Temporary Occupancy | 7/2/2020 | 9/30/2020 | 7/2/2020 | | DONE |
Brittany Hill
|
|
|
|
PubWorks Occupancy Approval | 7/2/2020 | 7/2/2020 | 7/2/2020 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 7/1/2020 | 7/1/2020 | 7/1/2020 | | DONE |
Leon Letson
|
|
|
temp only see email in documents blh 7-2-2020
|
BLD-Final | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Final | 6/24/2020 | 6/25/2020 | 6/25/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// ok pending address posting in units..
|
BLD-Blower Door Test Results | 6/25/2020 | 6/25/2020 | 6/25/2020 | P | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// average 5.7
|
FIRE-Final Inspection | 6/24/2020 | 6/25/2020 | 6/25/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Inspection by Greg.
Phone #: ###-#### Inspection requested via web by bill gullickson
|
FIRE-Final Inspection | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | FAIL |
Jim Page
|
|
|
Correctly repair holes that were next to fire sprinkler heads in furnace closets. CPVC pipe is exposed in side entry closet under the stairs.
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Final | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Energy code compliance | 4/14/2020 | 4/15/2020 | 4/16/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Energy code compliance | 4/10/2020 | 4/14/2020 | 4/14/2020 | P | PEND |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// needs re-inspection for fire
|
BLD-Framing/Rough-in | 4/8/2020 | 4/9/2020 | 4/9/2020 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Framing/Rough-in | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson
|
BLD-Framing/Rough-in | 4/3/2020 | 4/8/2020 | 4/8/2020 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson// nail hangers off as needed, strap plates as needed, overlap truss braces as needed,, nail hing studs as needed, etc, see paint
|
BLD-Wall Bracing | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson,, exterior was ok to cover
|
BLD-Wall Bracing | 3/25/2020 | 3/26/2020 | 3/26/2020 | A | PEND |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by bill gullickson. Needs to resolve with Tony.
|
BLD-Wall Bracing | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | CANC |
Tony Young
|
|
|
Exterior wall shear inspection. Cheers, Phone #: ###-#### >> Inspection requested via web by Nic Van Diepen Inspection cancelled from web by: Nic Van Diepen
|
CHANGE STATUS TO (ISS) | | | 2/19/2020 | | DONE |
|
|
|
plan mod approved
|
OVERRIDE | | | 2/18/2020 | | |
|
|
|
|
BLD-Wall Bracing | 2/14/2020 | 2/18/2020 | 2/18/2020 | A | CANC |
Tony Young
|
|
|
Ed Phone #: ###-#### Inspection cancelled from web by: Nic Van Diepen
|
Plan assigned to (JG) | 2/7/2020 | 2/7/2020 | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
02/18 plan mod Eaglehawk Fourplex - Bldg 1 ePlan
|
Routing - PLAN CHECK | 2/12/2020 | | 2/18/2020 | | PASS |
Javier Guzman
|
|
|
|
Permit Ready to Issue | | | 2/18/2020 | | DONE |
|
|
|
**PLAN MOD - DO NOT REISSUE** All plan mod fees assessed on BLD19-02617
|
Routing - MECHANICAL | 2/12/2020 | | 2/12/2020 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 2/7/2020 | | DONE |
|
|
|
plan mod 1- modification replaces engineeerd mechanical hvac design with Manual S/J design. General contractor describes Manual J design equipment provides better efficiency and is generally easier to install. Manual J/S replaces fan coil and heat pump units, and includes minor adjustment to duct runs and return air.
