Permit Information
Permit NumberBLD13-03405
StatusFinaled
Name ESI
Site Address 1011 S LA POINTE ST
Project NameLA POINTE
Customer Number 
ePlanReviewYes
Description
(LA POINTE - FORMERLY CALLED BOISE HEIGHTS APARTMENTS) Fire sprinklers used for area increase, story increase, and for fire area. To construct a 5 story garage and residential apartment building (one story garage at grade and 4 stories of residential apartments above). The 1st story was constructed under early start permit BLD14-00377. The garage and adjacent areas will have a total floor area of about 72,725 square feet and will be of Type I-A construction. An office area will also be located on the 1st story next to the garage and will have a floor area of about 2,448 square feet. It will be of Type V-A construction and will be separated from the garage by a 3-hr fire wall. A 3-hr horizontal assembly will separate the garage from the apartment building above. Each story of the apartment building will have a total floor area of about 42,646 square feet. A 2-hr fire wall will separate the apartment building into 2 “buildings” for building area reasons and to provide a horizontal exit. There will be a total of 131 apartment units (36 four bedroom units, 4 three bedroom units, 90 two bedroom units, and 1 one bedroom/model unit). There will be a total of 337 bedrooms. All apartment units are required to comply as Type B dwelling units. Three apartment units are required to comply as Type A dwelling units. A 1,187 square foot fitness building will also be constructed above the garage under this permit. It will have a 732 square foot exercise room. A 2,235 square foot elevated pool deck will be constructed next to the fitness building. Required Special Inspections include soils, concrete reinforcing steel including prestressing tendons, concrete, welding, masonry, spray applied fire-proofing, and wood shear walls. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy  8/28/2015 DONE
BLD-Final8/26/20158/27/20158/27/2015PPASS
DetailsDave Hannah
Tower 4 and building final Phone #: ###-#### Inspection requested via web by Tim Toups
FIRE-Final Inspection8/26/20158/27/20158/27/2015PPASS
DetailsThomas Walsh
Final fire and life satey inspection for Tower 4 portion of the building, including the east side parking garage. Tested exit signs and emergency lights for these areas. A few exit signs were added to improve locations of exits in the garage. EM lighting tested OK.
EVAC plans were installed in all units for this portion of the building. Fire extinguisers are installed. Fire sprinklers and fire alarm systems have been finaled. Areas of Refuge call systems(all elevators) were tested and all answered by lobby staff, or by monitoring company.
Zoning Approval8/26/20158/26/20158/26/2015 DONE
DetailsAndrea Tuning
BLD-Other8/19/20158/20/20158/20/2015PPART
DetailsDave Hannah
Life Safety for all of tower 3 and tower 4 corridors for egress. Phone #: ###-#### Inspection requested via web by Tim Toups ok to occ tower #3
FIRE-Final Inspection8/19/20158/20/20158/20/2015APART
DetailsThomas Walsh
Fire and Life-Safety inspection for use of Towers 3 & 4 corridors and stair 2 to egress these towers down to grade. Tested exit signs and EM lights for all floors - Tested OK. Two exit signs need to be added between Towers 2 & 3 at floors 2 and 3.
All stairwell doors and unit doors opening into the fire rated corridors for these two towers (all floors) need to be maintained closed and latched, in order to maintain the integrity of the corridor. GC talked to security to help maintain. Inspection of units for Tower 4 not completed yet.
BLD-Final8/18/20158/18/20158/20/2015PPART
DetailsDave Hannah
Fitness center Phone #: ###-#### Inspection requested via web by Carl Benjamin ok to occ
BLD-Other8/17/20158/18/20158/19/2015PNR
DetailsDave Hannah
Life safety for balance of tower 3 Phone #: ###-#### Inspection requested via web by Carl Benjamin
FIRE-Final Inspection8/17/20158/18/20158/18/2015ACANC
DetailsThomas Walsh
Fire life-safety inspection was called in for Tower 3 portion of the building, however for use and access to Tower 3 units, residents would have to have egress through Tower 4 corrdior to access th e southeast stairway. Tower 4 corridor is not complete yet, as most unit doors, which are fire/smoke assemblies, do not have their door hardware installed. Therefore Tower 4 corrdior is not complete, and Tower 3 units cannot be used until it is completed.
BLD-Other8/13/20158/14/20158/17/2015PPART
DetailsDave Hannah
Life Safety for Unit 514 ; 515 in tower 3 Phone #: ###-#### Inspection requested via web by Carl Benjamin
FIRE-Final Inspection8/14/20158/14/20158/14/2015PPART
DetailsThomas Walsh
Inspection to add two units on the fifth floor to TCO area (units 514 and 515).
Fire sprinklers and fire alarm devices inspected and OK for these units. A temp. wall and door assembly to be constructed in the corridor to prevent residents from going into construction zone.
