BLD-Final | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. All issues have been resolved. Ok for perm. occ.
|
BLD-Framing/Rough-in | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | CANC |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Final | 4/30/2018 | 4/30/2018 | 4/30/2018 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. All issues have been resolved except for protection of sleeves in 1hr. roof/ceiling assembly above coolers.
|
BLD-Conference | 4/4/2018 | 4/4/2018 | 4/4/2018 | A | DONE |
Mike Jordan
|
|
|
Request for Michael Jordan to visit the job site to discuss outstanding items. Phone #: ###-#### Inspection requested via web by Steve Jacobsen. Discussed 3M duct wrap EJ with contractor on wrapping the solar light tubes and duct for med gas room ventilation. Noted to contractor to send EJ to building official for approval.
|
FIRE-Final Inspection | 3/9/2018 | 3/12/2018 | 3/12/2018 | P | PASS |
Jim Page
|
|
|
Delayed egress doors tested and verified for proper operation. Final life fire safety inspection complete.
|
BLD-Final | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PART |
Mike Jordan
|
|
|
Ok for temp occupancy only.
|
BLD-Framing/Rough-in | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Bldg #100 Missing fire dampers at 1hr ceiling at rooms 117 and 126. Rooms 148 and 150 need 45 min doors., protec penetrations at 1hr. ceiling above coolors. provide 1hr. shaft in attic for gas room ventilation in room 131. Also noted solar light tubes installed in conferance room, not on approved plans. Architect to provide details on how to protect the opening in the 1hr. ceiling assembly. Will be ok for temp occ. once a bond has been posted for zoning to allow the state to start conducting their inspections and for building owner to move furniture in ONLY.
|
FIRE-Final Inspection | 2/23/2018 | 2/23/2018 | 2/23/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary for the life safety is being given to provide access for State Of Idaho certification. If cooking or training is to be started Scott Arellano is to be contacted for approval. For a final sign off I need the delayed egress doors tested, the project related fire alarm permit finaled and the exit discharge lighting issues approved as discussed.
Steve Phone #: ###-####
|
BLD-Final | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | FAIL |
Mike Jordan
|
|
|
did not want to schedule fire life & safety and understood fir permit failed inspection /// Nathan Phone #: ###-####. Bldg #300. Doors 302,303,304 to be 45 min. with self closer and smoke seals. Protect through penetrations in data room 322. No fire dampers in ceilings in rooms 307, 310 and 325. Bldg 200, doors at rooms 211, 212 and 213 to be 45 min., self closing with smoke seals and sweeps.
|
BLD-Final | 2/20/2018 | 2/21/2018 | 2/21/2018 | A | FAIL |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Bldg 200 only walk through. Needs to install all mirrors. Doors 204,210, 226 and 211 are required to be min. 45 min rated, they are not. Also need to verify slopes on sides to bldg 200, west side.
|
FIRE-Final Inspection | 2/21/2018 | 2/21/2018 | 2/21/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the exit discharge lighting issue resolved, need to test the Delay Egress Doors, need smoke damper actuation tested and shown on the fire alarm plans. See the mechanical sheets for locations of the fire/smoke dampers.
|
FIRE-Alarm Testing | 2/19/2018 | 2/21/2018 | 2/21/2018 | A | CANC |
Troy Cobbley
|
|
|
continued phased inspection of alarms Phone #: ###-#### Inspection requested via web by Steve Jacobsen
|
FIRE-Alarm Testing | 2/19/2018 | 2/20/2018 | 2/20/2018 | A | CANC |
Troy Cobbley
|
|
|
continued phased inspection of alarms Phone #: ###-#### Inspection requested via web by Steve Jacobsen
|
FIRE-Final Inspection | 2/9/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Troy Cobbley
|
|
|
Project is not ready for a final yet. Todays inspection was just to verify that the exit signs, emergency lights and exit discharge lights functioned on emergency generator. I noted that the exit discharge lights have been connected to photo cells for control. I have contacted plan review since I do not see this allowed in the Code.
Steve Phone #: ###-####
|
FIRE-Conference | 1/29/2018 | 1/29/2018 | 1/30/2018 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with Steve which included the medical gas rooms. Per the electrician the exit discharge lights are controled by a photo cell. Per Chapter 10 of the IFC no allowance is made for this or timers.
Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 1/16/2018 | 1/16/2018 | 1/16/2018 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Building #300.
|
BLD-Ceiling Grid Inspection | 12/12/2017 | 12/12/2017 | 12/12/2017 | P | PASS |
Mike Jordan
|
|
|
Nate Phone #: ###-####. Building 100 ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 12/7/2017 | 12/7/2017 | 12/7/2017 | A | PASS |
Mike Jordan
|
|
|
Building 200 ceiling grid ok.
|
BLD-Ceiling Grid Inspection | 12/6/2017 | 12/7/2017 | 12/7/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Wrong inspection entered. rescheduled.
|
BLD-Ceiling Grid Inspection | 11/16/2017 | 11/16/2017 | 11/17/2017 | P | CANC |
Mike Jordan
|
|
|
building 200- Steve Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/16/2017 | 11/17/2017 | 11/17/2017 | A | PASS |
Mike Jordan
|
|
|
ceiling grid in bldg. 200 ok.
|
BLD-Framing/Rough-in | 10/18/2017 | 10/19/2017 | 10/19/2017 | A | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. south half of building 300 ok to sheet rock.
|
BLD-Framing/Rough-in | 10/11/2017 | 10/12/2017 | 10/12/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. north rooms and lid ok to sheet rock.
|
BLD-Framing/Rough-in | 10/6/2017 | 10/9/2017 | 10/9/2017 | A | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Energy code inspection, exterior walls bldg. #300.
|
BLD-Framing/Rough-in | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Framing for p.c.
|
BLD-Framing/Rough-in | 9/29/2017 | 9/29/2017 | 9/29/2017 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Exterior walls only ok, pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 9/19/2017 | 9/20/2017 | 9/20/2017 | A | PASS |
Mike Jordan
|
|
|
Doug Phone #: ###-####. Ok to rock corridors ceilings and wall to plate line only. Also spoke to contractor about the possibilty of insulating that portion of wall above plate line prior to sheet rock.
|
BLD-Framing/Rough-in | 9/8/2017 | 9/11/2017 | 9/11/2017 | A | PART |
Dave Hannah
|
|
|
Nathan Phone #: ###-#### ok to cover walls bldg 100
|
BLD-Framing/Rough-in | 9/5/2017 | 9/5/2017 | 9/5/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Ok to rock remaining lids in bldg 100. Work in progress on insulation.
|
BLD-Energy code compliance | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | CANC |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 8/29/2017 | 8/29/2017 | 8/29/2017 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. building 100, ok to insualte north of first corridor only.
|
BLD-Framing/Rough-in | 8/25/2017 | 8/28/2017 | 8/28/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Building 100 framing. Needs to complete airseal, complete all pre rock and fireblocking nd install all hatchannel.
|
BLD-Framing/Rough-in | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Exterior shear on bldg 300 is now ok.
|
BLD-Framing/Rough-in | 8/10/2017 | 8/11/2017 | 8/11/2017 | A | PART |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. North wing, bldg 200 ok. Wall bracing on bldg. 300 noted several areas missing blocking and fasteners.
|
BLD-Conference | 8/8/2017 | 8/9/2017 | 8/9/2017 | A | FAIL |
Mike Jordan
|
|
|
Remove sheet rock from furred walls, nrth wing of building 200. Remove tyvek from exteriorof building 300 for bracing inspection. The tenmat listing provided for light protection in th 1 hr. ceiling is non compliant for this use. A corection notice was issued.
|
BLD-Framing/Rough-in | 8/8/2017 | 8/8/2017 | 8/8/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Ok to sheetrock corridor ceilings in bldg. 100. only.
|
BLD-Framing/Rough-in | 7/24/2017 | 7/25/2017 | 7/25/2017 | A | PASS |
Mike Jordan
|
|
|
Exterior shear and inteior shear walls on bldg. 100 ok. Smoke barrier above grid in bldg. 200 ok and at concealed areas. Roof ceiling assembly in concealed areas ok as well.
|
BLD-Energy code compliance | 7/24/2017 | 7/24/2017 | 7/24/2017 | P | PASS |
Mike Jordan
|
|
|
Nathan Phone #: ###-####. Elelctrical room Bldg. 100 ok.
