INSP-Final Inspection | 6/13/2019 | 6/14/2019 | 6/14/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/10/2019 | 6/11/2019 | 6/11/2019 | P | PASS |
Troy Cobbley
|
|
|
The overhead hydro tests were witnessed with no visible loss on the guages.
|
INSP-Sprinkler Rough-in | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Troy Cobbley
|
|
|
Tenting inspection passed. Piping can be covered.
Pat Palmer is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/2/2019 | 4/3/2019 | 4/3/2019 | A | CANC |
Troy Cobbley
|
|
|
There is a "Fees Due Hold" on this permit. Fees need to be paid prior to an inspection. Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 4/1/2019 | 4/2/2019 | 4/2/2019 | P | FAIL |
Jim Page
|
|
|
Current tenting install will allow blow-in insulation to collect under piping, blocking the gap required for the radiant heat from the sheetrock, pocket between piping and sheetrock must be maintained for freeze prevention, cover is not approved.
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/29/2019 | 4/1/2019 | 4/1/2019 | A | FAIL |
Troy Cobbley
|
|
|
Tenting needs to be extended further beyond pendant head drops and I noted one hanger not mount to the structure.
Gabe Garduno is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 3/28/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has passed
Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|