BLD-Framing/Rough-in7/15/20157/16/20157/16/2015APASS
DetailsDave Hannah
Elevator # 2 lobby soffits at each floor Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover7/13/20157/13/20157/13/2015APASS
DetailsDave Hannah
Tower 4 shaft wall Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference7/9/20157/10/20157/13/2015APART
DetailsDave Hannah
Dave, please be on site between 10 and 11am. Thank you Phone #: ###-#### Inspection requested via web by Tim Toups
FIRE-Final Inspection7/9/20157/10/20157/10/2015APART
DetailsThomas Walsh
TCO inspection for Towers 1 and 2, including exit signs, emergency lights, fire extinguishers, etc. for partial occupancy for this portion of the building. Fire sprinklers and fire alarm system testing for this area is completed. A temporary one-hour wall and fire door separates towers &/2 from towers 3&4. Unit EVAC plans are currently being made up and are pending.
OK to occupy Towers 1 & 2 - all floors.
BLD-Conference7/9/20157/9/20157/10/2015PPEND
DetailsDave Hannah
Dave, this is a pre-walk inspection for tower 1 ; 2. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover7/6/20157/7/20157/7/2015APASS
DetailsDave Hannah
No show for Monday, this is a re-schedule. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover7/6/20157/6/20157/7/2015PCANC
DetailsDave Hannah
Tower 4, podium level unit soffits and corridors. Phone #: ###-#### Inspection requested via web by Tim Toups
Zoning Approval Temp7/7/20157/7/20157/7/2015 DONE
DetailsAndrea Tuning
Temporary occupancy is provided to 27 units in Tower 1 and 39 units in Tower 2. This temporary occupancy is good for 90 days. Towers 3 adn 4 are not given any type of occupancy at this time.
BLD-Conference7/2/20157/2/20157/6/2015PPEND
DetailsDave Hannah
Dave, can you come between 10 - 12? Call if you have questions. Thanks Phone #: ###-#### Inspection requested via web by Tim Toups
FIRE-Final Inspection7/1/20157/2/20157/2/2015APART
DetailsThomas Walsh
Fire life/Safety inspection for the area where they want TCO, including the podium level units (5 total) along the west/south corner, including the parking garage on the north side only. Egress, emerg. lighting, fire extinguishers, were inspected for these areas. Fire alarm and fire sprinklers for these areas have also been.Found two emergency lights that need repair - one exit sign above the main door in the lobby, and one emerg. light on the southwest satirwell exterior. Evac signs are needed prior tooccupancy.
BLD-Conference7/1/20157/2/20157/2/2015ADONE
DetailsDave Hannah
Dave, can you come between 10 - 12? Call if you have questions. Thanks Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference7/1/20157/1/20157/2/2015ADONE
DetailsDave Hannah
See Carl Benjamin Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference6/30/20156/30/20156/30/2015PPASS
DetailsDave Hannah
Pool deck framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference6/26/20156/29/20156/29/2015ADONE
DetailsDave Hannah
With Carl Benjamin Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference6/26/20156/26/20156/29/2015PDONE
DetailsDave Hannah
Please see Carl Benjamin for conference. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover6/25/20156/26/20156/26/2015APASS
DetailsDave Hannah
4th ; 5th floor corridor soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection6/24/20156/24/20156/25/2015PPASS
DetailsDave Hannah
Lobby Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance6/19/20156/19/20156/19/2015APASS
DetailsMike Jordan
Maintenance room 118, stair well #2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover6/16/20156/16/20156/16/2015APASS
DetailsDave Hannah
3rd floor tower 4 soffits. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover6/12/20156/15/20156/16/2015PNR
DetailsDave Hannah
3rd floor tower 4 soffits. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance6/12/20156/15/20156/16/2015PPASS
DetailsDave Hannah
Tower 2 trash chute room at garage Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance6/12/20156/12/20156/12/2015PNR
DetailsDave Hannah
3rd floor tower 4 unit soffits and garage soffit at south end. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference6/8/20156/10/20156/11/2015APASS
DetailsDave Hannah
4th floor tower 4 soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover6/5/20156/5/20156/5/2015PPASS
DetailsDave Hannah
5th floor Tower 4 corridor soffit Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover6/4/20156/5/20156/5/2015ANR
DetailsDave Hannah
Tower 4 soffits and fire caulk at 2 hour wall Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance5/28/20155/28/20155/28/2015PPASS
DetailsMike Jordan
Garage soffit ( North west section) and stair well # 2. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in5/27/20155/27/20155/27/2015PPASS
DetailsMike Jordan
Tower 1, Two hour mech shaft Phone #: ###-#### Inspection requested via web by Tim Toups. Tower 1 mech shaft to bottom of roof deck ok for cover. Tower 4, floors 1 to 4 mech. shaft next to elvator, corridor side to bottom of floor decks ok.
BLD-Framing/Rough-in5/22/20155/26/20155/26/2015APASS
DetailsMike Jordan
Tower 1, 2 hour Mech. shaft Phone #: ###-#### Inspection requested via web by Tim Toups. Verified 2hr. mech. shaft construction to bottom of roof deck.
BLD-Framing/Rough-in5/22/20155/26/20155/22/2015PCANC
DetailsJim Storey
Two hour Mech shafts in tower 1 & 2 Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Conference5/21/20155/21/20155/22/2015PDONE
DetailsDave Hannah
Fire egress conference Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover5/20/20155/21/20155/21/2015PPASS
DetailsDave Hannah
Lobby lids, trash chutes. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in5/19/20155/20/20155/20/2015APASS
DetailsDave Hannah
Fitness center framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover5/18/20155/18/20155/18/2015PNR
DetailsDave Hannah
Podium level tower 3 unit soffits, trash chute tower 2. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover5/14/20155/15/20155/15/2015APASS
DetailsMike Jordan
Podium level corridor and unit soffits, stair tower 1 fire caulking Phone #: ###-#### Inspection requested via web by Tim Toups
Plan Reviewer's activity  5/14/2015 DONE
Based on an Email from the Architect, name changed to La Pointe.
