INSP-Final Inspection | 11/21/2017 | 11/21/2017 | 11/21/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/28/2016 | 9/29/2016 | 9/29/2016 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for Dry system 6 and eastside hose valve system.
|
INSP-Sprinkler Rough-in/Hydro | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping garage dry system 5 complete. 200 psi hydrostatic test for garage dry systems 5 and 7 complete
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2016 | 9/27/2016 | 9/27/2016 | P | CANC |
Jim Page
|
|
|
This inspection request was for 28SEPT2016, this inspection request is cancelled and a new inspection request will be generated for the correct day.
|
INSP-Sprinkler Rough-in | 9/8/2016 | 9/14/2016 | 9/14/2016 | A | CANC |
Jim Page
|
|
|
Inspection request will be completed during hydrostatic testing per conversation with point of contact, Jeff phone number ###-####.
|
INSP-Sprinkler Rough-in | 9/8/2016 | 9/13/2016 | 9/13/2016 | A | CANC |
Jim Page
|
|
|
Inspection request will be performed on 14SEPT2016.
|
INSP-Sprinkler Rough-in | 9/8/2016 | 9/12/2016 | 9/12/2016 | A | CANC |
Jim Page
|
|
|
Inspection will be performed on a later inspection request, inspection request reshedule has been coordinated with job foreman (Jeff ###-####). Shilo will call to schedule the inspection request for coordinated day.
|
INSP-Sprinkler Rough-in | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping located above restroom hardlids in basement level and level one complete, overhead fire sprinkler piping located above hardlids at basement level and level 1 approved for cover.
|
INSP-Final Inspection | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PASS |
Thomas Walsh
|
|
|
Testof the four (4) dry pipe systems protecting the underground parking garage, including fire alarm interface of low-air, waterflow and tampers. and trip tests of the dry-pipe valves. All tested satisfactorily. NOTE: FDC on 11th street not functional yet. to be hydrotested and flushed.
|
INSP-Final Inspection | 7/2/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Thomas Walsh
|
|
|
Flush test of the FS U/G supply line from the 11th street connection to the pump header (pump was bypassed). Flushed clear after 2 attempts. OK to connect this supply line to the pump suction feed main.
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | PASS |
Thomas Walsh
|
|
|
Completion of 24 hour air test of four (4) dry pipe valves located in the U/G parking garage. All PASSED.
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2015 | 7/6/2015 | 7/6/2015 | P | CANC |
Thomas Walsh
|
|
|
This is the wrong permit # called in for a diferent part of the building. See FIR 13-00725 for the proper permit and the inspection for today (7/6).
|
INSP-Sprinkler Rough-in | 7/2/2015 | 7/6/2015 | 7/6/2015 | P | PART |
Thomas Walsh
|
|
|
24 hour air test of four (4) dry pipe valves located in the U/G parking garage, including the water room, pump room and two systems supplying the north end PG. All measured 43 psi @ 11:30am. Will retest tomorrow - same time to ensure pass. Also hydrotest - 200 psi @ 2 hrs - for dry pipe valve supplying two different hose valves in the PG. - PASSED
|
INSP-Sprinkler Rough-in/Hydro | 7/1/2015 | 7/2/2015 | 7/2/2015 | A | PASS |
Thomas Walsh
|
|
|
Hydrotest of four (4) of the U/G parking garage dry pipe systems, and three (3) dry pipe systems serving the abovegrade stairs of stairs C1, B2, and B1. All passed the 200 psi @ 2 hrs. test.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2015 | 7/1/2015 | 7/1/2015 | A | CANC |
Thomas Walsh
|
|
|
Wrong permit called in for this inspection. See FIR13-00725 for inspections completed today (7/1).
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrostatic test of FS U/G supply line from 11th St. city connection to main BFP in basement riser room. PASSED
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2015 | 6/19/2015 | 6/19/2015 | P | PEND |
Thomas Walsh
|
|
|
Recieved pump report from fire pump rep., stating the results from pump test on 6/17. Report indicated that 150% test could not be performed. I informed Jeff (Shilo) that we would require the pump rep. conduct the next test to ensure that the pump is operating correctly, and that flows at the 150% of pump capacity can be obtained.
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2015 | 6/18/2015 | 6/18/2015 | P | CANC |
Thomas Walsh
|
|
|
Wrong permit called in for the systems inspected.
|
INSP-Sprinkler Rough-in/Hydro | 6/16/2015 | 6/17/2015 | 6/18/2015 | P | PART |
Thomas Walsh
|
|
|
Initial fire pump test, witnessed by Tom Walsh and Tim Frost. Test was conducted at various flows, including no flow, 1000gpm and attempted to conduct 1500 gpm test, but could not flow this portion of the test, due to pressure regulator installed after the pump. NOTE: Pump test will have to beconducted/ witnessed again when the generator and fire alarm systems interface is completed.
|
INSP-Sprinkler Rough-in/Hydro | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PART |
Thomas Walsh
|
|
|
Thrust block inspection of fire service underground supply line and FDC supply line for 11th street connection - hydrotest could not be conducted because city connection could not be made, due to a faulty connector. The contractor assumes all risk of burying pipe prior to hydrotest.
|
INSP-Sprinkler Rough-in | 6/11/2015 | 6/11/2015 | 6/11/2015 | P | NR |
Thomas Walsh
|
|
|
Concrete thrust blocks not installed yet - will reschedule inspection, and probably hydrotest for tomorrow.
|
INSP-Sprinkler Rough-in | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | CANC |
Thomas Walsh
|
|
|
This is an underground to cover inspection. Concrete to arrive at 11:30am. We request a 12pm or 12:30pm inspection. Bryan is the contact for scheduling. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotest/inspection of above grade parking garage dry pipe systems for floors 3 and 4 - both PASSED
|
INSP-Sprinkler Rough-in | 5/28/2015 | 5/29/2015 | 5/29/2015 | A | PASS |
Thomas Walsh
|
|
|
FSUG flush of the 9th street feed main from city connection to parking garage bulk feed main (just before pump connection) - flushed clear after 2 attempts.
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | PART |
Thomas Walsh
|
|
|
FS U/G hydrotest - 9th street connection. 200psi @ 2 hours - from PIV at street to first control valve in basement (8" x approx. 100ft.) PASSED. NOTE: 11th St. tie-in not tested yet.
|
INSP-Sprinkler Rough-in | 4/23/2015 | 4/24/2015 | 4/24/2015 | A | PART |
Katie Marron
|
|
|
Underground 8" main from PIV to underground parking garage OK to cover. Main has 4' of coverage at PIV due to location of united water's main, and then drops to over 5' of coverage at bldg connection.
|
INSP-Sprinkler Rough-in | 4/15/2015 | 4/16/2015 | 4/16/2015 | P | NR |
Katie Marron
|
|
|
Not ready for inspection per phone conversation from Contractor. Pending PIV location determination.
|
INSP-Sprinkler Rough-in | 4/15/2015 | 4/15/2015 | 4/15/2015 | P | CANC |
Katie Marron
|
|
|
Cancelled to be rescheduled per phone conversation with contractor.
|
INSP-Sprinkler Rough-in | 9/8/2014 | 9/9/2014 | 9/9/2014 | P | CANC |
Forrest France
|
|
|
This is an ug to cover. John is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 4/16/2014 | 4/17/2014 | 4/17/2014 | A | PART |
Forrest France
|
|
|
Preliminary walkthrough of the basement level, temp standpipe, and project conditions.
|