INSP-Final Inspection | 6/22/2020 | 6/22/2020 | 6/22/2020 | A | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection is complete.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 6/17/2020 | 6/18/2020 | 6/18/2020 | P | FAIL |
Jim Page
|
|
|
Replace 155 degree heads in washer/dryer closets to the 175 degree heads as shown on city approved drawings. Relocate overspaced head as discussed.
Call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Supply line flush | 5/29/2020 | 6/1/2020 | 5/29/2020 | A | CANC |
Jim Page
|
|
|
Scheduled for 9am with Stacy at Suez. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | CANC |
Jim Page
|
|
|
Underground hydro. Ready any time, call James before heading out. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
CHANGE STATUS TO (ISS) | | | 5/19/2020 | | DONE |
|
|
|
|
Plan assigned to (Stumbaugh) | 5/11/2020 | | 5/13/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Sprinkler Plan Check | 5/13/2020 | | 5/13/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review Time 1hr
No new devices
|
Permit Ready to Issue | | | 5/13/2020 | | DONE |
|
|
|
plan mod met
|
Plan Modification Accepted | | | 5/11/2020 | | DONE |
|
|
|
Nate requested a plan mod.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2020 | 4/9/2020 | 4/9/2020 | P | DONE |
Jim Page
|
|
|
Hydrostaic test for overhead fire sprinkler piping has been witnessed, no pressure loss observed at riser provided gauge.
Hydrostatic test Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved, cover sticker placed on window.
Tenting inspection, call James with any concerns, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection complete, piping between conditioned spaces approved for cover. No tenting installed at time of inspection, piping requiring tenting not approved for cover.
Tenting and overhead rough, call James before heading out. Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Issue and Print Permit | | | 3/11/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/24/2020 | | 2/26/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/26/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/26/2020 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 2/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/30/2020 | | 2/7/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/7/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 1/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/30/2020 | | 1/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 1/29/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 29 2020 2:18PM
|