BLD-Wall cover5/13/20155/13/20155/13/2015APASS
DetailsDave Hannah
3rd floor Tower 3 unit soffits and corridor Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover5/8/20155/11/20155/11/2015APASS
DetailsDave Hannah
5th floor tower 3 unit soffits Phone #: ###-#### Inspection requested via web by Tim Toups 4th floor also
BLD-Wall cover5/7/20155/8/20155/8/2015APART
DetailsDave Hannah
4th ; 5th floor Tower 3 corridor ; unit soffits Phone #: ###-#### Inspection requested via web by Tim Toups corridors ok but rooms not ready
BLD-Wall cover5/7/20155/7/20155/8/2015PPASS
DetailsDave Hannah
Soffit framing in tower 1 at elevator 3 lobbies, soffit framing tower 3 corridors. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover5/7/20155/7/20155/7/2015ANR
DetailsDave Hannah
Soffit framing at elevator #3 lobbies all floors. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference5/5/20155/6/20155/6/2015APASS
DetailsDave Hannah
Inspection request for the Ceiling Grid in the Parking Garage Level 1. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference5/4/20155/4/20155/4/2015PPEND
DetailsDave Hannah
Review of mechanical shafts for 2hr rating at tower 1 ; 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/30/20155/1/20155/1/2015PPASS
DetailsDave Hannah
Tower 4 elevator #2 mech shaft Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference4/29/20154/30/20155/1/2015PPASS
DetailsDave Hannah
Review 2 hour shaft at roof penetration of trash chute ; mech chase Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover4/28/20154/29/20154/29/2015APASS
DetailsDave Hannah
Exterior shear at east elevation. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/28/20154/29/20154/29/2015APASS
DetailsDave Hannah
Common area on podium level Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/27/20154/28/20154/28/2015APASS
DetailsDave Hannah
Common area at Podium level Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/27/20154/27/20154/28/2015PPASS
DetailsDave Hannah
Elevator # 2 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference4/23/20154/24/20154/24/2015APASS
DetailsDave Hannah
Inspection request for Tower 4, 2nd and 3rd floor insulation. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/22/20154/23/20154/24/2015PPEND
DetailsDave Hannah
Inspection request for the Shaft Wall openings at Towers 1, 2 and 3. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/22/20154/24/20154/23/2015PCANC
DetailsJim Storey
Inspection request for Tower 4, Floors 2 and 3 Insulation East Elevation. Phone #: ###-#### >> Inspection requested via web by Carl Benjamin Inspection cancelled from web by: Carl Benjamin
BLD-Conference4/21/20154/22/20154/22/2015APASS
DetailsDave Hannah
This inspection request is for an AM preferably at 11:30AM. Tower 4, East Elevation at 2nd and 3rd floor for Framing and Energy Seal. Tower 4, East Elevation 5th floor Insulation. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/20/20154/21/20154/21/2015APASS
DetailsDave Hannah
Inspection request for Tower 4, East elevation 4th floor Framing and Energy Seal. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Wall Bracing4/21/20154/21/20154/21/2015APASS
DetailsDave Hannah
Tower 3 East elevation Exterior Shear Nailing Inspection. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/16/20154/17/20154/21/2015APASS
DetailsDave Hannah
Tower 4, Floors 4 and 5 for Framing and Energy code East Elevation only. Tower 4, Floors 2 and 3 Insulation at West Elevation only. Thank you. Phone #: ###-#### Inspection requested via web by Carl Benjamin enery only ok to cover
BLD-Conference4/17/20154/20/20154/21/2015ANR
DetailsDave Hannah
This inspection is really for the PM with the original scheduled inspection but the system will not allow for an added item. Tower 4, East Elevation 4th and 5th Floors for Energy Code and Framing for Insulation cover. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/17/20154/20/20154/21/2015PDEFR
DetailsDave Hannah
Tower 3 East elevation Exterior Shear Nailing Inspection. Phone #: ###-#### Inspection requested via web by Carl Benjamin
BLD-Conference4/20/20154/21/20154/20/2015PCANC
DetailsJim Storey
Inspection request for Tower 4, 4th floor East elevation Framing and Energy Seal. Phone #: ###-#### >> Inspection requested via web by Carl Benjamin Inspection cancelled from web by: Carl Benjamin
BLD-Ceiling Grid Inspection4/15/20154/16/20154/16/2015APASS
DetailsDave Hannah
5th floor tower 2 unit soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/15/20154/16/20154/16/2015APASS
DetailsDave Hannah
Stair tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/15/20154/16/20154/16/2015APART
DetailsDave Hannah
Elevator and stair #2 Phone #: ###-#### Inspection requested via web by Tim Toups ok to insulate needs to add straping
BLD-Ceiling Grid Inspection4/16/20154/16/20154/16/2015APASS
DetailsDave Hannah
4th ; 5th floor tower 1 ; 2 corridor soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection4/14/20154/15/20154/16/2015APART
DetailsDave Hannah
4th ; 5th floor tower 1 ; 2 corridor soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/15/20154/15/20154/16/2015PPART
DetailsDave Hannah
4th ; 5th floors tower 4 west half Phone #: ###-#### Inspection requested via web by Tim Toups 5th floor west side ok
BLD-Framing/Rough-in4/14/20154/15/20154/15/2015APASS
DetailsDave Hannah
Podium ; 3rd floor tower 4 west framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection4/15/20154/15/20154/15/2015PCANC
DetailsJim Storey
5th floor tower 2 Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Ceiling Grid Inspection4/11/20154/13/20154/14/2015ACANC
DetailsDave Hannah
Unit soffits, 3rd floor tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Other4/14/20154/14/20154/14/2015ANR
DetailsDave Hannah
Unit soffits, 3rd floor tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover4/13/20154/14/20154/14/2015APASS
DetailsDave Hannah
