Permit Information
Permit NumberFIR14-00430
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1011 S LA POINTE ST
Project NameBoise Heights
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of protecting a parking garage with (2) dry systems. The remainder of the building and the standpipes will be under separate permits. Each systems is design as double trees with 1 ½” line with 3” and 4” mains.

(BOISE HEIGHTS APARTMENTS) Fire sprinklers used for area increase, story increase, and for fire area. To construct a 5 story garage and residential apartment building (one story garage at grade and 4 stories of residential apartments above). The 1st story was constructed under early start permit BLD14-00377. The garage and adjacent areas will have a total floor area of about 72,725 square feet and will be of Type I-A construction. An office area will also be located on the 1st story next to the garage and will have a floor area of about 2,448 square feet. It will be of Type V-A construction and will be separated from the garage by a 3-hr fire wall. A 3-hr horizontal assembly will separate the garage from the apartment building above. Each story of the apartment building will have a total floor area of about 42,646 square feet. A 2-hr fire wall will separate the apartment building into 2 “buildings” for building area reasons and to provide a horizontal exit. There will be a total of 131 apartment units (36 four bedroom units, 4 three bedroom units, 90 two bedroom units, and 1 one bedroom/model unit). There will be a total of 337 bedrooms. All apartment units are required to comply as Type B dwelling units. Three apartment units are required to comply as Type A dwelling units. A 1,187 square foot fitness building will also be constructed above the garage under this permit. It will have a 732 square foot exercise room. A 2,235 square foot elevated pool deck will be constructed next to the fitness building. Required Special Inspections include soils, concrete reinforcing steel including prestressing tendons, concrete, welding, masonry, spray applied fire-proofing, and wood shear walls. The work is required to comply with the approved drawings, with the plan review report, with the structural design, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/24/201511/25/201511/25/2015APASS
DetailsJim Page
Inspection completed on 8/27/2015 by Tom Walsh, was labeled as a rough in inspection, not a final. Inspection notes state final inspections completed.
INSP-Sprinkler Rough-in/Hydro8/26/20158/27/20158/27/2015APASS
DetailsThomas Walsh
Final inspection and sign off for this permit.
INSP-Final Inspection8/26/20158/26/20158/27/2015APASS
DetailsThomas Walsh
See notes under previous inspection.
INSP-Final Inspection8/20/20158/21/20158/21/2015ACANC
DetailsThomas Walsh
Inspection for this permit canceled. Loking for inspection of Tower 3 residential floors only.
INSP-Final Inspection8/19/20158/20/20158/20/2015APART
DetailsThomas Walsh
Fire sprinkler system inspection for Towers 3 & 4 - fire alarm interface only, i.e. tampers for standpipe control valves, and inspection of sprinklers for the corridors and stairwells serving Towers 3 & 4 - No unit inspections were conducted.
INSP-Alarm Testing8/17/20158/17/20158/17/2015PPART
DetailsThomas Walsh
Trip test of DP Valve for the north side of the parking garage. Ann accelerator was added to this system due to failure of last trip test.
Trip test past at 35 seconds to waterflow.
INSP-Final Inspection7/10/20157/10/20157/10/2015PFAIL
DetailsThomas Walsh
Final inspection for the dry pipe valve protecting the north parking garage. Trip test resulted in 85 seconds to water at the IT, so the contractor agreed to install an accelerator. Will retest after this is installed.
INSP-Sprinkler Rough-in7/2/20157/6/20157/6/2015APART
DetailsThomas Walsh
Completion of the 24 hour air test of the the three dry pipe systems protecting the parking garage and fitness area. PASSED
Conducted a trip test of the two dry systems protecting the parking garage. The system to the north flowed at 90 seconds, while the system to the south flowed at 50 seconds.
Also tested fire alarm interface of these systems, including water flow, tampers, low-air, etc. All tested OK.
