FIRE-Final Inspection | 8/12/2020 | 8/13/2020 | 8/13/2020 | P | FAIL |
Greg Ruxton
|
|
|
Pavement required for TCO not complete.
Paving operations for fire truck access should wrap up in the morning.Other small items addressed from Troy Cobbley''s visit on Wednesday. Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Final | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | NR |
Tell Riley
|
|
|
Need a couple hours in the morning. After 10 am inspection preferred Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
FIRE-Final Inspection | 8/11/2020 | 8/12/2020 | 8/12/2020 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok for a temp when the additional pavement has been layed as agreed. For a final the permanant address and heaters will need to be provided and veriifed.
Lee *screened Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 8/12/2020 | | DONE |
|
|
|
Status altered after DR routing added and completed - permit needs to stay in issued status.
|
Routing - Design Review | 8/11/2020 | | 8/11/2020 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Wall cover | 6/2/2020 | 6/2/2020 | 6/2/2020 | P | PART |
Tell Riley
|
|
|
Drop ceiling on 1st and 2nd floors for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//soffits ok to cover when fire caulk is fixed as discussed//areas will be framed down in laundry//fire tape areas as discussed 2nd floor//Jeremy will send photos to confirm//
|
BLD-Wall Bracing | 5/22/2020 | 5/22/2020 | 5/22/2020 | P | PART |
Tell Riley
|
|
|
Reinspect for gyp shear on all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn//4th and 3rd floor ok//fix shear wall in 2nd floor, block edges//add screws at first floor//
|
BLD-Wall Bracing | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | CANC |
Tell Riley
|
|
|
Re inspect of gypsum board shear on all floors Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Wall cover | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PART |
Tell Riley
|
|
|
3rd and 4th floor drop ceiling inspection for cover along with gyp shear in the entire building Phone #: ###-#### Inspection requested via web by Travis Blackburn//drops ok, third floor pending fire sprinkler approval//shear walls will need to be re-inspected after more screws are added//
|
BLD-Wall cover | 5/20/2020 | 5/20/2020 | 5/21/2020 | P | CANC |
Tell Riley
|
|
|
Inspect drop ceilings on bldg K 4th floor, possibly 3rd also Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PART |
Tell Riley
|
|
|
Corridor inspection to cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//add lags in areas marked//fire caulk penetrations where marked//
|
BLD-Energy code compliance | 5/6/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 5/4/2020 | 5/5/2020 | 5/5/2020 | A | PART |
Tell Riley
|
|
|
Inspection to insulate 1st floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//add bolts as noted on floor//fix holddown that is not installed//fire caulk areas noted//photos of repairs will be sent//
|
BLD-Wall cover | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | PART |
Tell Riley
|
|
|
Cover inspection for 2nd floor only Phone #: ###-#### Inspection requested via web by Travis Blackburn//2nd floor cover ok, add insulation around vent exhausts at exterior wall and at rims where needed//
|
BLD-Wall cover | 4/23/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Dave Hannah
|
|
|
Insulation inspection to cover 3rd floor only Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Conference | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | DONE |
Tell Riley
|
|
|
Discuss phased turnover and clubhouse firestopping. Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 4/21/2020 | 4/22/2020 | 4/22/2020 | A | PART |
Tell Riley
|
|
|
Framing inspection to insulate 2nd floor only. Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to insulate 2nd floor//collars on 3rd and 4th floor installed, and joist repairs were made//
|
BLD-Framing/Rough-in | 4/20/2020 | 4/21/2020 | 4/21/2020 | P | PART |
Tell Riley
|
|
|
Inspection on 3rd floor for approval to insulate and cover inspection on 4th floor Phone #: ###-#### Inspection requested via web by Travis Blackburn//4th floor ok to cover when fire collars are on drain pipe//3rd floor ok to insulate, fix sprinkler tenting, add fire collar to drain pipe, fix hole in joist in furnace room on two of the 4 units//
|
BLD-Conference | 4/1/2020 | 4/1/2020 | 4/1/2020 | P | DONE |
Tell Riley
|
|
|
met onsite with Matt, plumbing inspector, discussed with Travis need for plumbing plans to be revised for building and all other buildings prior to any passed plumbing inspections//
|
BLD-Wall cover | 3/31/2020 | 4/1/2020 | 4/1/2020 | A | PEND |
Tell Riley
|
|
|
4th floor only approval to cover. Phone #: ###-#### Inspection requested via web by Travis Blackburn//insulation ok---still need trades inspections completed--need them prior to insulation and cover//