Tower 1 mech. shaft Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/11/20154/13/20154/13/2015APASS
DetailsDave Hannah
Lobby insulation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/11/20154/13/20154/13/2015APASS
DetailsDave Hannah
5th ; 4th floor west units of tower 4 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/8/20154/9/20154/9/2015APASS
DetailsDave Hannah
Tower 3 POD units at Podium level Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/8/20154/9/20154/9/2015APASS
DetailsDave Hannah
Lobby framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection4/6/20154/7/20154/7/2015PPASS
DetailsDave Hannah
4th floor tower 2 soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/6/20154/7/20154/7/2015PPASS
DetailsDave Hannah
3rd ; 4th floor POD units Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover4/3/20154/6/20154/6/2015APASS
DetailsDave Hannah
5th floor tower 2 soffits, 5th floor tower 3 POD units. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/3/20154/3/20154/3/2015PPASS
DetailsDave Hannah
Tower 3 POD unit framing of 3rd floor ; podium Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/2/20154/3/20154/3/2015APASS
DetailsDave Hannah
Tower 3 POD framing at 2nd ; 3rd floors Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection4/1/20154/2/20154/2/2015ANR
DetailsDave Hannah
5th floor tower 2 soffits Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance4/1/20154/1/20154/1/2015APART
DetailsDave Hannah
Tower 3 POD all floors Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance3/30/20153/31/20154/1/2015PPASS
DetailsDave Hannah
Tower 3 POD ceilings Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in4/1/20154/1/20154/1/2015APASS
DetailsDave Hannah
4th ; 5th floor POD unit framing. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/31/20153/31/20153/31/2015PPASS
DetailsDave Hannah
Stair tower # 1, Lobbies at Elevator # 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference3/26/20153/26/20153/27/2015PDONE
DetailsDave Hannah
Lobby wall types and fire rating Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/25/20153/26/20153/26/2015ACANC
DetailsDave Hannah
Stair #1 framing Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Energy code compliance3/23/20153/24/20153/24/2015APASS
DetailsDave Hannah
Podium level tower 3 insulation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall Bracing3/20/20153/23/20153/23/2015APASS
DetailsDave Hannah
Exterior shear on elevator # 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance3/19/20153/20/20153/20/2015APASS
DetailsDave Hannah
3rd floor tower 3 insulation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/19/20153/20/20153/20/2015APASS
DetailsDave Hannah
Exterior shear tower 2 ; 3 east elevation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/18/20153/19/20153/19/2015APASS
DetailsDave Hannah
Tower 2 north east elevation exterior shear, tower 3 podium level framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/17/20153/18/20153/19/2015APASS
DetailsDave Hannah
Framing at Lobby for pre-rock behind duct work. Framing at tower 3 podium level. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/13/20153/16/20153/16/2015APASS
DetailsDave Hannah
3rd floor tower 3 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance3/13/20153/16/20153/16/2015APASS
DetailsDave Hannah
4th floor tower 3 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/12/20153/13/20153/13/2015APASS
DetailsDave Hannah
Exterior shear at Fitness center ; south elevation of tower 4 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance3/11/20153/12/20153/13/2015PPASS
DetailsDave Hannah
5th floor tower 3 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/11/20153/12/20153/12/2015APASS
DetailsDave Hannah
Tower 3 trash shoot framing Phone #: ###-#### Inspection requested via web by Tim Toups
FIRE-Conference3/10/20153/11/20153/11/2015ACANC
DetailsTroy Cobbley
fire blocking foam - Carl Phone #: ###-####
BLD-Framing/Rough-in3/10/20153/10/20153/11/2015PPASS
DetailsDave Hannah
4th floor tower 3 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/10/20153/10/20153/10/2015ANR
DetailsDave Hannah
4th floor tower 3 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/9/20153/9/20153/10/2015PPASS
DetailsDave Hannah
Exterior shear, east elevation, south end of tower 4. Elevator #1 wall framing. 5th floor tower 3, unit framing. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/3/20153/3/20153/6/2015PPASS
DetailsDave Hannah
Interior shear at 2 hour wall between towers 3 ; 4 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in3/4/20153/5/20153/5/2015APASS
DetailsDave Hannah
Exterior store front shear at stair #1. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance3/4/20153/5/20153/5/2015APASS
DetailsDave Hannah
Insulation at 2 hour wall dividing tower 2 ; 3, insulation at 5th floor tower 3 roof drains. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/27/20153/3/20153/4/2015APART
DetailsDave Hannah
Exterior shear at towers 3 ; 4 west elevation Phone #: ###-#### Inspection requested via web by Tim Toup section by bldg split two panels all 4 levels
BLD-Energy code compliance2/26/20152/26/20152/27/2015PPASS
DetailsDave Hannah
Insulation 2nd floor tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/26/20152/26/20152/27/2015PPASS
DetailsDave Hannah
3rd floor tower 1 unit soffits at fire dampers Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/25/20152/26/20152/26/2015ANR
DetailsDave Hannah
3rd floor tower 1 unit soffits at fire dampers Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/24/20152/26/20152/26/2015ANR
DetailsDave Hannah
Insulation 2nd floor tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/25/20152/25/20152/26/2015APART
DetailsDave Hannah
2,3,4, ; 5th floor Trash chutes in tower 2, 2 hr wall at stair # 1 Inspection requested via web by Tim Toups needs to rock room side in floor space of trash chutes . back of stair tower wall ok.
