Permit NumberFIR19-00792
StatusFinaled
Name ALPINE FIRE SPRINKLERS NC
Site Address 11964 W FAIRVIEW AVE
Project NameVillage East Apartments Bldg K
Customer Number 
ePlanReviewYes
Description
Building "K" - 4 stories - New 13R fire sprinkler system. Dedicated fire line installed under FIR19-00775. residential
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/11/20208/12/20208/12/2020PPASS
DetailsGreg Ruxton
Fire Sprinkler Final Passed.

SCREENED // Tanner Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro8/12/20208/12/20208/12/2020PPASS
DetailsTroy Cobbley
Overhead hydro of the 3rd and 4th floors witnessed with no pressure loss.

Screened- Tanner Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro8/10/20208/11/20208/11/2020APART
DetailsTroy Cobbley
The standpipe, 1st and 2nd floor hydro tests witnessed. 3rd and 4th would not hold pressure.

Tanner - */Screened/* Phone #: ###-####
INSP-Sprinkler Rough-in6/18/20206/19/20206/19/2020APASS
DetailsTroy Cobbley
Rough-in for the stand pipe passed. Will need hydro and painted as discussed.

Tanner *screened* Phone #: ###-####
INSP-Sprinkler Rough-in6/1/20206/2/20206/2/2020APASS
DetailsTroy Cobbley
The piping above the soffits for the first and second floors can be covered. Tanner *screened* Phone #: ###-####
INSP-Sprinkler Rough-in5/22/20205/22/20205/22/2020PPART
DetailsTroy Cobbley
Third floor piping in soffits is ok for cover. Plans are in review status for some reason. If changes in piping is required, piping will need to be uncovered. Tanner Phone #: ###-####
INSP-Sprinkler Rough-in5/20/20205/20/20205/20/2020PPASS
DetailsTroy Cobbley
The piping above the 4th floor soffits is ok for cover. Tanner *screened* Phone #: ###-####
INSP-Sprinkler Rough-in5/5/20205/6/20205/7/2020APASS
DetailsTroy Cobbley
The heat tape/insulation in the breeze ways is ok for cover. *Screened* Tanner Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/17/20203/18/20203/18/2020APASS
DetailsTroy Cobbley
Tenting passed. Piping can be covered except for the piping that crosses the breeze way. It will need separate inspection when the heat tape has been installed and inspected.

Tanner Phone #: ###-####
INSP-Sprinkler Rough-in3/13/20203/13/20203/13/2020PFAIL
DetailsTroy Cobbley
Need the flexible cplgs installed and then hydro tested. WIll need the pressure guage moved back to the top when hydro is over. Tanner Phone #: ###-####
INSP-Sprinkler Rough-in2/27/20202/27/20202/27/2020PPASS
DetailsTroy Cobbley
The new plans match the actual main pipe routing. Piping can not be covered until the tenting is approved. There is still the issue with the possible relocation of the stand pipe.


Tanner Phone #: ###-####
INSP-Sprinkler Rough-in2/25/20202/26/20202/26/2020ACANC
DetailsTroy Cobbley
The plan mods were not on site when I arrived for the inspection. Will need to be rescheduled.

Tanner Phone #: ###-####
INSP-Sprinkler Rough-in2/19/20202/20/20202/20/2020AFAIL
DetailsTroy Cobbley
Tenting not done yet. I let Tanner know they will need to provide design and approved drawings of any changes including the relocation of the stand pipe.

Tanner Phone #: ###-####
INSP-Sprinkler Rough-in2/19/20202/19/20202/19/2020PPART
DetailsTroy Cobbley
Piping rough-in passed. As-buillts are needed showing the supply pipe routing change for the 4th floor. Piping can not be covered until a tenting inspection has been passed. The stand pipe was not inspected due to a relocation request.

Tanner Phone #: ###-####