INSP-Final Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 | A | PASS |
Jim Page
|
|
|
Inspection completed on 8/27/2015 by Tom Walsh, was labeled as a rough in inspection, not a final. Inspection notes state final inspections completed.
|
INSP-Sprinkler Rough-in/Hydro | 8/26/2015 | 8/27/2015 | 8/27/2015 | A | PASS |
Thomas Walsh
|
|
|
Final inspection and sign off for this permit.
|
INSP-Final Inspection | 8/26/2015 | 8/26/2015 | 8/27/2015 | A | PASS |
Thomas Walsh
|
|
|
See notes under previous inspection.
|
INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | CANC |
Thomas Walsh
|
|
|
Inspection for this permit canceled. Loking for inspection of Tower 3 residential floors only.
|
INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PART |
Thomas Walsh
|
|
|
Fire sprinkler system inspection for Towers 3 & 4 - fire alarm interface only, i.e. tampers for standpipe control valves, and inspection of sprinklers for the corridors and stairwells serving Towers 3 & 4 - No unit inspections were conducted.
|
INSP-Alarm Testing | 8/17/2015 | 8/17/2015 | 8/17/2015 | P | PART |
Thomas Walsh
|
|
|
Trip test of DP Valve for the north side of the parking garage. Ann accelerator was added to this system due to failure of last trip test. Trip test past at 35 seconds to waterflow.
|
INSP-Final Inspection | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | FAIL |
Thomas Walsh
|
|
|
Final inspection for the dry pipe valve protecting the north parking garage. Trip test resulted in 85 seconds to water at the IT, so the contractor agreed to install an accelerator. Will retest after this is installed.
|
INSP-Sprinkler Rough-in | 7/2/2015 | 7/6/2015 | 7/6/2015 | A | PART |
Thomas Walsh
|
|
|
Completion of the 24 hour air test of the the three dry pipe systems protecting the parking garage and fitness area. PASSED Conducted a trip test of the two dry systems protecting the parking garage. The system to the north flowed at 90 seconds, while the system to the south flowed at 50 seconds. Also tested fire alarm interface of these systems, including water flow, tampers, low-air, etc. All tested OK.
|
INSP-Alarm Testing | 7/1/2015 | 7/1/2015 | 7/1/2015 | P | PART |
Thomas Walsh
|
|
|
Fire alarm interface inspection of the 2 dry systems protecting the grade level parking garage, including flow testing, low air alarms, tampers, etc. The 24 hour air test started after all alarm features were tested. Complete air test will be conducted next day.
|
INSP-Sprinkler Rough-in | 6/29/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrostatic test of two Dry Pipe systems protecting the grade level parking garage - 200 psi @ 2 hours - PASSED
|
INSP-Sprinkler Rough-in/Hydro | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | PASS |
Thomas Walsh
|
|
|
Hydrotests of two (2) dry pipe systems protecting the grade level parking garage. - 200 psi @ 2 hrs - PASSED
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2015 | 6/30/2015 | 6/30/2015 | P | CANC |
Thomas Walsh
|
|
|
Wrong permit called in for this area. See FIR14-00531 for inspections completed today (6/30).
|
INSP-Sprinkler Rough-in | 4/24/2015 | 4/28/2015 | 4/28/2015 | A | PART |
Katie Marron
|
|
|
Rough-in of parking garage complete. Areas with hard lid ok to cover. One drop to be fixed to maintain 6' min separation (see plan) and a couple lines to be straightened from ceiling contractor disturbing/twisting when installing ceiling grid. Before final ensure temp construction walls are demolished or sprinkler lines/heads will need to be adjusted.
|
INSP-Sprinkler Rough-in | 3/12/2015 | 3/13/2015 | 3/13/2015 | A | PART |
Troy Cobbley
|
|
|
Re- inspection of the 5th floor, tower 3. See the city approved plans for the apartments with corrections from 3/12/2015 that have been corrected and piping can be covered. One apartment still has missing upright head.
|
INSP-Sprinkler Rough-in | 3/11/2015 | 3/12/2015 | 3/12/2015 | A | PART |
Troy Cobbley
|
|
|
Requesting RTC inspection on the 5th floor, tower 3. Todays inspection included six apartments. See city approved plans for two of the six that are ok to cover as marked "ok" with todays date. The other four are mark for overspaced heads, blocked heads and missing heads and the piping can not be covered.
|
INSP-Sprinkler Rough-in | 3/4/2015 | 3/6/2015 | 3/6/2015 | A | PART |
Forrest France
|
|
|
Completed rough-in inspection for tower 3 podium level living units as noted on plans. Missing drops and sprinklers at unit 206 bedroom and closet, provide standard pendent heads per plan at both trash rooms, unit 215 is missing sprinkler coverage at a closet and need to relocate one head too close to a ceiling fan junction box. Discussed floor control manifold location and configurations.
|
INSP-Sprinkler Rough-in | 1/30/2015 | 2/2/2015 | 2/2/2015 | P | PART |
Forrest France
|
|
|
Inspection intended for project related FIR14-00531 - Tower 2 5th floor living units and common corridor rough in.
|
INSP-Sprinkler Rough-in | 1/30/2015 | 1/30/2015 | 1/30/2015 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | PART |
Forrest France
|
|
|
Inspection for concealed space coverage and pendent head drops installed to date at tower 2 5th floor pods only- Soffits not yet built
|
INSP-Sprinkler Rough-in | 12/10/2014 | 12/12/2014 | 12/12/2014 | A | PART |
Forrest France
|
|
|
Rough-in inspection completed for tower one 4th floor, 3rd floor and podium levels room units 430 - 437, 330 - 337, 230 - 237. Discussed obstructions that may occur due to soffits not yet built, temps at heads in HVAC closets and in proximity to diffusers, fire stop material compatibility with CPVC. Coverage at stairways not yet installed.
|
INSP-Sprinkler Rough-in | 7/24/2014 | 7/25/2014 | 7/25/2014 | A | CANC |
Scott Arellano
|
|
|
Permit holder not present during inspection. Inspection was for underground cover only. Inspection could not be performed because underground piping had been covered up by the jobsite excavator. Informed excavator that the fire sprinkler pipe needed to be exposed for the inspection to be completed. Communicated with the permit applicant on the status of the inspection and advised him to call the inspection back in when the pipe and fittings have been uncovered.
|