INSP-Final Inspection | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been completed, final fire alarm inspection complete.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 3/6/2019 | 3/6/2019 | 3/6/2019 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection is complete provided the as-builts match the added work that was completed. Once as-builts are submitted, approved and matches completed work then permit can be finaled.
Looking to get T.C.O. submital for stairs threw 3rd to fourth are in Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 2/28/2019 | 3/1/2019 | 3/1/2019 | P | FAIL |
Jim Page
|
|
|
Inspection for rough in was failed, reference notes provided under rough in inspection.
Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2019 | 3/1/2019 | 3/1/2019 | A | FAIL |
Jim Page
|
|
|
Add head in closet on 5 as discussed. City approved drawings do not show stair opening between 3 and 4, no head under stairs, could not verify space under landing, appears to be a combustible concealed space. Close spaced sprinkler heads may be required between levels.
Rough to cover Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Final Inspection | 2/26/2019 | 2/28/2019 | 2/28/2019 | P | CANC |
Troy Cobbley
|
|
|
No rough-in inspection has been scheduled or performed. A rough-in inspection will need to be scheduled and ceiling tile removed for the inspection. Phone #: ###-#### Inspection requested via web by jeremiah robison
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2019 | 2/1/2019 | 2/1/2019 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping on levels 3, 4 and 5 witnessed, no pressure loss observed.
Floors 3,4, and 5 Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact.
5th floor Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2018 | 12/21/2018 | 12/20/2018 | A | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Matthew Lewis Inspection cancelled from web by: Matthew Lewis
|