INSP-Alarm Testing7/1/20157/1/20157/1/2015PPART
DetailsThomas Walsh
Fire alarm interface inspection of the 2 dry systems protecting the grade level parking garage, including flow testing, low air alarms, tampers, etc. The 24 hour air test started after all alarm features were tested. Complete air test will be conducted next day.
INSP-Sprinkler Rough-in6/29/20156/30/20156/30/2015PPASS
DetailsThomas Walsh
Hydrostatic test of two Dry Pipe systems protecting the grade level parking garage - 200 psi @ 2 hours - PASSED
INSP-Sprinkler Rough-in/Hydro6/30/20156/30/20156/30/2015PPASS
DetailsThomas Walsh
Hydrotests of two (2) dry pipe systems protecting the grade level parking garage.
- 200 psi @ 2 hrs - PASSED
INSP-Sprinkler Rough-in/Hydro6/29/20156/30/20156/30/2015PCANC
DetailsThomas Walsh
Wrong permit called in for this area. See FIR14-00531 for inspections completed today (6/30).
INSP-Sprinkler Rough-in4/24/20154/28/20154/28/2015APART
DetailsKatie Marron
Rough-in of parking garage complete. Areas with hard lid ok to cover. One drop to be fixed to maintain 6' min separation (see plan) and a couple lines to be straightened from ceiling contractor disturbing/twisting when installing ceiling grid. Before final ensure temp construction walls are demolished or sprinkler lines/heads will need to be adjusted.
INSP-Sprinkler Rough-in3/12/20153/13/20153/13/2015APART
DetailsTroy Cobbley
Re- inspection of the 5th floor, tower 3. See the city approved plans for the apartments with corrections from 3/12/2015 that have been corrected and piping can be covered. One apartment still has missing upright head.
INSP-Sprinkler Rough-in3/11/20153/12/20153/12/2015APART
DetailsTroy Cobbley
Requesting RTC inspection on the 5th floor, tower 3. Todays inspection included six apartments. See city approved plans for two of the six that are ok to cover as marked "ok" with todays date. The other four are mark for overspaced heads, blocked heads and missing heads and the piping can not be covered.
INSP-Sprinkler Rough-in3/4/20153/6/20153/6/2015APART
DetailsForrest France
Completed rough-in inspection for tower 3 podium level living units as noted on plans. Missing drops and sprinklers at unit 206 bedroom and closet, provide standard pendent heads per plan at both trash rooms, unit 215 is missing sprinkler coverage at a closet and need to relocate one head too close to a ceiling fan junction box. Discussed floor control manifold location and configurations.
INSP-Sprinkler Rough-in1/30/20152/2/20152/2/2015PPART
DetailsForrest France
Inspection intended for project related FIR14-00531 - Tower 2 5th floor living units and common corridor rough in.
INSP-Sprinkler Rough-in1/30/20151/30/20151/30/2015APART
DetailsForrest France
INSP-Sprinkler Rough-in1/28/20151/29/20151/29/2015APART
DetailsForrest France
Inspection for concealed space coverage and pendent head drops installed to date at tower 2 5th floor pods only- Soffits not yet built
INSP-Sprinkler Rough-in12/10/201412/12/201412/12/2014APART
DetailsForrest France
Rough-in inspection completed for tower one 4th floor, 3rd floor and podium levels room units 430 - 437, 330 - 337, 230 - 237. Discussed obstructions that may occur due to soffits not yet built, temps at heads in HVAC closets and in proximity to diffusers, fire stop material compatibility with CPVC. Coverage at stairways not yet installed.
INSP-Sprinkler Rough-in7/24/20147/25/20147/25/2014ACANC
DetailsScott Arellano
Permit holder not present during inspection. Inspection was for underground cover only. Inspection could not be performed because underground piping had been covered up by the jobsite excavator. Informed excavator that the fire sprinkler pipe needed to be exposed for the inspection to be completed. Communicated with the permit applicant on the status of the inspection and advised him to call the inspection back in when the pipe and fittings have been uncovered.