Permit NumberFIR18-00930
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 8000 S FEDERAL WAY
Project NameMicron Canopy
Customer Number 
ePlanReviewYes
Description
Viking is to install a dry line sprinkler system and heads under an outdoor canopy area near the cafeteria. Viking will tie into the existing wet system to feed the dry line system.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection5/2/20195/2/20195/2/2019PPASS
DetailsTroy Cobbley
Permit finaled
Plan assigned to (Stumbaugh)4/30/2019 5/2/2019 DONE
DetailsMark Stumbaugh
as built
Sprinkler Plan Check5/2/2019 5/2/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  5/2/2019 DONE
DetailsMark Stumbaugh
Plan Mod Fee $150.00
Permit Ready to Issue  5/2/2019 DONE
plan mod
CHANGE STATUS TO (ISS)  5/2/2019 DONE
plan mod
INSP-Final Inspection4/29/20194/30/20194/30/2019AFAIL
DetailsTroy Cobbley
Permit will be ok for final when the plan mod is approved.

Roy is the contact Phone #: ###-#### Inspection requested via web by Chris Green
Plan resubmittals received  4/30/2019 DONE
per Chris Green from Viking Fire Protection start workflow as-built
Plan assigned to (Stumbaugh)4/30/2019 4/30/2019 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check4/30/2019 4/30/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  4/30/2019 DONE
DetailsMark Stumbaugh
As-Built drawings no fee
INSP-Final Inspection3/4/20193/5/20193/5/2019APART
DetailsJim Page
Trip test was completed with Lee Meridith, could not perform walkthrough due to time constraints. Final walk through of project will need to be completed.

Zack Grasmick is the contact. Needing a final and a trial test. Phone #: ###-#### Inspection requested via web by Chris Green
INSP-Sprinkler Rough-in/Hydro2/28/20193/1/20193/1/2019PDONE
DetailsJim Page
Hydrostatic test for canopy dry system witnessed, no pressure loss observed.

zack Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro2/19/20192/20/20192/20/2019ACANC
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping in conapy has been cancelled, weather does not permit a hydrostatic test, temperature for hydrostaic tests needs to be maintained at 40 degrees or above for hydro to be accepted.

Zach Phone #: ###-####
INSP-Supply line flush2/19/20192/20/20192/20/2019ACANC
DetailsJim Page
Inspection request was for a completion on the air test, not a main line flush, this request is cancelled.

air test // Zack Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro2/20/20192/20/20192/20/2019ADONE
DetailsJim Page
24 hour air test complete with no pressure loss witnessed.
INSP-Supply line flush2/19/20192/19/20192/19/2019PPART
DetailsJim Page
Air test started at 9AM with 50 PSI.

air test // Zack Phone #: ###-####
Sprinkler Plan Check12/28/2018 12/31/2018 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  12/31/2018 PASS
DetailsMark Stumbaugh
Permit Ready to Issue  12/31/2018 DONE
met
Issue and Print Permit  12/31/2018 DONE
Plan resubmittals received  12/28/2018 DONE
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/28/2018 12/28/2018 DONE
DetailsMark Stumbaugh
Sprinkler Plan Check12/19/2018 12/19/2018 FAIL
DetailsMark Stumbaugh
Application received  12/11/2018 DONE
Application submitted via PDS Online on Dec 11 2018 10:30AM
Intake Approval  12/11/2018 PASS
DetailsMark Stumbaugh
Plan assigned to (Stumbaugh)12/11/2018 12/11/2018 DONE
DetailsMark Stumbaugh