INSP-Final Inspection | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection complete.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 7/25/2019 | 7/25/2019 | 7/25/2019 | A | FAIL |
Jim Page
|
|
|
Irrigation system is not complete, irrigation will need to be completed to test water flow shutdown to irrigation when flow switch activates during fire sprinkler water flow.
Call James before heading out. Thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2019 | 5/3/2019 | 5/3/2019 | P | PASS |
Troy Cobbley
|
|
|
Corrections made. Tenting passed. Piping can be covered.
As Built Plans approved. Call James to coordinate Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2019 | 5/2/2019 | 5/2/2019 | P | FAIL |
Troy Cobbley
|
|
|
Provide missing sprinkler head in bay window of master bedroom or provide exception, sprinkler heads are overspaced from the ceiling transition edge in the Kitchen area, provide sprinkler coverage under the second floor walkway as discussed, fix tenting as discussed. See the city approved plans for locations. Also the hydro test failed due to visible loss of pressure on the guage.
|