Permit Information
Permit NumberFIR19-00215
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 11792 W KING ST
Project NameFairvew 24-Plex #11792
Customer Number 
ePlanReviewYes
Description
Shilo will install a new fire sprinkler system into the new 24-Plex per NFPA 13R, 2016, and the City of Boise. Underground permit FIR18-00698
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/21/20198/21/20198/21/2019PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection8/2/20198/5/20198/5/2019APART
DetailsTroy Cobbley
The second group (six) of apartments to the north of the central breeze sprinkler work is complete.

Gabe Garduno is the contact for this final inspection. We appreciate your help, thank you. Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection7/1/20197/2/20197/2/2019APART
DetailsTroy Cobbley
Todays inspection was just for the six north end apartments, two canopies need installed and one side wall adjusted as discussed.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/28/20196/28/20196/28/2019PCANC
DetailsJim Page
Inspection request needs to be coordinated with fire alarm vendor, alarm contractor has inspection scheduled for 01JULY2019, this request is cancelled.

Gabe Garduno is the contact for this final. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Final Inspection6/27/20196/28/20196/28/2019ACANC
DetailsJim Page
Could not final, fire alarms not ready, this request is cancelled.

Gabe Garduno is the contact. Thank you for all that you do! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in/Hydro6/11/20196/12/20196/12/2019ADONE
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed.

Gabe Garduno is the contact. This inspection is to be done in connection with an underground flush/hydro for 11783 W. Fairview at 10:00 AM, as well as an underground flush/hydro for this building. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in5/2/20195/3/20195/3/2019APASS
DetailsTroy Cobbley
The rough-in passed for the remaining piping for the south half of the buiding. Tenting passed. All piping can be covered.
INSP-Sprinkler Rough-in4/24/20194/25/20194/25/2019APART
DetailsTroy Cobbley
See the city approved plans for apartments marked on the north half of the building where piping is ok for cover.

Gabe Garduno is the contact. Thank you for the hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/23/20194/24/20194/24/2019AFAIL
DetailsTroy Cobbley
City approved plans not on site. We discussed cocerage under the exterior eave at the entrys. I deferred him to the designer and plan review.

Gabe Garduno is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/11/20194/12/20194/12/2019APART
DetailsTroy Cobbley
See the city approved plans for several locations on the second floor where piping is marked "ok" for cover. Plan mods are needed for pipe routing changes. Possible additional heads will be required due to soffits being added.

Gabe Garduno is the contact. He wants this to be a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
INSP-Sprinkler Rough-in4/9/20194/10/20194/10/2019APART
DetailsTroy Cobbley
Inspection was actually a conference about pipe covering in two rooms


Gabe Garduno is the contact. This inspection is for a partial rough-in. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus