BLD-Final | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | PASS |
Brandon Shaw
|
|
|
Front door is open Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Final | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. complete fire caulking in garage. repair sheet rock on house/garage seperation.
|
BLD-Blower Door Test Results | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | DONE |
Mike Jordan
|
|
|
4.9
|
BLD-Energy code compliance | 1/15/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/15/2020 | 1/16/2020 | 1/16/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Energy code compliance | 1/13/2020 | 1/15/2020 | 1/15/2020 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/13/2020 | 1/15/2020 | 1/15/2020 | P | FAIL |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle 2nd c/n posted .
|
BLD-Framing/Rough-in | 1/6/2020 | 1/13/2020 | 1/13/2020 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Complete airseal pak. Provide attic access in garage. F4 floor truss installed backwards. Provide (2) 2x under 2ply upstairs (behind tub). Correction notice posted. Ok to insulate.
|
BLD-Wall Bracing | 1/3/2020 | 1/6/2020 | 1/6/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
Routing - MECHANICAL | 1/2/2020 | | 1/3/2020 | | PASS |
Troy James
|
|
|
|
BLD-Wall Bracing | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | FAIL |
Mike Jordan
|
|
|
Sorry framer said no one was there with plans, they are here now. Phone #: ###-#### Inspection requested via web by Joel Hirtle. Nail sill plate with galvanized nails. Fasten all missed areas on sheathing. Install missed blocking and repair incorrect installed blocking.
|
BLD-Wall Bracing | 12/31/2019 | 1/2/2020 | 1/2/2020 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. No plans on site.
|
Plan Modification Accepted | | | 12/31/2019 | | DONE |
|
|
|
Gloria requested the workflow to be opened for new Manual J.
|
BLD-Foundation | 12/6/2019 | 12/9/2019 | 12/9/2019 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/5/2019 | 12/6/2019 | 12/6/2019 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/4/2019 | 12/5/2019 | 12/5/2019 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 12/3/2019 | 12/4/2019 | 12/4/2019 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/27/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/27/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/26/2019 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 11/22/2019 | 11/22/2019 | 11/26/2019 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 11/26/2019 | | 11/26/2019 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2019 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 11/26/2019 | | DONE |
|
|
|
met
|
1st review completed | | | 11/25/2019 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 10/28/2019 | | 11/25/2019 | | FAIL |
Jenny Nelson
|
|
|
Per D_S review
|
Plan assigned to (RDP) | 10/28/2019 | 10/28/2019 | 11/22/2019 | | DEFR |
Rob Patrick
|
|
|
11/12 sfd L1 ePlan
|
Route to Impact Fee Review | 10/28/2019 | 10/31/2019 | 10/29/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 10/28/2019 | | 10/29/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/28/2019 | | 10/28/2019 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 10/28/2019 | | 10/28/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/28/2019 | | 10/28/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/28/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/28/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/28/2019 | | PASS |
|
|
|
|
Application received | | | 10/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 25 2019 7:27AM
|