Permit Information
Permit NumberBLD17-04686
StatusFinaled
Name ANDERSEN CONSTRUCTION COMPANY IDAHO
Site Address 1005 W MAIN ST
Project NameJohn Alden Reno & addition
Customer Number 
ePlanReviewYes
Description
(JOHN ALDEN BUILDING) BO & AFM MODIFICATION ATTACHED TO CASE: MECHANICAL ROOF WELL AND (2) 1,680 SQ. FT. AREAS ON 2ND & 3RD FLOORS ALLOWED SPRINKLERS FOR SUBSTITUTION FOR GIRDERS & JOISTS, HOWEVER DECK & SUPPORTING COLUMNS WILL BE 1HR. RATED AND SUPPORTING WALLS 2HR. RATED. "PLAN MODIFICATION 2: TO CONSTUCT AN ADDIOTNAL HALLWAY, TENANT DEMISING WALL AND MODIFY THE STOREFRONT"" ""PLAN MODIFICATION TO ADD AN ADDITIONAL STAIRWAY BETWEEN THE 3rd AND 4th FLOORS"" Permit for core and shell upgrades and the addition of a 5,330 sq. ft. 5th story to the building with work to include, acessible restrooms, minor space reconfiguations and the installation of a new elevator. A separate permit will be required for the interior build out of the tenant spaces. This building is fully fire sprinklered. Separate fire sprinkler and fire alarm permits will be required; as regulated by Boise Fire Department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  5/1/2019 DONE
BLD-Final4/25/20194/25/20194/25/2019ADONE
DetailsBob Archibald
All associated permits are finaled.
DOC - C/O Approved  4/25/2019 DONE
BLD-Final4/23/20194/24/20194/24/2019APASS
DetailsDave Hannah
Pete Phone #: ###-####
BLD-Final3/18/20193/18/20193/18/2019PPASS
DetailsDave Hannah
Pete Phone #: ###-####
BLD-Final3/6/20193/7/20193/7/2019APASS
DetailsDave Hannah
Tom Phone #: ###-#### ok for tco
FIRE-Conference1/18/20191/22/20191/22/2019ADONE
DetailsJim Page
Fire conference complete.

Tyler Phone #: ###-####
BLD-Final1/3/20191/4/20191/4/2019APART
DetailsDave Hannah
Pete Phone #: ###-#### ok for tco
FIRE-Final Inspection1/3/20191/3/20191/3/2019PPASS
DetailsJim Page
Final life fire safety inspection for core and shell only complete, Tenant improvements are under a seperate permit and is currently under construction.

KEITH Phone #: ###-####
BLD-Final12/28/201812/28/201812/31/2018PNR
DetailsDave Hannah
Pete Phone #: ###-####
FIRE-Final Inspection12/28/201812/28/201812/28/2018PFAIL
DetailsJim Page
Exposed combustible material in basement that is no covered by fire sprinklers. Need FIR permits for fire alarm and fire sprinkler finaled before life safety can be completed. Install sheetrock in level 1 elevator lobby, sprinkler head not installed because of no sheetrock. Provide signage for exterior showing which stairwell has roof top access and the one that does not. Still need to test emergency lighting.

Mop sink on level 4 leaked down to level 3 saturating the monitoring modules for the fire alarm system, leak needs to be fixed to prevent false alarms.

Pete Phone #: ###-####
FIRE-Final Inspection12/27/201812/27/201812/27/2018PFAIL
DetailsJim Page
Project not ready for life fire safety.

Phone #: ###-####
Plan Reviewer's activity  12/19/2018 DONE
DetailsJason Blais
BUILDING OFFICIAL AND ASSISTANT FIRE MARSHAL MODIFICATION APPROVAL ATTACHED TO THIS CASE UNDER DOCUMENTS): TYPE OF CONSTRUCTION III-A, HOWEVER, MECHANICAL ROOF WELL AND (2) 1,680 SQ. FT. AREAS ON 2ND & 3RD FLOORS ALLOWED SPRINKLERS FOR SUBSTITUTION FOR GIRDERS & JOISTS, HOWEVER DECK & SUPPORTING COLUMNS WILL BE 1HR. RATED AND SUPPORTING WALLS 2HR. RATED.
BLD-Conference12/11/201812/12/201812/12/2018ADONE
DetailsDave Hannah
Pete Phone #: ###-####
Inspection Record Card- Bld  12/11/2018 DONE
BLD-Conference12/7/201812/7/201812/10/2018PDONE
DetailsDave Hannah
Pete Phone #: ###-####
FIRE-Conference11/19/201811/19/201811/19/2018ADONE
DetailsJim Page
Signage discussed for pruposed TCO, temporary signage can be used if a TCO is aggress upon, permenant signage needs to be in place for final C of O.
FIRE-Final Inspection11/16/201811/19/201811/19/2018ACANC
DetailsJim Page
Request is for a conference, not a final. This request is cancelled.

