INSP-Final Inspection | 6/12/2020 | 6/12/2020 | 6/12/2020 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, final fire sprinkler inspection is complete, irrigation shutdown on flow switch activation witnessed.
|
INSP-Final Inspection | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | FAIL |
Jim Page
|
|
|
Hole was cut into ceiling in master bathroom, tenting has been removed from over top of pipe, area notated had no insulation on top of piping. Provide 175 degree head in master closet, head is within 24 inches of heat register.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire srpinkler piping witnessed at city pressure, no pressure loss onserved at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/13/2020 | 4/14/2020 | 4/14/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Sticker has been placed for cover approval.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/3/2020 | 4/3/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection complete, no tenting installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Issue and Print Permit | | | 2/25/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/21/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/21/2020 | | 2/21/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/21/2020 | | 2/21/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/21/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/21/2020 | | DONE |
|
|
|
met
|
Application received | | | 2/19/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 19 2020 5:02PM
|