BLD-Final | 5/13/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
Bo Phone #: ###-####
|
DOC - Permit Finaled | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Wall cover | 5/7/2020 | 5/12/2020 | 5/12/2020 | A | PASS |
Brandon Shaw
|
|
|
Screened- Bo Phone #: ###-####
|
BLD-Energy code compliance | 5/1/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Brandon Shaw
|
|
|
Sreened- Bo Phone #: ###-####
|
BLD-Final | 4/8/2020 | 4/9/2020 | 4/9/2020 | A | FAIL |
Jim Storey
|
|
|
Bo **cleared** Phone #: ###-#### 2 hr pl wall not complet leagers and membrane .// insulation not done.
|
FIRE-Final Inspection | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Jim Page
|
|
|
Previously noted item has been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signatures provided on permit sign off card.
cleared // Bo Phone #: ###-####
|
FIRE-Final Inspection | 3/23/2020 | 3/25/2020 | 3/25/2020 | A | FAIL |
Jim Page
|
|
|
Fire sprinkler riser room is not 1 hour rated as required.
Bo Phone #: ###-####
|
FIRE-Final Inspection | 3/19/2020 | 3/20/2020 | 3/20/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need project related fire alarm and fire sprinkler permits finaled, need all small documents. No inspection performed but we did conference on life safety items.
Bo Phone #: ###-####
|
FIRE-Final Inspection | 3/19/2020 | 3/19/2020 | 3/19/2020 | P | FAIL |
Jim Page
|
|
|
Associated FIR permits for fire alarm and fire sprinkler are not finaled, FIR permits must be finaled before life fire safety inspection can be performed.
Bo Phone #: ###-####
|
BLD-Energy code compliance | 12/11/2019 | 12/13/2019 | 12/13/2019 | P | PART |
Brandon Shaw
|
|
|
partial insulation and vapor barrier for 1st floor north wall and section of east wall to the elevator, and exterior elevator wall. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Exterior sheeting, roof deck sheeting, hardware.
|
BLD-Framing/Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | PASS |
Brandon Shaw
|
|
|
framing hardware - holddown bolts HUD2, HUD5, HUD8 Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Energy code compliance | 9/30/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Brandon Shaw
|
|
|
foundation insulation. Phone #: ###-#### Inspection requested via web by J.C. Murray
|
BLD-Foundation | 9/30/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to puor, pending special inspection...
|
BLD-Footing | 9/30/2019 | 9/30/2019 | 9/30/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by J.C. Murray
|