|
BLD-Framing/Rough-in | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PEND |
Tell Riley
|
|
|
Shaftliner cover and 4th floor ok to insulate Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok when firecaulk has been done at shaftliner//ok to insualate 4th floor pending other trades inspections//
|
BLD-Framing/Rough-in | 3/24/2020 | 3/25/2020 | 3/25/2020 | P | NR |
Tell Riley
|
|
|
2ND and 3RD Floor preliminary inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//discussed framing corrections for cut joists, will need fixed//some fire caulking, need plumbing and fire alarm finished//
|
BLD-Framing/Rough-in | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | PART |
Tell Riley
|
|
|
3rd and 4th floor//truss bracing fixed//framing appears to be ok//need mechanical, electrical, and plumbing roughs passed//will need to do walk through before insulation//
|
BLD-Framing/Rough-in | 3/18/2020 | 3/19/2020 | 3/19/2020 | A | CANC |
Tell Riley
|
|
|
3rd and 4th floor preliminary walk to check structural aspects. Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Framing/Rough-in | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PART |
Tell Riley
|
|
|
Preliminary inspection for trusses and structural as time allows Phone #: ###-#### Inspection requested via web by Travis Blackburn//northside 4th floor units trusses ok//south side 4th floor units trusses need bracing//shear straps 4th floor ok//
|
BLD-Other | 2/17/2020 | 2/18/2020 | 2/18/2020 | A | PART |
Tell Riley
|
|
|
Exterior sheetrock inspection to install weather barrier Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok per pla ns//
|
BLD-Framing/Rough-in | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PART |
Tell Riley
|
|
|
Walk prerock areas in K for insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//will be ok after hold downs installed//
|
BLD-Wall Bracing | 1/14/2020 | 1/14/2020 | 1/14/2020 | P | PART |
Tell Riley
|
|
|
Shear inspection on last wall and h2.5''s to be covered at eves Phone #: ###-#### Inspection requested via web by Travis Blackburn//shear area on exterior south wall ok//see CN for other areas requested to look at//
|
BLD-Wall Bracing | 1/8/2020 | 1/10/2020 | 1/10/2020 | A | PART |
Tell Riley
|
|
|
Exterior shear and hardware for cover. Interior at a later date Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to cover exterior with wrap--DO NOT COVER south wall until approved for straps and fixed sheathing//
|
BLD-Conference | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | DONE |
Tell Riley
|
|
|
Discuss 2hr walls Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Wall Bracing | 1/7/2020 | 1/8/2020 | 1/8/2020 | P | NR |
Tell Riley
|
|
|
Shear inspection for hardware for exterior cover Phone #: ###-#### Inspection requested via web by Travis Blackburn
|
BLD-Wall Bracing | 1/7/2020 | 1/7/2020 | 1/8/2020 | P | CANC |
Tell Riley
|
|
|
|
BLD-Wall Bracing | 1/3/2020 | 1/6/2020 | 1/6/2020 | A | PART |
Tell Riley
|
|
|
Shear inspection and hardware inspection Phone #: ###-#### Inspection requested via web by Travis Blackburn//nailing ok//need to finish straps//provide documentation on nails in pressure treat or use hot dipped galvanized//will need to check hold downs//
|
BLD-Concrete | 10/14/2019 | 10/14/2019 | 10/14/2019 | P | PASS |
Tell Riley
|
|
|
Concrete pour at 1pm. Inspection on reinforcing steel at edges of corridor Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
|
BLD-Concrete | 10/9/2019 | 10/10/2019 | 10/10/2019 | P | PART |
Tell Riley
|
|
|
We are pouring the slab for building K at 6:30 on Friday morning. Phone #: ###-#### Inspection requested via web by Matt Perry//ok pending specials//
|
BLD-Concrete | 10/3/2019 | 10/4/2019 | 10/4/2019 | P | CANC |
Tell Riley
|
|
|
Pouring slab on grade for this building early Monday morning so late inspection should work Phone #: ###-#### Inspection requested via web by Travis Blackburn//cancel per Matt//
|
BLD-Foundation | 9/18/2019 | 9/19/2019 | 9/19/2019 | P | PART |
Tell Riley
|
|
|
Concrete pour scheduled for 3:30 Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok to pour//pending special inspections///
|
BLD-Footing | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PART |
Tell Riley
|
|
|
Second half of this building will need inspected for reinforcement.Pour time is after the walls on the clubhouse walls this afternoon Phone #: ###-#### Inspection requested via web by Travis Blackburn//bar fixed while onsite// ok pending specials//
|
BLD-Footing | 9/10/2019 | 9/12/2019 | 9/12/2019 | P | FAIL |
Mike Jordan
|
|
|
Concrete pour is at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn. Clearance issues fromm bottom of footing. Needs to install verts in corner, rebar needs to be tied as to resist movement when concrete is placed.