|
BLD-Framing/Rough-in | 7/21/2017 | 7/21/2017 | 7/21/2017 | P | PASS |
Mike Jordan
|
|
|
Bldg. 100 roof ok toover.
|
BLD-Framing/Rough-in | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | FAIL |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Complete all penetrations on smoke barrier wall. Remove rock from areas behind tubs on either side of smoke barrier walls and conplete ceiling assembly and rock those portions of smoke barrier.
|
BLD-Framing/Rough-in | 7/14/2017 | 7/14/2017 | 7/17/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Bldg 200 ok to sheet rock except for north wing.
|
BLD-Conference | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | CANC |
Mike Jordan
|
|
|
Steve Jacobson Phone #: ###-####
|
BLD-Energy code compliance | 7/12/2017 | 7/12/2017 | 7/12/2017 | P | PASS |
Mike Jordan
|
|
|
Steve Jacobson Phone #: ###-####. South and west exterior walls only on bldg.200 ok.
|
BLD-Framing/Rough-in | 7/12/2017 | 7/12/2017 | 7/12/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 100 roof strapping was completed. Prevously noted missing straps not required per engineers site visit. South and west wings rooms ok.
|
BLD-Framing/Rough-in | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | PART |
Mike Jordan
|
|
|
Roof nailing ok. Installing strapping when on site. Engineer to provide RFI for alternate connections on drag trusses.
|
BLD-Framing/Rough-in | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | NR |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Roof for building 100, not ready.
|
BLD-Framing/Rough-in | 6/8/2017 | 6/9/2017 | 6/9/2017 | A | PART |
Dave Hannah
|
|
|
Steve Phone #: ###-#### south side of bldg 200 corradors ok to cover lids
|
BLD-Conference | 6/6/2017 | 6/6/2017 | 6/6/2017 | P | DONE |
Mike Jordan
|
|
|
Reviewed alternate 1hr. details from architect for double walls to comply with the 1hr. wall requirements. Listed Assembly provided with addition of 2 layers of 5/8 type x rock above double top plates to keep continuity of 1hr. ceiling assembly.
|
BLD-Conference | 6/5/2017 | 6/5/2017 | 6/5/2017 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Conference | 6/1/2017 | 6/2/2017 | 6/2/2017 | A | DONE |
Mike Jordan
|
|
|
Meeting with sub contractors on fire stopping requirements.
|
BLD-Wall Bracing | 5/22/2017 | 5/25/2017 | 5/25/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 200 exterior shearwalls ok.
|
BLD-Framing/Rough-in | 5/19/2017 | 5/22/2017 | 5/22/2017 | A | PASS |
Mike Jordan
|
|
|
Bldg. 200 roof nailing ok. all straps in and completed. Also received RFI from engineer of record giving staple conversion for roof sheathing attachment.
|
BLD-Wall Bracing | 5/22/2017 | 5/22/2017 | 5/22/2017 | A | FAIL |
Mike Jordan
|
|
|
Bldg. 200 exterior shear walls. Several areas missed. All missed areas were marked. Framer to fasten all missed areas.
|
BLD-Framing/Rough-in | 5/19/2017 | 5/19/2017 | 5/19/2017 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 5/18/2017 | 5/18/2017 | 5/18/2017 | P | PEND |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Roof nailing on bldg. 200. Used staples, plans call for 8d nails. Waiting for RFI from engineer.
|
BLD-Foundation | 12/6/2016 | 12/7/2016 | 12/7/2016 | P | PASS |
Mike Jordan
|
|
|
Rebar // Steve Phone #: ###-####. Perimeter stemwalls for bldg. 100.
|
BLD-Footing | 12/1/2016 | 12/1/2016 | 12/1/2016 | P | PART |
Mike Jordan
|
|
|
Steve-rebar Phone #: ###-####. Bldg.300 perimeter footings. Will have special inspection.
|
BLD-Footing | 11/22/2016 | 11/22/2016 | 11/22/2016 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Perimeter stemwalls and courtyards for bldg. 200. Perimeter footings for blg. 100 and garden area.
|
BLD-Footing | 11/15/2016 | 11/16/2016 | 11/16/2016 | P | PART |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Perimter footings and west courtyard footings for bldg. 200. Will have special inspection..
|