INSP-Final Inspection | 8/11/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Greg Ruxton
|
|
|
Fire Sprinkler Final Passed.
SCREENED // Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2020 | 8/12/2020 | 8/12/2020 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro of the 3rd and 4th floors witnessed with no pressure loss.
Screened- Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PART |
Troy Cobbley
|
|
|
The standpipe, 1st and 2nd floor hydro tests witnessed. 3rd and 4th would not hold pressure.
Tanner - */Screened/* Phone #: ###-####
|
INSP-Sprinkler Rough-in | 6/18/2020 | 6/19/2020 | 6/19/2020 | A | PASS |
Troy Cobbley
|
|
|
Rough-in for the stand pipe passed. Will need hydro and painted as discussed.
Tanner *screened* Phone #: ###-####
|
Sprinkler Plan Check | 6/2/2020 | | 6/4/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2020 | | DONE |
Mark Stumbaugh
|
|
|
As Built Drawings - No Fee
|
Permit Ready to Issue | | | 6/4/2020 | | DONE |
|
|
|
**DO NOT REISSUE - AS BUILT**
|
CHANGE STATUS TO (ISS) | | | 6/4/2020 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 6/1/2020 | 6/2/2020 | 6/2/2020 | A | PASS |
Troy Cobbley
|
|
|
The piping above the soffits for the first and second floors can be covered. Tanner *screened* Phone #: ###-####
|
Plan resubmittals received | | | 6/2/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 5/29/2020 | | FAIL |
Mark Stumbaugh
|
|
|
Plans resubmitted without any changes from last submittal. Returned to applicant
|
Sprinkler Plan Check | 5/26/2020 | | 5/28/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Miscellaneous action | | | 5/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
Emailed Bill with Alpine fire explaining what was need on as built drawings(attached in docs)
|
Plan assigned to (Stumbaugh) | 5/21/2020 | | 5/26/2020 | | DONE |
Mark Stumbaugh
|
|
|
as built
|
INSP-Sprinkler Rough-in | 5/22/2020 | 5/22/2020 | 5/22/2020 | P | PART |
Troy Cobbley
|
|
|
Third floor piping in soffits is ok for cover. Plans are in review status for some reason. If changes in piping is required, piping will need to be uncovered. Tanner Phone #: ###-####
|
Plan resubmittals received | | | 5/21/2020 | | DONE |
|
|
|
as built reqest by Bill Corbit
|
INSP-Sprinkler Rough-in | 5/20/2020 | 5/20/2020 | 5/20/2020 | P | PASS |
Troy Cobbley
|
|
|
The piping above the 4th floor soffits is ok for cover. Tanner *screened* Phone #: ###-####
|
INSP-Sprinkler Rough-in | 5/5/2020 | 5/6/2020 | 5/7/2020 | A | PASS |
Troy Cobbley
|
|
|
The heat tape/insulation in the breeze ways is ok for cover. *Screened* Tanner Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/1/2020 | | DONE |
|
|
|
|
Intake Approval | | | 3/24/2020 | | PASS |
|
|
|
|
1st review completed | | | 3/24/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/24/2020 | | 3/24/2020 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/24/2020 | | DONE |
|
|
|
Plan mod passed. Minimum of $65 for review fee is due.
|
Permit Ready to Issue | | | 3/24/2020 | | DONE |
|
|
|
plan mod met
|
Permit Ready to Issue | | | 3/24/2020 | | DONE |
|
|
|
plan mod passed
|
Plan assigned to (Stumbaugh) | 3/18/2020 | | 3/23/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod request to add heat trace for the sprinkler system
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | PASS |
Troy Cobbley
|
|
|
Tenting passed. Piping can be covered except for the piping that crosses the breeze way. It will need separate inspection when the heat tape has been installed and inspected.
Tanner Phone #: ###-####
|
Plan Modification Accepted | | | 3/18/2020 | | DONE |
|
|
|
plan mod request to add heat trace for the sprinkler system
|
INSP-Sprinkler Rough-in | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | FAIL |
Troy Cobbley
|
|
|
Need the flexible cplgs installed and then hydro tested. WIll need the pressure guage moved back to the top when hydro is over. Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/27/2020 | 2/27/2020 | 2/27/2020 | P | PASS |
Troy Cobbley
|
|
|
The new plans match the actual main pipe routing. Piping can not be covered until the tenting is approved. There is still the issue with the possible relocation of the stand pipe.
Tanner Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | CANC |
Troy Cobbley
|
|
|
The plan mods were not on site when I arrived for the inspection. Will need to be rescheduled.
Tanner Phone #: ###-####
|
Permit Ready to Issue | | | 2/25/2020 | | DONE |
|
|
|
met
|
CHANGE STATUS TO (ISS) | | | 2/25/2020 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/25/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/21/2020 | | 2/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
no new devices
|
Plan assigned to (Stumbaugh) | 2/20/2020 | | 2/21/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
INSP-Sprinkler Rough-in | 2/19/2020 | 2/20/2020 | 2/20/2020 | A | FAIL |
Troy Cobbley
|
|
|
Tenting not done yet. I let Tanner know they will need to provide design and approved drawings of any changes including the relocation of the stand pipe.
Tanner Phone #: ###-####
|
Plan Modification Accepted | | | 2/20/2020 | | DONE |
|
|
|
relocating a main
|
INSP-Sprinkler Rough-in | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PART |
Troy Cobbley
|
|
|
Piping rough-in passed. As-buillts are needed showing the supply pipe routing change for the 4th floor. Piping can not be covered until a tenting inspection has been passed. The stand pipe was not inspected due to a relocation request.
Tanner Phone #: ###-####
|
Sprinkler Plan Check | 12/2/2019 | | 12/3/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/3/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 12/3/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 12/3/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/2/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 11/22/2019 | | 11/25/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 11/22/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 11/20/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/23/2019 | | 10/28/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/28/2019 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 10/23/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/23/2019 | | 10/23/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 10/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 21 2019 3:42PM
|