Tyler Phone #: ###-####
BLD-Other10/25/201810/26/201810/29/2018PPART
DetailsDave Hannah
Tyler-fire caulking Phone #: ###-####
BLD-Wall Bracing10/8/201810/8/201810/8/2018PPASS
DetailsDave Hannah
5th fl - Pete Phone #: ###-####
BLD-Wall Bracing9/27/20189/27/20189/27/2018PPASS
DetailsDave Hannah
Pete Phone #: ###-####
BLD-Framing/Rough-in9/19/20189/19/20189/24/2018PPASS
DetailsDave Hannah
5th fl // Pete Phone #: ###-####
BLD-Wall Bracing9/21/20189/21/20189/21/2018PPASS
DetailsDave Hannah
Pete Phone #: ###-####
BLD-Framing/Rough-in9/17/20189/17/20189/17/2018PPART
DetailsDave Hannah
framing 5th floor exterior walls // Pete Phone #: ###-#### ok to shear
BLD-Wall Bracing9/12/20189/12/20189/13/2018PCANC
DetailsDave Hannah
2nd floor exterior shear // Pete Phone #: ###-#### ok to cover ext wall
CHANGE STATUS TO (ISS)  9/13/2018 DONE
Plan Mod
Inspection Record Card- Bld  9/13/2018 DONE
BLD-Framing/Rough-in9/6/20189/6/20189/6/2018PPASS
DetailsDave Hannah
4th fl exterior framing - Pete Phone #: ###-####
OVERRIDE  9/6/2018  
Plan assigned to (CDM)8/21/20188/21/20189/6/2018 PASS
DetailsCarl D Madsen
plan mod
Routing - PLAN CHECK8/23/2018 9/6/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  9/6/2018 DONE
Permit Ready to Issue  9/6/2018 DONE
MET
Need Revised Cert of Value from GC for additional value for Plan Mod. DO NOT REISSUE (see emails to and from Tyle McIntyre 9/12/18)
BLD-Framing/Rough-in9/4/20189/4/20189/4/2018PPART
DetailsDave Hannah
4th fl // Pete Phone #: ###-#### restroom ok and east side parepit
BLD-Framing/Rough-in8/30/20188/30/20188/30/2018PFAIL
DetailsDave Hannah
4th, bathroom, roof- Keth Phone #: ###-####
Routing - FIRE8/23/20188/23/20188/24/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - Design Review8/23/2018 8/24/2018 PASS
DetailsAndrea Tuning
Plan Modification Accepted  8/21/2018 DONE
Plan Modification application accepted for Extension of 1st floor tenant hallway to capture final tenant configuration as well as new demising walls between ground floor tenants. New tenant storefront with direct access to street will be added that matches previously approved storefront doorways and replaces existing windows.
BLD-Framing/Rough-in8/20/20188/20/20188/20/2018PPART
DetailsDave Hannah
Tyler Phone #: ###-#### roof framing 1st floor
BLD-Framing/Rough-in8/6/20188/6/20188/6/2018PPART
DetailsDave Hannah
Pete Phone #: ###-#### third floor restrooms ok and parapet on north side ok
BLD-Framing/Rough-in7/23/20187/23/20187/23/2018PPART
DetailsDave Hannah
Pete Phone #: ###-#### second floor rest rooms ok
BLD-Conference7/10/20187/11/20187/11/2018ADONE
DetailsDave Hannah
pete Phone #: ###-####
CHANGE STATUS TO (ISS)  7/2/2018 DONE
Inspection Record Card- Bld  7/2/2018 DONE
OVERRIDE  6/18/2018  
Permit Ready to Issue  6/18/2018 DONE
plan mod so please do not re issued
Need
Cert of Value
hourly fee was paid but still need the rev cert of val for plan mod
Plan assigned to (CDM)5/2/20185/2/20186/16/2018 PASS
DetailsCarl D Madsen
Plan Mod
Routing Off Site - STRUCTURAL6/2/2018 6/16/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  6/16/2018 DONE
BLD-Conference5/31/20186/1/20186/1/2018ADONE
DetailsDave Hannah
Pete Phone #: ###-#### needs engineer field judgement
FIRE-Conference5/25/20185/29/20185/29/2018ADONE
DetailsJim Page
Fire conference complete.

