INSP-Final Inspection | 4/2/2020 | 4/3/2020 | 4/3/2020 | P | PASS |
Jim Page
|
|
|
Plans have been updated showing upright heads being added, final fire sprinkler inspection for area of work is complete.
Cole Bierman is the contact. Thanks(: Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan assigned to (Stumbaugh) | 3/31/2020 | | 4/1/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 4/1/2020 | | 4/1/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/1/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
2 new devices
|
Permit Ready to Issue | | | 4/1/2020 | | DONE |
|
|
|
plan mod approved
|
CHANGE STATUS TO (ISS) | | | 4/1/2020 | | DONE |
|
|
|
|
INSP-Final Inspection | 3/30/2020 | 3/31/2020 | 3/31/2020 | P | PART |
Jim Page
|
|
|
Partial final inspection is complete, upright heads were added above T-grid by electrical room attached to room at end of hallway 203, n ceiling in electrical room and wall does not go all of the way to the deck. Drawings need to show addition of upright heads that were added to be compliant with 2016 NFPA13, section 8.15.23, permit will not be finaled until drawings are updated with changes made.
Cole Bierman is the contact and has asked to be notified 1 hr ahead of time. Thanks(: Phone #: ###-#### Inspection requested via web by Stan Beus
|
Plan Modification Accepted | | | 3/31/2020 | | DONE |
|
|
|
Kyle from Shilo asked for a plan mod workflow to be started
|
INSP-Sprinkler Rough-in | 3/16/2020 | 3/17/2020 | 3/16/2020 | P | CANC |
Jim Page
|
|
|
Tony Cetani is the contact. The Inspection will also be for the third floor. Thanks for all that you do! (: Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | CANC |
Jim Page
|
|
|
Wrong permit requested, no inspection for this site per conversation with point of contact.
Tony Cetani is the contact. This inspection will also be for the 3rd floor. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 2/18/2020 | 2/18/2020 | 2/18/2020 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping in area of work complete, approved for cover. Notated electrical room on city approved drawing that does not have a ceiling and wall does not go all the up, wall needs to go all the way to the deck or the sprinkler system needs to comply with 8.15.23 of the 2016 NFPA13, will verify during next inspection.
Cole Bierman is the contact for this RTC inspection. Cole is needing a hour notice to get there as he is at another job site. Thank you so much for your help. Phone #: ###-#### Inspection requested via web by Stan Beus
|
Application received | | | 10/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2019 7:17AM
|
Intake Approval | | | 10/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 10/24/2019 | | 10/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 10/24/2019 | | 10/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 10/24/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 10/24/2019 | | DONE |
|
|
|
met
|
Issue and Print Permit | | | 10/24/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 10/24/2019 | | DONE |
|
|
|
|