INSP-Final Inspection | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for scope of work is complete.
Phone #: ###-#### Inspection requested via web by Matthew Lewis
|
INSP-Final Inspection | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | NR |
Jim Page
|
|
|
Area of work is not complete, finish item at bottom of escalator not in place, sprinkler head is to far down from deck without finsh material installed, project not ready for final inspection.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for scope of work complete.
Jogn Phone #: ###-####
|
INSP-Sprinkler Rough-in | 9/24/2019 | 9/25/2019 | 9/25/2019 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler pipng above hardlids complete, hardlids approved for cover.
TOM Phone #: ###-####
|