Pete Phone #: ###-####
Routing - PLAN CHECK5/2/2018 5/26/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL5/9/2018 5/26/2018 FAIL
DetailsCarl D Madsen
Plan Modification Accepted  5/2/2018 DONE
Plan Mod application, demolish rectangular opening in 4th floor to provide an opening for a future communicating stair between 3 & 4th floors. Demolish existing column at 3rd floor, and replace it with a new column in a new location and a new beam.
CHANGE STATUS TO (ISS)  4/25/2018 DONE
as per Bill V-change status to ISS-contractor is going to finish the job after all-WRONG PERMIT
CHANGE STATUS TO (RDY)  4/25/2018 DONE
change status to RDY-i wqas in the wrong permit
Telephone call  4/25/2018 DONE
emailed the fees due to Tyler
Inspection Record Card- Bld  4/25/2018 DONE
Issue PAID IN FULL permit  4/25/2018 DONE
Routing - PLANNING2/13/2018 4/24/2018 PASS
DetailsSusan Riggs
No Review required per Susan Riggs in Eplan
OVERRIDE  4/23/2018  
Routing - FIRE4/18/20184/18/20184/23/2018 PASS
DetailsErika Akin
Attached revised comments to case. Proposed fiire pump was removed from project.
Plan assigned to (CDM)2/13/20182/13/20184/23/2018 PASS
DetailsCarl D Madsen
John Alden Building
PLANS/APPL TAKEN TO FRONT DESK  4/23/2018 DONE
Permit Ready to Issue  4/23/2018 DONE
ALL MET-NEED
RP-met
GC FORM-met
REVISED CERT-met
Routing Off Site - STRUCTURAL4/18/2018 4/21/2018 PASS
DetailsCarl D Madsen
Routing - PLAN CHECK4/18/2018 4/21/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/12/2018 4/12/2018 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK4/2/2018 4/12/2018 FAIL
DetailsCarl D Madsen
Routing - PLUMBING4/2/2018 4/5/2018 PASS
DetailsBill VanDegrift
1) remove P102
2) P303 doesn't have stamp, install per ISPC
Routing - MECHANICAL4/2/2018 4/4/2018 PASS
DetailsTroy James
Route to Impact Fee Review3/17/20183/20/20183/19/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  3/17/2018 DONE
Routing - PLAN CHECK2/13/2018 3/17/2018 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL2/13/2018 3/16/2018 FAIL
DetailsCarl D Madsen
Routing - FIRE2/13/20182/13/20182/26/2018 FAIL
DetailsScott Arellano
Attached comments to case and emailed architect
Routing PW Environmental2/13/2018 2/21/2018 PASS
DetailsRick Christenson
Grease Interceptor shown for future use.
Routing - Erosion and Sediment2/13/2018 2/20/2018 PASS
DetailsAndy J. Long
ESC plan waiver request approved. Major TI. Need to designate valid ESC Responsible Person for contractor.
Routing - MECHANICAL2/13/2018 2/15/2018 FAIL
DetailsTroy James
Routing - PLUMBING2/13/2018 2/15/2018 FAIL
DetailsBill VanDegrift


1) remove "preliminary" when design is ready for submittal
2) all plumbing plans require a signed engineers stamp.
3) review NFPA 20 for required floor drainage
4) pipe secondary roof drainage to exterior by gravity.ISPC 1101.12.2.2.1

Routing PW Solid Waste2/13/2018 2/14/2018 PASS
DetailsEvan Carpenter
Routing PW Geothermal2/13/2018 2/13/2018 PASS
DetailsJon R. Gunnerson
No connection to geothermal heating district. Contact Public Works if desiring to connect onto system.
Intake Approval  2/13/2018 PASS
Routing PW Drainage2/13/2018 2/13/2018 PASS
DetailsBrian Murphy
Routing - Addressing2/13/2018 2/13/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS2/13/2018 2/13/2018 PASS
DetailsRachael Beierle
Routing - Design Review2/13/2018 2/13/2018 PASS
DetailsAndrea Tuning
Intake Approval  1/29/2018 FAIL
Application received  12/29/2017 DONE
Application submitted via PDS Online on Dec 29 2017 9:28AM