BLD-Conference2/23/20152/24/20152/24/2015APASS
DetailsDave Hannah
Review handrail requirements at concrete ramp in garage. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/20/20152/23/20152/24/2015APASS
DetailsDave Hannah
Framing rough in and NFPA code podium level tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups ok to insulste
BLD-Wall cover2/19/20152/20/20152/20/2015APASS
DetailsJim Storey
Drywall at corridor lids in towers 3 ; 4 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/19/20152/20/20152/20/2015APASS
DetailsJim Storey
3rd floor tower 2 insulation at ceiling only Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover2/19/20152/19/20152/19/2015PNR
DetailsJim Storey
Drywall at corridor lids in towers 3 ; 4 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/18/20152/19/20152/19/2015PNR
DetailsJim Storey
3rd floor tower 2 insulation at ceiling only Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover2/17/20152/18/20152/18/2015APASS
DetailsJim Storey
Exterior shear nail off at Lobby. Phone #: ###-#### Inspection requested via web by Tim Toups to podem level ok.
BLD-Framing/Rough-in2/17/20152/18/20152/18/2015APASS
DetailsJim Storey
Framing at patio decks of tower 3 ; 5 Phone #: ###-#### Inspection requested via web by Tim Toupsdecks ok
BLD-Wall cover2/17/20152/18/20152/18/2015APASS
DetailsJim Storey
Drywall patch backs at fire dampers 5th floor tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/17/20152/18/20152/18/2015APASS
DetailsJim Storey
3rd floor tower 2 ceiling insulation Phone #: ###-#### Inspection requested via web by Tim Toupsair seal ok
BLD-Wall cover2/16/20152/17/20152/17/2015ANR
DetailsJim Storey
Exterior shear nail off at Lobby. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/13/20152/17/20152/17/2015ADEFR
DetailsJim Storey
Framing at patio decks of tower 3 ; 4 Phone #: ###-#### Inspection requested via web by Tim Toups out of time
BLD-Energy code compliance2/13/20152/17/20152/17/2015APASS
DetailsJim Storey
3rd floor tower 2 , NFPA code at ceiling. Phone #: ###-#### Inspection requested via web by Tim Toups air seal to i joist ok
BLD-Wall cover2/12/20152/13/20152/13/2015APASS
DetailsJim Sly
5th floor tower 2 lid at Pod 543 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Other2/12/20152/13/20152/13/2015APASS
DetailsJim Sly
Roof sheathing of fitness center Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/12/20152/13/20152/13/2015APART
DetailsJim Sly
Exterior shear west elevation of tower 3 Phone #: ###-#### Inspection requested via web by Tim Toups Ext. Shear Nailing......OK
BLD-Wall cover2/10/20152/11/20152/11/2015APASS
DetailsJim Storey
3rd floor tower 2 framing/rough-in Phone #: ###-#### Inspection requested via web by Tim Toups ok to insulate exterior walls only/ exterior sheer nailling north wall. 5 th floor damper ok to instal gyp ceilling tower 1#
BLD-Framing/Rough-in2/10/20152/10/20152/10/2015PDEFR
DetailsJim Storey
Exterior shear panel nail off N/E elevation of tower 2.

Also need correction notice from yesterdays inspection at 4th and 5th floor dryer ducts. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in2/7/20152/9/20152/9/2015PPART
DetailsJim Storey
3rd floor tower 2 framing/rough-in Phone #: ###-#### Inspection requested via web by Tim Toups ok to insulate exterior walls only
BLD-Energy code compliance2/6/20152/6/20152/6/2015PPASS
DetailsJim Storey
Reinspect 4th floor tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance2/4/20152/5/20152/5/2015PPASS
DetailsJim Storey
Insulation at 4th ; 5th floors of tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups east/north corner ok
BLD-Ceiling Grid Inspection2/4/20152/5/20152/5/2015APASS
DetailsJim Storey
Re-inspection at 5th floor tower 1 units Phone #: ###-#### Inspection requested via web by Tim Toups ok to cover drops
Case Summary (BLD)  2/5/2015  
BLD-Framing/Rough-in2/3/20152/4/20152/4/2015APASS
DetailsJim Storey
Lobby framing Phone #: ###-#### Inspection requested via web by Tim Toups ok for exteriot walls to cover.
