Second Notice | | 5/17/2020 | 5/21/2020 | | DONE |
|
|
|
This permit finaled on the web by Charlene Meadows
|
First Notice | | 5/2/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
Permanent Occupancy | | | 4/22/2020 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Jim Page
|
|
|
Previously noted item for fire alarm finalization has been completed, final life fire safety inspection for area of work is complete.
Bill ** cleared ** Phone #: ###-####
|
BLD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Dave Hannah
|
|
|
Bill ** cleared ** Phone #: ###-####
|
FIRE-Final Inspection | 4/13/2020 | 4/14/2020 | 4/14/2020 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, will be rescheduled after FIR permit for fire alarm system is complete.
Screened call to meet // Bill Phone #: ###-####
|
FIRE-Final Inspection | 4/10/2020 | 4/13/2020 | 4/13/2020 | A | FAIL |
Jim Page
|
|
|
As stated in the 25FEB2020 inspection notes, FIR permit for fire alarms must be completed and finaled before life fire safety will be completed.
Call ahead - Bill Phone #: ###-####
|
Change Expiration Date Only | | | 3/17/2020 | | DONE |
|
|
|
extend TCO 90 days from 3/22/20 per Jason Blais. See DOCS
|
Telephone call | | | 3/13/2020 | | DONE |
|
|
|
emailed EKC to let them know that their permit will expire on 3/22/20
|
BLD-Aging Inspection | 2/24/2020 | 2/24/2020 | 2/28/2020 | | PEND |
Dave Hannah
|
|
|
|
BLD-Final | 2/24/2020 | 2/25/2020 | 2/25/2020 | P | CANC |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
FIRE-Final Inspection | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | CANC |
Jim Page
|
|
|
FIR permit for fire alarms needs to be completed, see notes entered under FIR19-00948, after as-builts are received, reviewed and permit is back into issued status then the fire alarm permit can be finaled as well as life safety. Per conversation with point of contact, this request is cancelled and will be scheduled when FIR permit for fire alarms is complete.
Bill Phone #: ###-####
|
Telephone call | | | 2/24/2020 | | DONE |
|
|
|
mailed courtesy letter to GC regarding TCO expiration date: 3/22/20
|
BLD-Final | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PEND |
Dave Hannah
|
|
|
Bill Phone #: ###-####
|
BLD-Final | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PART |
Dave Hannah
|
|
|
temporary occupancy // Bill Phone #: ###-#### ok for tco needs to install doors
|
FIRE-Final Inspection | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PART |
Troy Cobbley
|
|
|
A temp for life safety is approved by Joe until the project related fire alarm permit is finaled and the doors/hardware has been installed/verified.
Bill Phone #: ###-####
|
Temporary Occupancy | 12/23/2019 | 3/22/2020 | 12/23/2019 | | DONE |
Brittany Hill
|
|
|
|
FIRE-Final Inspection | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | CANC |
Jim Page
|
|
|
Bill Phone #: ###-####
|
FIRE-Final Inspection | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | FAIL |
Jim Page
|
|
|
Smoke detector in main lobby of tenant space, next to conference room is overspaced. Conference room requires notification. Modifications have been made without a fire alarm permit. FIR permit for fire sprinkler needs to be finaled before life fire safety inspection can be completed. No occupancy allowed until inspection process is complete and finaled.
Bill- Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | PART |
Jim Storey
|
|
|
Bill Phone #: ###-#### fire stopping in floor/ceilling ok to cover need wire max 8 inches of mains spot check ok.
|
BLD-Conference | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | DONE |
Dave Hannah
|
|
|
Call to meet there // Braden Phone #: ###-####
|
BLD-Wall cover | 10/22/2019 | 10/23/2019 | 10/23/2019 | P | PASS |
Dave Hannah
|
|
|
As late as possible Phone #: 2088672227 >> Inspection requested via mobile web by Brayden Sielaff
|
Issue PAID IN FULL permit | | | 10/4/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/4/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/4/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 9/26/2019 | | |
Brian McGowan
|
|
|
Applicant asked to change from a Vanilla to an Occupancy for Bank of Jackson Hole.
|
Route to Impact Fee Review | 8/16/2019 | 8/19/2019 | 8/19/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (BJM) | 7/25/2019 | 7/25/2019 | 8/16/2019 | | DONE |
Brian McGowan
|
|
|
07/31 L1 Vanilla, ePlan
|
Routing - PLAN CHECK | 7/25/2019 | | 8/16/2019 | | PASS |
Brian McGowan
|
|
|
|
1st review completed | | | 8/16/2019 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2019 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/16/2019 | | DONE |
|
|
|
all met: braydens@ekcconstruction.com
NEED GC
NEED Rev Val
|
Routing - Addressing | 7/25/2019 | | 7/26/2019 | | PASS |
Doug Chausow
|
|
|
Ste 308
|
Routing - PUBLIC WORKS | 7/25/2019 | | 7/25/2019 | | PASS |
Angela Hardy
|
|
|
|
Intake Approval | | | 7/25/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by BJM
|
Application received | | | 7/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 19 2019 1:14PM
|