|
Issue PAID IN FULL permit | | | 8/15/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/15/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2019 | | DONE |
|
|
|
DO NOT ISSUE WITHOUT OHTER 13 PERMITS AND VOIDED PERMIT HAS PLAN CHECK FEES
met
RP
GC
Revised Certificate of Value
|
Routing PW Street Lights | 8/12/2019 | | 8/12/2019 | | PASS |
Tom Marshall
|
|
|
|
Plan assigned to (CJW) | 3/11/2019 | 3/11/2019 | 8/10/2019 | | PASS |
Carl Westfall
|
|
|
* (2nd done) 04/08/19 (new buildings - 25 days) (eplan) Village East Apartments (K) (approved pending structural)
|
Plan Reviewer's activity | | | 8/10/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for all buildings.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2019 | | DONE |
|
|
|
|
Routing - Design Review | 8/5/2019 | | 8/5/2019 | | PASS |
Andrea Tuning
|
|
|
|
Routing - FIRE | 7/9/2019 | 7/9/2019 | 7/16/2019 | | PASS |
Mark Scharfen
|
|
|
07/16-Village East Building K resumbittal. MS. Completed fire review. Uploaded rev_fire 07.16.2019.pdf. All permits ok on fire.
|
Routing PW Drainage | 7/15/2019 | | 7/15/2019 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals received | | | 7/8/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 3rd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Routing - FIRE | 6/13/2019 | 6/13/2019 | 6/24/2019 | | FAIL |
Mark Scharfen
|
|
|
06/26-Village East Building K resubmittal MS. Completed review and uploaded rev_fire 06.24.2019.pdf. Emailed review to architect.
|
Routing - Design Review | 6/17/2019 | | 6/17/2019 | | FAIL |
Andrea Tuning
|
|
|
A total of 272 bicycle parking spaces will be required. A minimum of 68 of the bicycle parking spaces are required to be covered. To provide a safe, covered and efficient location for the bicycles, design the spaces to be a minimum of 6-feet long and 2.5 feet wide and have an overhead clearance of 7-feet if covered. A 4-foot wide aisle is required between rows of bicycle parking or nearby walls. Stationary racks shall be located on improved non-permeable surfaces and anchored to the ground. A detail of the rack and how it is attached to the wall should be submitted with the building permit.
Vertical curbing shall be utilized adjacent to all landscaping and pedestrian walk ways. Permanent wheel restraints may be utilized in lieu of curbing adjacent to pedestrian walk ways.
All interior and terminal planter islands shall provide at least one Class II tree within all of the interior and terminal planters.
Provide an easement for portions of the Valley Regional transit stop located on private property.
Continue to work with staff to provide a cohesive and quality exterior building design in regard to material breaks, the application of brick on each building and the color palette for the development. This may include providing a brick wainscot or brick corner elements on each building, reevaluating the location of material breaks and further refining the color palette.
Employ techniques to recess windows above the ground floor a minimum of 2-inches from the façade or incorporated window trim at least 4-inches in width. Submit a window detail showing this recess.
|
Plan Reviewer's activity | | | 6/13/2019 | | DONE |
|
|
|
See the routing under permit BLD19-00526 for the 2nd plan review. None of the permits can be issued until all plan reviews are approved. CJW
|
Route to Impact Fee Review | 5/10/2019 | 5/13/2019 | 5/10/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 3/11/2019 | | 5/7/2019 | | FAIL |
Carl Westfall
|
|
|
|
1st review completed | | | 5/7/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 5/7/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 3/11/2019 | | 4/25/2019 | | PASS |
Andy J. Long
|
|
|
see ESC19-00181 for details
|
Routing - FIRE | 3/11/2019 | 3/11/2019 | 4/12/2019 | | FAIL |
Mark Scharfen
|
|
|
IFC 1st review 04.12.2019.pdf
|
Routing Off Site - STRUCTURAL | 3/11/2019 | | 3/27/2019 | | FAIL |
Carl Westfall
|
|
|
Cory Harelson (KPFF)
|
Routing PW Sewer Design | 3/12/2019 | | 3/26/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 3/12/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 3/12/2019 | | 3/21/2019 | | FAIL |
Brian Murphy
|
|
|
|
Routing - PLANNING | 3/11/2019 | | 3/19/2019 | | FAIL |
Leon Letson
|
|
|
See DR comments
|
Routing - MECHANICAL | 3/11/2019 | | 3/15/2019 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 3/11/2019 | | 3/13/2019 | | FAIL |
Andrea Tuning
|
|
|
|
Routing - Addressing | 3/11/2019 | | 3/12/2019 | | PASS |
Doug Chausow
|
|
|
Bldg K: 11964 W Fairview Ave
|
Routing - PUBLIC WORKS | 3/11/2019 | | 3/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing PW Street Lights | 3/12/2019 | | 3/12/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 3/11/2019 | | 3/11/2019 | | PASS |
Daryl Spivey
|
|
|
Meet suds relief requirements and per ISPC.
|
Intake Approval | | | 3/5/2019 | | PASS |
|
|
|
|
Application received | | | 2/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 21 2019 5:02PM
|
BLD-Final | 8/13/2020 | 8/14/2020 | | A | |
Tell Riley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Travis Blackburn
|