INSP-Final Inspection | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection is complete, irrigation shut-down on flow switch activation has been witnessed.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2020 | 6/9/2020 | 6/9/2020 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire srpinkler piping witnessed at city pressure, no pressure loss onserved at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/9/2020 | 4/10/2020 | 4/10/2020 | A | PASS |
Jim Page
|
|
|
All tenting in place at time of inspection, cover is approved. Cover sticker has been placed.
tenting Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
INSP-Sprinkler Rough-in | 4/1/2020 | 4/3/2020 | 4/3/2020 | P | PART |
Jim Page
|
|
|
Rough in inspection complete, no tenting installed at time of inspection, cover is not approved.
Phone #: ###-#### Inspection requested via web by Jonathan Lee
|
Issue and Print Permit | | | 3/20/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/24/2020 | | 2/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 2/28/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/28/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/28/2020 | | DONE |
|
|
|
met
|
Application received | | | 2/24/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2020 9:28AM
|
Intake Approval | | | 2/24/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/24/2020 | | 2/24/2020 | | DONE |
Mark Stumbaugh
|
|
|
|