BLD-Framing/Rough-in2/3/20152/3/20152/3/2015PPART
DetailsJim Sly
4th ; 5th floor east end of tower 2 Pod 440 ; 540 Phone #: ###-#### Inspection requested via web by Tim Toups
All OK including fire stopping at tub drains. Need fix for missed bearing points of trusses above door headers......can see from corridoor side.
BLD-Conference1/30/20152/2/20152/2/2015ANR
DetailsJim Storey
Intumescent Paint at structural steel Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection2/2/20152/2/20152/2/2015AFAIL
DetailsJim Storey
5th floor tower 1 drop ceilings Phone #: ###-#### Inspection requested via web by Tim Toups c/n on site
BLD-Framing/Rough-in1/30/20152/2/20152/2/2015APASS
DetailsJim Storey
north exterior sheer ok to covergrid xx to i/ lobby roof and paripet ok to cover. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Ceiling Grid Inspection1/30/20151/30/20151/30/2015PFAIL
DetailsJim Storey
Fire caulking and drywall patch back in tower 1, 5th floor Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance1/29/20151/30/20151/30/2015APASS
DetailsJim Storey
5th floor tower 2 insulation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/29/20151/30/20151/30/2015APART
DetailsJim Storey
Exterior shear nailing of south elevation tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/29/20151/30/20151/30/2015APASS
DetailsJim Storey
4th floor tower 2 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance1/28/20151/29/20151/29/2015PPASS
DetailsJim Storey
5th floor tower 2 insulation Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/28/20151/28/20151/29/2015PPART
DetailsJim Storey
Exterior shear nailing of south elevation tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/26/20151/27/20151/27/2015APASS
DetailsJim Storey
5th floor tower 2 framing Phone #: ###-#### Inspection requested via web by Tim Toups as noted on site
BLD-Other1/26/20151/27/20151/27/2015APASS
DetailsJim Storey
Mineral wool and fire caulking at stair # 3 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/22/20151/23/20151/23/2015PPASS
DetailsJim Storey
Tower 4 roof and parapets, tower 2 patio decks, Lobby roof . Phone #: ###-#### Inspection requested via web by Tim Toups north exterior decks ok/ south roof ok w paripets ok to cover
BLD-Conference1/22/20151/23/20151/22/2015PCANC
DetailsJim Storey
Tower 4 roof sheathing and parapets, tower 1 patio decks, Lobby roof and parapets. Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Framing/Rough-in1/21/20151/22/20151/22/2015ANR
DetailsJim Storey
Patio deck framing tower 2, Roof sheathing @ Lobby and tower 4, P-3 parapets. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/19/20151/20/20151/20/2015PPASS
DetailsJim Storey
Exterior shear east elevation of tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups grid g 2 thru 5 exterior sheer south ok/grid 11 2 thur 5 sheer ok / corridor ceilling rock ok tower 2 2 thur 5 floors.
BLD-Conference1/14/20151/15/20151/15/2015PPASS
DetailsJim Storey
Tower 3 parapets, roof sheathing east end tower 2 and elevator #1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover1/13/20151/14/20151/14/2015APART
DetailsJim Storey
stair 3# firestopping first floor/ conf on mailboxes wip ok fs/ mailbox design ok
BLD-Energy code compliance1/12/20151/13/20151/13/2015PPASS
DetailsJim Storey
Stair/elevator shaft # 3 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in1/7/20151/8/20151/8/2015APASS
DetailsJim Storey
Framing tower at elevator ; stair #3 shafts Phone #: ###-#### Inspection requested via web by Tim Toups frame ok
BLD-Framing/Rough-in1/5/20151/6/20151/6/2015PPASS
DetailsJim Storey
Tower 3 roof sheathing Phone #: ###-#### Inspection requested via web by Tim Toups tower 2 and 3 roof deck ok to cover.
BLD-Energy code compliance12/30/201412/31/201412/31/2014PPASS
DetailsJim Storey
Balance of podium level in tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in12/29/201412/30/201412/30/2014APART
DetailsJim Storey
Framing 5th floor corridor of tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups c/n 5th floor rfi to corridor need detail for 1 hr protection elavation and wide flange beam.
