspection to be performed correctly.
3rd floor and contact is Gerarrdo. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 10/26/2018 | 10/29/2018 | 10/29/2018 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on levels 1 and 2 complete, levels 1 and 2 approvbed for cover. Rough in inspection for level 3 complete, tenting still needs to be installed, level 3 not approved for cover.
Phone #: ###-#### Inspection requested via web by Stan Beus
|