Print Statement | | | 9/22/2015 | | DONE |
|
|
|
|
Third Notice | | 7/14/2015 | 8/12/2015 | | DONE |
|
|
|
|
Second Notice | | 6/20/2015 | 7/9/2015 | | DONE |
|
|
|
Mailed 7-10-15
|
First Notice | | 5/3/2015 | 6/10/2015 | | DONE |
|
|
|
Mailed out 6-10-15
|
Permanent Occupancy | | | 4/23/2015 | | DONE |
|
|
|
|
BLD-Final | 4/17/2015 | 4/20/2015 | 4/20/2015 | P | PASS |
Jim Storey
|
|
|
Craig Phone #: ###-####
|
FIRE-Final Inspection | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PASS |
Katie Marron
|
|
|
Fire life safety passed. All previous noticed items have been satisfactory completed.
|
BLD-Energy code compliance | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | CANC |
Jim Storey
|
|
|
Craig Phone #: ###-####
|
FIRE-Final Inspection | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | FAIL |
Katie Marron
|
|
|
Emergency exit/egress lighting not functional. Ceiling tiles to be replaced and electrical receptacles to be covered in new open tenant space.
|
BLD-Framing/Rough-in | 3/27/2015 | 3/27/2015 | 3/30/2015 | P | PASS |
Dave Hannah
|
|
|
Approved set with store sup. - dimising wall framing & consult - Craig Phone #: ###-####
|
BLD-Wall Bracing | 3/18/2015 | 3/18/2015 | 3/18/2015 | P | PART |
Jim Storey
|
|
|
Craig-dry wall screw inspection Phone #: ###-#### need city aproved plans on site for insp.
|
BLD-Framing/Rough-in | 3/17/2015 | 3/17/2015 | 3/17/2015 | P | PART |
Jim Storey
|
|
|
Craig Phone #: ###-#### tennet wall one sde for progreestion of const ok
|
Issue PAID IN FULL permit | | | 3/13/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 3/13/2015 | | DONE |
Christina Prado
|
|
|
|
Case Summary (BLD) | | | 3/11/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 1/9/2015 | 1/9/2015 | 2/27/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Rite Aid
|
Routing - PLAN CHECK | 2/27/2015 | | 2/27/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/27/2015 | | DONE |
Christina Prado
|
|
|
Need GC form & Revised cert of value for issuance 3-12-15 all requirement met
|
Route to Impact Fee Review | 2/2/2015 | 2/5/2015 | 2/3/2015 | | PASS |
Cindy M. Gould
|
|
|
Under the impact fee threshold no fees.
|
1st review completed | | | 2/2/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 1/9/2015 | | 2/2/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 1/9/2015 | 1/9/2015 | 1/20/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Sewer Rating | 1/12/2015 | | 1/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 1/9/2015 | | 1/12/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 1/9/2015 | | 1/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 1/9/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Adele Schaffeld-Griffin and plan review fees paid.
|
Pending Assignment by JCB | 1/9/2015 | | 1/9/2015 | | DONE |
Jason Blais
|
|
|
|
Application received | | | 1/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 5 2015 9:15AM
|
Routing - Design Review | 1/9/2015 | | 1/12/2014 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - New storefront entry
Approved new storefront entry through building permit.
|