INSP-Final Inspection | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for TCO phase 1 complete.
Richard Clark is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 8/6/2020 | 8/7/2020 | 8/7/2020 | P | NR |
Jim Page
|
|
|
Area for final inspection not ready
Richard Clark is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Final Inspection | 7/13/2020 | 7/17/2020 | 7/17/2020 | A | NR |
Jim Page
|
|
|
Not ready for final inspection.
Richard Clark is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/16/2020 | 7/16/2020 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact.
Richard Clark is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/15/2020 | 7/15/2020 | A | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact.
Richard Clark is the contact Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/13/2020 | 7/14/2020 | 7/14/2020 | A | PART |
Jim Page
|
|
|
Rough to cover inspection from grid line 8 west is approved for cover, excluding main corridor located south side of building, grid is not installed.
Richard Clark is the contact. Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Richard Clark. is the contact. (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in | 6/29/2020 | 6/30/2020 | 6/30/2020 | A | FAIL |
Troy Cobbley
|
|
|
I called contact, could not leave message as box was full. Went to job site but did not make contact. No inpection performed.
Richard Clark is the contact. Thank you for your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
CHANGE STATUS TO (ISS) | | | 6/19/2020 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/17/2020 | | 6/18/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2020 | | DONE |
Mark Stumbaugh
|
|
|
Review time 1 hr
87 new devices
|
Permit Ready to Issue | | | 6/18/2020 | | DONE |
|
|
|
Plan Mod
|
Plan assigned to (Stumbaugh) | 6/15/2020 | | 6/17/2020 | | DONE |
Mark Stumbaugh
|
|
|
plan mod
|
Plan Modification Accepted | | | 6/15/2020 | | DONE |
|
|
|
plan mod request see Document email
|
INSP-Sprinkler Rough-in | 6/10/2020 | 6/12/2020 | 6/12/2020 | P | FAIL |
Jim Page
|
|
|
Make corrections on drop down nipple 90's as discussed.
Richard Clark is the contact. Thanks! (: Phone #: ###-#### Inspection requested via web by Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/10/2020 | 6/10/2020 | 6/10/2020 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping has been witnessed, no pressure loss observed at riser provided gauge.
Richard Clark is the contact. Thank you for all your hard work! Phone #: ###-#### Inspection requested via web by Stan Beus
|
Issue and Print Permit | | | 5/1/2020 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/30/2020 | | 4/30/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 4/30/2020 | | DONE |
|
|
|
met
|
Plan resubmittals received | | | 4/29/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 4/27/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/27/2020 | | 4/27/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 4/23/2020 | | 4/24/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
1st review completed | | | 4/24/2020 | | FAIL |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 4/23/2020 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 4/23/2020 | | 4/23/2020 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 3/10/2020 | | FAIL |
Mark Stumbaugh
|
|
|
waiting for BLD20-00796 to be issued.
|
Application received | | | 3/9/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 9 2020 9:27AM
|