INSP-Final Inspection | 8/7/2020 | 8/11/2020 | 8/11/2020 | A | FAIL |
Troy Cobbley
|
|
|
As-builts needed showing the increase in candella in the two restrooms, The one and only duct smoke detector tested shut the unit down but did not report to the FACP. All duct smoke detectors will need to be tested. Notification is needed in the marked exit path through the east side office and the 30cd strobe needs to be located as per plans to provide coverage in the short corridor in front of the electrical room.
Need to sound bells at 7am prior to offices opening.
This is for phases 3 ; 4. Phone #: ###-#### Inspection requested via web by James Williams
|
INSP-Sprinkler Rough-in | 2/18/2020 | 2/19/2020 | 2/19/2020 | A | PASS |
Troy Cobbley
|
|
|
The phase 1 and phase 2 fire alarm installation is complete as marked on the plans. One hvac unit in phase 1 is still in need of repairs and verification that the duct smoke detector functions.
Needs to be done at 7:00am Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Alarm Testing | 2/13/2020 | 2/18/2020 | 2/18/2020 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for phjase 1 and phase 2. See the city approved plans for corrections marked in red. Plan mods will be needed prior to a final sign off.
Needs to be done at 7:00am Phone #: ###-#### Inspection requested via web by Sam Ball
|
Issue and Print Permit | | | 11/12/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/8/2019 | | DONE |
|
|
|
|
Alarm Plan Check | 11/8/2019 | | 11/8/2019 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/8/2019 | | DONE |
|
|
|
Passed with review comments.
|
Permit Ready to Issue | | | 11/8/2019 | | DONE |
|
|
|
|
1st review completed | | | 11/5/2019 | | DONE |
|
|
|
Mary is to provide details of phased work.
|
Plan assigned to (Lee) | 11/4/2019 | | 11/4/2019 | | DONE |
Lee G Meredith
|
|
|
|
Intake Approval | | | 11/4/2019 | | PASS |
|
|
|
|
Miscellaneous action | | | 11/4/2019 | | DONE |
|
|
|
Application indicates this is a phased project. Emailed Mary to see if there is an upgrade agreement or other approval for phased work. She is to contact the general contractor to find out.
|
Application received | | | 11/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 2 2019 12:25PM
|