|
BLD-Energy code compliance | 11/26/2019 | 11/26/2019 | 11/26/2019 | P | PASS |
Tony Young
|
|
|
Foundation rigid insulation. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Energy code compliance | 11/25/2019 | 11/26/2019 | 11/26/2019 | A | PART |
Tony Young
|
|
|
Foundation wall rigid insulation. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
|
BLD-Foundation | 11/19/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
BLD-Footing | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####
|
Fees Due Hold | 10/5/2019 | | 11/19/2019 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Telephone call | | | 10/4/2019 | | DONE |
|
|
|
called Perryman-talked to
Addy in accounting-she will let the GC know that there are more fees due-i told her they wouldn't be able to schedule and inspection untill it was paid
|
Issue PAID IN FULL permit | | | 9/19/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 9/18/2019 | | |
|
|
|
|
Plan assigned to (JG) | 7/17/2019 | 7/18/2019 | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
9/20 3rd rev comp, 08/27 - 506 Eaglehawk Fourplex Bldg 1 ePlan**
|
Routing - PLAN CHECK | 9/16/2019 | | 9/18/2019 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/18/2019 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Value
DO NOT ISSUE WITHOUT BLD19-02617-BLD19-02622
|
Routing PW Street Lights | 9/16/2019 | | 9/17/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Design Review | 9/16/2019 | | 9/17/2019 | | PASS |
Josh Wilson
|
|
|
Revised site and landsape plan ok
|
Routing - PLAN CHECK | 9/3/2019 | | 9/11/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 9/3/2019 | | 9/11/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by KPFF Engineer
|
Routing PW Drainage | 9/3/2019 | | 9/11/2019 | | PASS |
Melissa Jannusch
|
|
|
Drainage approved under the subdivison review process ODI 3719
|
Routing PW Street Lights | 9/11/2019 | | 9/11/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - FIRE | 9/3/2019 | 9/3/2019 | 9/10/2019 | | PASS |
Mark Scharfen
|
|
|
09/10-Eaglehawk building 1 Resubmittal complete. Uploaded rev_fire 09.10.2019.pdf.
|
Routing - PLANNING | 9/10/2019 | | 9/10/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - Design Review | 9/3/2019 | | 9/10/2019 | | FAIL |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 9/6/2019 | | 9/6/2019 | | PASS |
Troy James
|
|
|
Engineered designed load calcs.See building plans.
|
Routing PW Street Lights | 9/3/2019 | | 9/3/2019 | | FAIL |
Tom Marshall
|
|
|
Streetlight plan insufficient contact Tom Marshall ###-####.
|
Routing - MECHANICAL | 9/3/2019 | | 9/3/2019 | | FAIL |
Troy James
|
|
|
Still have two different heating and cooling design.
|
Route to Impact Fee Review | 8/20/2019 | 8/23/2019 | 8/21/2019 | | PASS |
Shannon Cade
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/17/2019 | 7/18/2019 | 8/20/2019 | | FAIL |
Mark Scharfen
|
|
|
08/20 Eaglehawk Fourplex Bldg 1 (ePlan)- MS-review complete. Uploaded and emailed to architect rev_fire 08.20.2019.pdf
|
Routing Off Site - STRUCTURAL | 7/18/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
Failed in ePlan by KPFF Engineer
|
1st review completed | | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 7/17/2019 | | 8/20/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Drainage | 7/19/2019 | | 7/29/2019 | | FAIL |
Melissa Jannusch
|
|
|
Please provide most recent set of Civil Plans dated 10-1-2018
|
Routing - MECHANICAL | 7/17/2019 | | 7/24/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to Architect.
|
Routing - Erosion and Sediment | 7/17/2019 | | 7/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP listed. Site preparation inspection is required.
|
Routing - PLANNING | 7/17/2019 | | 7/21/2019 | | PASS |
Leon Letson
|
|
|
|
Routing - PUBLIC WORKS | 7/17/2019 | | 7/19/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 7/19/2019 | | 7/19/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 7/19/2019 | | 7/19/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Solid Waste | 7/19/2019 | | 7/19/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 7/17/2019 | | 7/18/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PLUMBING | 7/17/2019 | | 7/18/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 7/17/2019 | | 7/18/2019 | | FAIL |
Andrea Tuning
|
|
|
Locate the street trees along Bogart Lane within the landscape planter located between the sidewalk and the curb line.
Install landscape planter islands at the terminus of each row of parking. The planters shall be a minimum of 8-feet in width (measured inside of curb to inside of curb) and include the required Class II or Class III tree with low shrubs or other vegetative groundcover.
Install a mixture of deciduous and evergreen trees, shrubs, or other vegetative groundcover in the northwest corner of the site that will create a visual barrier that provides a minimum of 60-percent of a barrier within five years of planting for the existing single-family residential dwelling that is an “out parcel”.
Locate all site lighting outside of the required planter islands.
Clearly identify all mechanical units and how they will be screened.
|
Intake Approval | | | 7/17/2019 | | PASS |
Brian McGowan
|
|
|
|
Application received | | | 7/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 15 2019 2:09PM
|