Permit Information
Permit NumberMIS20-00070
StatusIssued
Name BOISE BOMB SHELTER LLC
Site Address 600 W CURLING DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Dirt work without an erosion permit
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
ESC-Conference5/19/20205/20/20205/28/2020PPEND
DetailsAndy J. Long
ESC-Conference4/29/20205/13/20205/19/2020PPEND
DetailsAndy J. Long
Not vegetated. No muddy runoff observed, but a lot of runoff from this building and the Crane Creek parking lot
ESC-Conference4/29/20205/13/20205/12/2020ADONE
DetailsAndy J. Long
No sediment leaving site. Hill doesn't seem to be vegetating. Follow up scheduled. BLD permit is still open

note - entry is from 4/29. new inspection on schedule
ESC-Conference4/9/20204/28/20204/29/2020PPEND
DetailsAndy J. Long
ESC-Conference3/24/20204/9/20204/9/2020PPEND
DetailsAndy J. Long
No new activity or erosion. No vegetation establishing yet, still need to work on roof access grading.
ESC-Conference3/24/20203/24/20203/24/2020PCANC
DetailsAndy J. Long
ESC-Conference3/4/20203/18/20203/24/2020PPEND
DetailsAndy J. Long
Corrective actions have been intiated at site:
- Perimeter sediment control wattle installed along Curling as requested.
- Placed wattle to slow down runoff on the roof access road.
- No loose dirt on sidewalk or parking area
- Owner Jon states hillside has been seeded as requested.

Notified Jon that the wattle placement and clean up was good, but the wattles need to be trenched into the ground so water does not flow under them.

Will check vegetation establishment and wattle trenching in 2 weeks.
ESC-Conference2/27/20202/28/20203/4/2020APEND
DetailsAndy J. Long
Met with building owner Jon ###-####. Disturbance occurred digging out side of the shelter to install new fire & sprinkler lines.

Review stormwater and erosion controls that should be implemented.

1. Berm road to prevent flow of water down the roof access to the slope
2. Rake in seeding into the bare/disturbed areas
3. Install perimeter control wattles around disturbed slope
4. Install slope interupting/water check wattles on the roof access road.

Will follow up in 2 weeks.

ESC-Conference5/28/20206/2/2020 P 
DetailsAndy J. Long