INSP-Final Inspection | 2/11/2019 | 2/12/2019 | 2/12/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/7/2019 | 2/11/2019 | 2/11/2019 | P | FAIL |
Troy Cobbley
|
|
|
Need to have access to verify the insulation has been installed since the ceiling were put in.
Contact Leroy Anderson ###-#### 30 min prior to Fire Final start please.
Thank YOU Phone #: ###-#### Inspection requested via web by Scott Carter II
|
INSP-Sprinkler Rough-in | 1/3/2019 | 1/4/2019 | 1/4/2019 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but piping can not be covered until the barrier above the ceiling has been repaired/re-installed. One head in a corridor needs to be re-located to match plans and will be checked at the next inspection.
Please contact Brad Westbrook 30 mins prior inspection. Phone #: ###-#### Inspection requested via web by Teri Cruickshank
|
INSP-Sprinkler Rough-in | 1/2/2019 | 1/4/2019 | 1/3/2019 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Teri Cruickshank Inspection cancelled from web by: Teri Cruickshank
|
INSP-Sprinkler Rough-in/Hydro | 12/26/2018 | 12/27/2018 | 12/27/2018 | A | PASS |
Troy Cobbley
|
|
|
Piping in the two rooms that have been marked "ok" can be covered. I spoke to Leroy about the large note that if any ceiling exceed 10' then plan modifications will be needed.
rough to cover for sheet rock // Austin Phone #: ###-####
|