INSP-Final Inspection | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PART |
Jim Page
|
|
|
Elevator recall complete, initiating devices in pump room, garbage room, mech room next too fire pump room and fire panel heat have been tested. Level 1 garage dry system and level 6 dry system alarm pressure switches reported to panel, all other monitoring devices will need to be tested after trip times are corrected on dry systems, no other fire alarm associated devices for fire sprinkler monitoring have been tested. Monitoring has been verified.
Coordinated with Sprinkler contractor for 9AM inspection, Buck Phone #: ###-####
|
INSP-Final Inspection | 3/4/2020 | 3/5/2020 | 3/5/2020 | A | CANC |
Jim Page
|
|
|
Rescheduled for 9AM, 06MAR2020, this request is cancelled.
Buck Phone #: ###-####
|
Plan resubmittals received | | | 2/26/2020 | | DONE |
|
|
|
|
Alarm Plan Check | 2/26/2020 | | 2/26/2020 | | PASS |
Lee G Meredith
|
|
|
Design is passed as noted and will require a plan modification or as built submittal prior to final acceptance testing. Any changes to this design (as noted) will require resubmittal. This passed design is required to be sent to the engineer of record for review and approval. Any changes required by the engineer of record will required resubmittal for city review.
|
PLANS TAKEN FRONT DESK ALARM | | | 2/26/2020 | | PASS |
|
|
|
Review is passed as noted with review comments and requirements.
4th review requires review at $65 per hour. Total 4th review time is 2.5 hours for a total of $162.50, plus the original base fee of $150.00, plus total amount for 129 alarm devices. Installation has begun prior to a permit being issued so permit fee is to be doubled.
|
Permit Ready to Issue | | | 2/26/2020 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 2/26/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/25/2020 | | DONE |
|
|
|
|
1st review completed | | | 2/25/2020 | | FAIL |
|
|
|
Detection coverage corrections still have note been made. Returned to Ken to have drawing notes / requirements met.
|
Plan resubmittals received | | | 2/18/2020 | | DONE |
|
|
|
|
1st review completed | | | 2/18/2020 | | FAIL |
|
|
|
See 2nd review comments. Updated review comments were emailed to Rita.
|
Plan assigned to (Lee) | 10/9/2019 | | 10/9/2019 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 10/9/2019 | | PASS |
|
|
|
|
1st review completed | | | 10/9/2019 | | FAIL |
|
|
|
See 1st review comments.
|
Application received | | | 10/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2019 11:22AM
|