BLD-Energy code compliance12/29/201412/30/201412/30/2014APASS
DetailsJim Storey
Insulation of 2nd floor tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups first 3 rms south to north.ok
BLD-Framing/Rough-in12/22/201412/23/201412/23/2014PPASS
DetailsJim Storey
Tower 3 parapet framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in12/22/201412/23/201412/23/2014APASS
DetailsJim Storey
2nd floor of tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in12/16/201412/16/201412/16/2014PPASS
DetailsJim Storey
3rd floor tower 1 framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Wall cover12/12/201412/15/201412/15/2014ADONE
DetailsJim Storey
5th floor tower 1 drywall. Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance12/11/201412/12/201412/12/2014APASS
DetailsJim Storey
4th floor tower 1 insulation Phone #: ###-#### Inspection requested via web by Tim Toups up to 36/37
BLD-Framing/Rough-in12/9/201412/10/201412/10/2014PPASS
DetailsJim Storey
4th floor of tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
FIRE-Sprinkler Rough-in12/10/201412/10/201412/10/2014ADONE
DetailsForrest France
Rough-in at tower one 5th floor 531-537
BLD-Energy code compliance12/9/201412/9/201412/9/2014PPASS
DetailsJim Storey
5th floor phase 1 ok
BLD-Energy code compliance12/9/201412/10/201412/9/2014ACANC
DetailsJim Storey
Insulation 5th floor tower 1(north end) Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Energy code compliance12/8/201412/9/201412/9/2014APASS
DetailsJim Storey
Unit insulation at tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance12/8/201412/8/201412/8/2014PPART
DetailsJim Storey
Insulation/ Pre- drywall Phone #: ###-#### Inspection requested via web by Tim Toups 36 an 37 ok
BLD-Energy code compliance12/4/201412/8/201412/8/2014ANR
DetailsJim Storey
Insulation/ Pre- drywall Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Energy code compliance12/4/201412/5/201412/5/2014APASS
DetailsJim Storey
Fire caulking at tub/shower enclosures Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference12/4/201412/5/201412/5/2014APASS
DetailsJim Storey
Overview of today''s insp. w/Dave H. Phone #: ###-#### Inspection requested via web by Tim Toups 5th floor ok to cover walls
BLD-Framing/Rough-in12/2/201412/4/201412/4/2014APART
DetailsDave Hannah
Framing inspection tower 1 (5th floor only) Phone #: ###-#### Inspection requested via web by Tim Toups ok to insulate
FIRE-Alarm Testing12/1/201412/2/201412/3/2014ADONE
DetailsForrest France
This request is for a Courtesy Fire Alarm Inspection. Thank you. Phone #: ###-#### Inspection requested via web by Carl Benjamin
FIRE-Conference12/2/201412/3/201412/3/2014ADONE
DetailsForrest France
BLD-Conference11/25/201411/25/201411/28/2014PCANC
DetailsForrest France
Courtesy Fire Alarm with Forrest France

Thank you, Phone #: ###-#### >> Inspection requested via web by Carl Benjamin Inspection cancelled from web by: Tim Toups
BLD-Conference11/25/201411/26/201411/28/2014APASS
DetailsDave Hannah
Patio soffit framing for pre-rock installation in tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in11/21/201411/24/201411/22/2014ACANC
DetailsJim Storey
Final framing at all floors of tower 1 Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Carl Benjamin
BLD-Framing/Rough-in11/19/201411/21/201411/21/2014AFAIL
DetailsJim Storey
Final framing at all floors of tower 1 Phone #: ###-#### Inspection requested via web by Tim Toups c/n for 5 and 4 tower 1
BLD-Conference11/17/201411/17/201411/17/2014PPASS
DetailsJim Storey
Review fire rating requirements behind shower enclosures Phone #: ###-#### Inspection requested via web by Tim Toups double studs ok inlew of gyp corridor rm side
BLD-Framing/Rough-in11/10/201411/12/201411/12/2014APASS
DetailsJim Storey
Tower 1 parapet framing ; roof sheathing Phone #: ###-#### Inspection requested via web by Tim Toups exterior tower 1 ok/ roof tower 2 ok
BLD-Framing/Rough-in11/7/201411/10/201411/10/2014PPASS
DetailsJim Storey
Parapet ; roof sheathing on tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference11/10/201411/12/201411/10/2014ACANC
DetailsJim Storey
Tower 2 parapet framing Phone #: ###-#### >> Inspection requested via web by Tim Toups Inspection cancelled from web by: Tim Toups
BLD-Framing/Rough-in11/6/201411/7/201411/7/2014PCANC
DetailsJim Storey
Sheathing nail off of parapets (type P-3) on tower 2 Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in11/5/201411/6/201411/6/2014PPASS
DetailsJim Storey
Tower 2, parapet framing at west end. Phone #: ###-#### Inspection requested via web by Tim Toups east and south exterior nailling and hardware ok up to parapet.
BLD-Framing/Rough-in10/28/201410/29/201410/29/2014APART
DetailsJim Storey
Re-inspect tower 1 parapet sheathing Phone #: ###-#### Inspection requested via web by Tim Toups roof side only ok
BLD-Framing/Rough-in10/24/201410/28/201410/28/2014PFAIL
DetailsJim Storey
Tower 1 Roof parapet sheathing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Framing/Rough-in10/24/201410/27/201410/27/2014PPASS
DetailsJim Storey
Tower 1 parapet framing Phone #: ###-#### Inspection requested via web by Tim Toups
BLD-Conference8/20/20148/21/20148/21/2014APASS
DetailsJim Storey
Wall framing inspection requested for the Podium Level.
Intumescent Fire Paint inspection requested for the Common Area
Thank you. Phone #: ###-#### Inspection requested via web by Carl Benjamin area 1 1st floor walls ok
BLD-Conference8/14/20148/15/20148/15/2014APART
DetailsJim Storey
Request for Podium Level partial framing inspection. Requesting an 8am inspection. Please call to verify inspection time please!

