Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD19-02010
StatusFinaled
Name CARL FUNK CONSTRUCTION
Site Address 1447 N PINEVIEW LN
Project NameEncore Townhouses
Customer NumberEPLAN BLD19-02007
ePlanReview 
Description
**PRESCRIPTIVE ENERGY REQUIREMENTS** (TWO PERMITS FILED UNDER BLD19-02007) Permit for the construction of a new 1513 sq. ft., 2 story (first story 674 sq. ft., second story 839 sq. ft.) Townhouse with 3 bedrooms, 2.5 bathrooms, 56 sq. ft. covered patio/porch and a 400 sq. ft. attached garage per the approved plans and any notations. C-1D zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance/Occupancy  3/3/2020 DONE
BLD-Final2/27/20202/28/20202/28/2020PPASS
DetailsJim Storey
Jim Phone #: ###-####
DOC - Permit Finaled2/28/20202/28/20202/28/2020PPASS
DetailsJim Storey
BLD-Blower Door Test Results2/28/20202/28/20202/28/2020PDONE
DetailsJim Storey
Jim Phone #: ###-#### 4.93
BLD-Final2/24/20202/25/20202/25/2020AFAIL
DetailsMike Jordan
Carl Phone #: ###-####. Complete fire cauliking in garage and provide blower door test results.
BLD-Framing/Rough-in11/6/201911/7/201911/7/2019APASS
DetailsMike Jordan
sheet rock framing // Jim Phone #: ###-####
BLD-Framing/Rough-in10/24/201910/25/201910/25/2019APASS
DetailsMike Jordan
jim Phone #: ###-####
BLD-Energy code compliance10/25/201910/25/201910/25/2019APASS
DetailsMike Jordan
jim Phone #: ###-####
BLD-Wall cover10/24/201910/24/201910/24/2019PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Carl Funk
BLD-Framing/Rough-in10/24/201910/24/201910/24/2019PNR
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Carl Funk
BLD-Framing/Rough-in10/21/201910/21/201910/21/2019PFAIL
DetailsMike Jordan
Complete lateral bracing on A3 trusses. Complete fireblocking on furdowns. Nail off all simpson hangars and provide fixes for trusses at entry way. Ok to insulate.
BLD-Framing/Rough-in10/18/201910/21/201910/21/2019ACANC
DetailsMike Jordan
JIM Phone #: ###-####. moved to pm inspection.
BLD-Framing/Rough-in10/15/201910/15/201910/15/2019PFAIL
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Conference9/30/20199/30/20199/30/2019PDONE
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Wall Bracing9/30/20199/30/20199/30/2019PPASS
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Wall Bracing9/27/20199/27/20199/27/2019AFAIL
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Carl Funk//sthds in wrong locations//framing and nailing needs address at portal frames//window added in shear location at front entry//2 hr wall does not reflect plans//
BLD-Wall Bracing9/17/20199/18/20199/18/2019AFAIL
DetailsMike Jordan
Carl Phone #: ###-####. Needs to provide a full set of approved plans. Notes say there should be a total of eight pages of construction docs. Omly seven are provided. Wall bracing
BLD-Foundation8/16/20198/16/20198/16/2019PPASS
DetailsMike Jordan
stem wall // Willie Phone #: ###-####
BLD-Footing8/9/20198/12/20198/12/2019APASS
DetailsMike Jordan
Sergio Phone #: ###-####
BLD-Footing8/8/20198/9/20198/9/2019AFAIL
DetailsMike Jordan
Sergio Phone #: ###-####. Approved plans shows duplex 1hr. wall seoeration, per scope of work, townhouses are being constructed, which require a 2hr. seperation. Plans to be resubmitted.
BLD-Footing8/8/20198/8/20198/8/2019PFAIL
DetailsMike Jordan
surgeo Phone #: ###-####. No city approved plans on site.
Issue PAID IN FULL permit  7/30/2019 DONE
Inspection Record Card- Bld  7/30/2019 DONE
Telephone call  7/26/2019 DONE
GC will be here next week to submit 302 and sign for permits
OVERRIDE  7/24/2019  
Plan assigned to (J_N)7/10/20197/10/20197/24/2019 DONE
DetailsJenny Nelson
2nd review, waiting for planning. 1st complete 7/12, wall bracing, floor joist main floor, ul or ga
Routing - PLANNING7/22/2019 7/24/2019 PASS
DetailsBrent Moore
PLANS/APPL TAKEN TO FRONT DESK  7/24/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  7/24/2019 DONE
ALL MET-
NEED VALID RP
DO NOT ISSUE WITHOUT BLD19-02007
owner changed GC- needs to provide New GC
Routing - PLAN CHECK7/22/2019 7/22/2019 PASS
DetailsJenny Nelson
1st review completed  7/12/2019 DONE
DetailsJenny Nelson
Routing - PLAN CHECK7/10/2019 7/12/2019 FAIL
DetailsJenny Nelson
Routing - PLANNING7/10/2019 7/12/2019 FAIL
DetailsBrent Moore
Need to show distance from 2nd floor to west property line. 15' setback required.
Route to Impact Fee Review7/10/20197/13/20197/11/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - Addressing7/10/2019 7/10/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/10/2019 7/10/2019 PASS
DetailsAngela Hardy
Routing - MECHANICAL7/10/2019 7/10/2019 PASS
DetailsTroy James
Plans ACCEPTED BY PLAN TECH  7/10/2019 DONE
Intake Approval  7/10/2019 PASS
Recd Pcfee & Taken To Pln CK  7/10/2019 DONE
Intake Approval  6/27/2019 FAIL
1. Stair section detail showing dimensions of treads, risers, headroom, handrails, & guard requirements.
2. elevation height to top of roof
3. energy compliance- REScheck
4. Label furnace and air conditioner
5. Light switches of top and bottom of stairs for both townhomes.
Application received  6/3/2019 DONE
Application submitted via PDS Online on Jun 3 2019 8:33AM