Second Notice | | 7/19/2020 | 7/22/2020 | | DONE |
|
|
|
This permit finaled on the web by Chris Witt
|
First Notice | 5/14/2020 | 5/14/2020 | 7/9/2020 | | DONE |
Brandon Shaw
|
|
|
mailed 7-9-2020
|
BLD-Final | 5/13/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
Bo Phone #: ###-####
|
DOC - Permit Finaled | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Wall cover | 5/7/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brandon Shaw
|
|
|
Screened- Bo Phone #: ###-####
|
BLD-Energy code compliance | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Brandon Shaw
|
|
|
Sreened- Bo Phone #: ###-####
|
BLD-Final | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | FAIL |
Jim Storey
|
|
|
Bo **cleared** Phone #: ###-#### 2 hr pl wall not complet leagers and membrane .// insulation not done.
|
FIRE-Final Inspection | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
cleared // Bo Phone #: ###-####
|
PubWorks Occupancy Approval | 4/1/2020 | 4/1/2020 | 4/1/2020 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 3/23/2020 | 3/25/2020 | 3/25/2020 | A | FAIL |
Jim Page
|
|
|
Fire sprinkler riser room is not 1 hour rated as required.
Bo Phone #: ###-####
|
FIRE-Final Inspection | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm and fire sprinkler permits finaled, need all small documents. No inspection performed but we did conference on life safety items.
Bo Phone #: ###-####
|
FIRE-Final Inspection | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | FAIL |
Jim Page
|
|
|
Associated FIR permits for fire alarm and fire sprinkler are not finaled, FIR permits must be finaled before life fire safety inspection can be performed.
Bo Phone #: ###-####
|
Zoning Approval | 3/19/2020 | 3/19/2020 | 3/19/2020 | | DONE |
Josh Wilson
|
|
|
|
BLD-Energy code compliance | 12/11/2019 | 12/13/2019 | 12/13/2019 | P | PART |
Brandon Shaw
|
|
|
partial insulation and vapor barrier for 1st floor north wall and section of east wall to the elevator, and exterior elevator wall. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Exterior sheeting, roof deck sheeting, hardware.
|
BLD-Framing/Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | PASS |
Brandon Shaw
|
|
|
framing hardware - holddown bolts HUD2, HUD5, HUD8 Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Brandon Shaw
|
|
|
foundation insulation. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Foundation | 9/30/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to puor, pending special inspection...
|
BLD-Footing | 9/30/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by J.C. Murray
|
Print Occupancy Form | | | 8/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/22/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/22/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/14/2019 | | |
|
|
|
|
Plan assigned to (JAR) | 6/5/2019 | 6/5/2019 | 8/14/2019 | | DONE |
Julie Romig
|
|
|
08/08 - 3rd Rev - 1st Rev Comp - 2nd Rev Comp - 502 Broadway Mixed Use Shell/Core
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/14/2019 | | DONE |
|
|
|
MET bhurlburt@petrainc.net
NEED
GC FORM
Revised Value
RP
ACHD
|
Routing - Design Review | 8/12/2019 | | 8/14/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 8/3/2019 | | 8/13/2019 | | PASS |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/23/2019 | | 8/1/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - Design Review | 7/23/2019 | | 7/29/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing PW Drainage | 7/23/2019 | | 7/26/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing Off Site - STRUCTURAL | 7/23/2019 | | 7/26/2019 | | PASS |
Julie Romig
|
|
|
KPFF 2nd Review
|
Routing PW Sewer Design | 7/25/2019 | | 7/26/2019 | | PASS |
DeAnn Brown
|
|
|
Building is connecting to existing sewer stub.
|
Routing - FIRE | 7/23/2019 | 7/23/2019 | 7/23/2019 | | PASS |
Mark Scharfen
|
|
|
completed fire review. UPloaded rev_fire 07.23.2019.pdf.
|
Routing PW Street Lights | 7/23/2019 | | 7/23/2019 | | PASS |
Tom Marshall
|
|
|
|
Route to Impact Fee Review | 7/15/2019 | 7/18/2019 | 7/16/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 7/15/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 6/5/2019 | | 7/15/2019 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 6/4/2019 | 6/5/2019 | 7/12/2019 | | FAIL |
Mark Scharfen
|
|
|
07.16.2019-Fire review complete. Needs PIV or rated riser room. Uploaded rev_fire 07.16.2019.pdf and emailed architect.
|
Routing Off Site - STRUCTURAL | 6/5/2019 | | 6/18/2019 | | FAIL |
Julie Romig
|
|
|
KPFF
|
Routing - Design Review | 6/5/2019 | | 6/13/2019 | | PASS |
Josh Wilson
|
|
|
Ok per DRH19-00032
|
Routing PW Environmental | 6/6/2019 | | 6/12/2019 | | PASS |
Terry Alber
|
|
|
Grease interceptor (1500-gallon) shown and approved. Grease waste line shall connect to any tenant space that may house food service.
|
Routing PW Solid Waste | 6/6/2019 | | 6/10/2019 | | PASS |
Peter J. McCullough
|
|
|
Approved for alley service; be aware that service could be affected in future due to the dead-end alley, as other developments could alter the truck's through-access
|
Routing - PLANNING | 6/5/2019 | | 6/10/2019 | | PASS |
David Moser
|
|
|
|
Routing - MECHANICAL | 6/5/2019 | | 6/7/2019 | | PASS |
Chad Schwendiman
|
|
|
Approved with mark ups
|
Routing - PLUMBING | 6/5/2019 | | 6/6/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Street Lights | 6/6/2019 | | 6/6/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - Addressing | 6/5/2019 | | 6/6/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/5/2019 | | 6/6/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 6/5/2019 | | 6/6/2019 | | PASS |
Michael Zawacki
|
|
|
RP needed. Site prep inspection required.
|
Intake Approval | | | 6/4/2019 | | PASS |
Brian McGowan
|
|
|
|
Intake Approval | | | 5/10/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide the following in order for your Prescreen to be approved:
1. A completed Permanent O and M Agreement.
2. Form # 310 for Special Inspections.
3. Verification of Legal Lot or Parcel.
4. The ESC Narrative needs to be signed.
5. I could not find an Interior Finish Schedule (not on Sheet A51-53)
6. The Structural Section of the Checklist was not completed. Please complete.
|
Application received | | | 5/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2019 3:07PM
|
Routing PW Drainage | 6/6/2019 | | | | FAIL |
Brian Murphy
|
|
|
NEEDS O AAND M ,APDEX J
|