Thank you, Phone #: ###-#### Inspection requested via web by Carl c/n posted for area #1 stair #3 gyp must have continuity for ratting of 2 hr . engineer to verify that osb can be removed to complet corner. 2/ missing joist hangers 224#/ 3 sheer wall washers and resolve bottom plate butt conection//4/ min 4 toe nails for studs to 3x plate/ 5 ceilling rated at unusable spaces to maintaine floor ceilling ratting./ need sheer aplaided to framing.
Permit Ready to Issue  5/6/2014 DONE
DetailsCandy A. Nichols
Issue PAID IN FULL permit  5/6/2014 DONE
DetailsCandy A. Nichols
Print Occupancy Form  5/6/2014  
DetailsCandy A. Nichols
Plan assigned to (CJW)12/31/201312/31/20134/11/2014 PASS
DetailsCarl Westfall
BOISE HEIGHTS APARTMENTS - ePlanReview - New Building - (20 days - Jan 27)
Routing - PLAN CHECK4/9/2014 4/11/2014 PASS
DetailsCarl Westfall
Routing completed. Drawnigs approved.
Routing - FIRE4/10/2014 4/11/2014 PASS
DetailsCraig D. Hanson
See Fire Plan Review Rev 1 04-11-14
PLANS/APPL TAKEN TO FRONT DESK  4/11/2014 DONE
Plan resubmittals received  4/9/2014 DONE
Plan resubmittals requested  4/8/2014 DONE
Fire concerns not resolved
Routing - MECHANICAL4/4/2014 4/8/2014 PASS
DetailsTroy James
Routing - FIRE4/4/2014 4/7/2014 FAIL
DetailsCraig D. Hanson
No items from the attached Fire Plan Review were addressed.
Routing PW Flood Plain4/4/2014 4/7/2014 PASS
Routing - PLAN CHECK3/25/2014 4/7/2014 PASS
DetailsCarl Westfall
(4-4-14) Confirmed that the drawings need only be routed back to Mechanical, to Fire, and to Flood Plain

(4-7-14) Drawings approved with "red lines".
Plan resubmittals received  3/25/2014 DONE
Submitted at 5:04 on Tuesday night. Resubmittal review started a week later on Wednesday.
Plan resubmittals requested  2/12/2014 DONE
Routing Off Site - STRUCTURAL2/5/2014 2/11/2014 PASS
DetailsRon Hill
Uploaded plans and contacted Jared to start review of resubmittals. All issues have been resolved. See Eplan review.
Routing - PLANNING12/31/2013 2/11/2014 PASS
DetailsJoshua Johnson
Josh Johnson - CUP13-00040 & CVA13-00029 & CFH13-00024
Routing - FIRE12/31/201312/31/20132/10/2014 FAIL
DetailsCraig D. Hanson
See Attached Fire Plan Report 02-10-14
Routing - PLAN CHECK12/31/2013 2/10/2014 FAIL
DetailsCarl Westfall
30 days to do the 1st review. Emailed a copy of the plan review report to the Architect.
1st review completed  2/10/2014 FAIL
Routing PW Solid Waste1/3/2014 2/7/2014 PASS
DetailsPeter J. McCullough
Plan resubmittals received  2/5/2014  
Route to Impact Fee Review12/31/20131/6/20142/3/2014 PASS
DetailsCindy M. Gould
Case Summary (BLD)  1/28/2014 DONE
Routing Off Site - STRUCTURAL12/31/2013 1/24/2014 FAIL
DetailsJoe Blow
CH2M Hill - Jared Bauder
Routing - Addressing12/31/2013 1/13/2014 PASS
DetailsEmily Dixon
New parcel number corrected, based off ROS13-00069
Routing - MECHANICAL12/31/2013 1/10/2014 FAIL
DetailsTroy James
eplan
Routing PW Flood Plain1/3/2014 1/8/2014 FAIL
Details
Routing - PLANNING Land Div12/31/2013 1/3/2014 PASS
DetailsDave Abo
Parcel consolidated under ROS13-00069 recorded under ROS 9602.
Routing PW Drainage1/3/2014 1/3/2014 PASS
DetailsBrian Murphy
Routing PW Sewer Design1/3/2014 1/3/2014 PASS
DetailsKyle S. Rosenmeyer
Routing PW Sewer Rating1/3/2014 1/3/2014 PASS
DetailsConnie Baumgartner
Routing - PUBLIC WORKS12/31/2013 1/3/2014 PASS
DetailsConnie Baumgartner
Route to Floodplain reviewer.
Routing - Erosion and Sediment12/31/2013 1/2/2014 PASS
DetailsEvan Jenkins
Staging Area: Permit Required prior to any earth disturbance or staging
Routing - Design Review12/31/2013 1/2/2014 PASS
DetailsAndrea Tuning
Andrea Tuning - DRH13-00204
Routing - PLUMBING12/31/2013 1/2/2014 PASS
DetailsBill VanDegrift
1. Install drain for outside shower to prevent freezing.
2. Per plan and ISPC.
Intake Approval  12/31/2013 PASS
DetailsJason Blais
Prescreen approved by Sam Zahorka. Plan Review Fees paid.
Pending Assignment by JCB12/31/2013 12/31/2013 DONE
DetailsJason Blais
Application received  12/10/2013 DONE
Application submitted via PDS Online on Dec 10 2013 1:51PM
First Notice 9/7/2015