Permit Number | FIR18-00765 |
Status | Finaled |
Name |
SHILO AUTOMATIC SPRINKLER CO
|
Site Address |
8485 S FEDERAL WAY
|
Project Name | TEFFCO WAREHOUSE SHELL BUILDIN |
Customer Number | |
ePlanReview | Yes |
Description |
[Federal Way Industrial Building]
The fire sprinkler scope of work consists of connection to the previously installed 8" dedicated underground fire service and install a new 1250 @130psi fire pump to supply the 3 new ESFR fire sprinkler systems, utilizing 6" and 4" mains with 2½” and 2" branch lines supplying 16.8k ESFR pendants to protect the 119,473 ft² core and shell building for rack or high pile storage up to 20 feet.
• This permit is for shell and core ONLY. There shall be NO occupancy under this permit.
Location on Plan - Warehouse
Commodity - Unknown (Core and Shell)
Classification - Group A Expanded
Storage Type (rack, solid pile, etc.) - Rack
Pallet Type (wood or plastic) - Wood
Aisle Width - 8’
Height of Storage - 20’
Ceiling Height - 40’
Encapsulated - No
Solid Shelves - No
Smoke and Heat Vents - No
Draft Curtain - No
In Rack Sprinklers - NO
Sprinkler Type - ESFR K=16.8
High Temperature Sprinklers Required - No
Applicable NFPA Section - T 17.2.3.1
Hydraulic Design Criterion - 52#, 3 rows of 4 sprinklers
Hose Stream Requirements - 250
[BLD18-00596]
This building is fire sprinklered in accordance with NFPA 13 with 60 ft yards for unlimited area. Permit for the construction of a new 117,432 sq. ft., 1-story concrete tilt-up shell building and associated site work. Scope of work includes: construction of slab on grade concrete foundation, concrete tilt up construction, construction of new steel bar-joist roof framing / steel pan deck, electrical, mechanical, plumbing. All work shall comply with the approved plans, DRH17-00143 and all applicable codes. Utilizes ANSI/ASHREA 90.1. Special Inspections Required, see form 310. A separate permit is required prior to occupying this structure and a separate racking permit is required if racks are installed over 8 feet in height. Separate permits will be required for the building fire protection systems, as regulated by the Fire Department. **JAR**
Alternative Materials and Methods:
This project includes approved code alternates to the following fire protection systems and/or building life safety systems. Please review the supplemental documents attached to this building permit case for details. Fire protection “shop drawings” shall include approved code alternate design.
• There are no AMM at this time.
|