Site Final | 10/18/2019 | 10/18/2019 | 10/21/2019 | P | PASS |
Michael Zawacki
|
|
|
|
DOC - Permit Finaled | 10/21/2019 | 10/21/2019 | 10/21/2019 | P | PASS |
Michael Zawacki
|
|
|
|
General Inspection | 10/18/2019 | 10/18/2019 | 10/18/2019 | | CANC |
Andy J. Long
|
|
|
|
General Inspection | 9/26/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Michael Zawacki
|
|
|
Exterior complete and lot landscaped. Workers in ninterior.
|
General Inspection | 7/15/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Andy J. Long
|
|
|
Frame is built, construction entrance installed. No trackout or discharges.Washout was used, but is now dry and full, but currently not in use.
|
General Inspection | 6/5/2019 | 6/5/2019 | 6/5/2019 | P | PASS |
Michael Zawacki
|
|
|
Some wood scraps and waster from builders throwing cut ends off roof. No major ESC issues.
|
General Inspection | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Michael Zawacki
|
|
|
WIP on framing. Concrete washout damaged when backfill removed, will need to be rebuilt or repaired. Site is clean, no ESC issues.
|
BMP Violation | 3/28/2019 | 3/29/2019 | 4/2/2019 | A | PASS |
Michael Zawacki
|
|
|
Large washout constructed and used.
|
General Inspection | 3/19/2019 | 3/26/2019 | 3/26/2019 | P | PEND |
Andy J. Long
|
|
|
follow up
corrections not completed. No new issues. Subdvision landscaping using stockpile and causing minor trackout from stockpile.
|
Random Inspection | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | FAIL |
Andy J. Long
|
|
|
No concrete washout containment set up.
Dumped on stockpile, then dumped again on by neighboring project's pool.
Warning and request to clean up ASAP. Follow up scheduled.
|
General Inspection | 2/7/2019 | 2/15/2019 | 2/15/2019 | A | PASS |
Michael Zawacki
|
|
|
Excavation for home has begun, no concrete work. Lot is contained, backfill stored on parcel. No trackout.
|
General Inspection | 2/14/2019 | 2/14/2019 | 2/15/2019 | P | CANC |
Michael Zawacki
|
|
|
|
Site Preparation | 2/5/2019 | 2/7/2019 | 2/7/2019 | A | PASS |
Andy J. Long
|
|
|
10 AM Lance 6311356
Site walk through with GC Lance and RP Matt with Beus Excavation. Preconstruction meeting. Permit sign posted, RP will coordinate with Jeff Wright Privada RP as well. Receiving storm drains have sediment protection installed.
RP to install sediment control wattle on the east perimeter above the landscaped entrance. Trench and stake every 4-5 ft requested. RP to park trash trailer at front of site. Rock entrance is installed, request for more rock to be added. Have employees park on street not open lots.
Approved for construction. Follow up scheduled.
|
Permit Ready to Issue | | | 2/5/2019 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 2/5/2019 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 12/5/2018 | | 12/7/2018 | | PASS |
Andy J. Long
|
|
|
ESC site map with BMPs approved. Contractor needs to identify certified Responsible Person prior to issue. Site Preparation Inspection required prior to construction.
|
Application received | | | 11/13/2018 | | |
|
|
|
|