Information based on query as of Sunday, May 12, 2024.
Permit Information
Permit NumberBLD18-03923
StatusFinaled
Name PARKWAY C&A LP
Site Address 7499 W OVERLAND RD
Project NameHampton Inn and Suites Remodel
Customer NumberEARLY START BLD18-04155
ePlanReviewNo
Description
(HAMPTON INN AND SUITES REMODEL) // 06/10/19 PLAN MOD TO FIRE RATE THE LOBBY BEAM USING OPTION 2 (GA FILE BM1137) OR OPTION 3 (UL N759). JAR // 06/06/19 PLAN MOD TO REPAIR PORTE COCHERE ROOF DUE TO WATER DAMAGE. REPAIR TO MATCH ORIGINAL DESIGN AND TO BE CONSTRUCTED AS 1-HOUR FIRE RESISTANCE RATED ASSEMBLY WITH RATED PENETRATIONS. ALL RECESSED LIGHTS TO BE UL LISTED. JAR // This building is fire sprinklered. Permit for minor remodel to an existing hotel. Work to include: interior demo of office non-rated, non-bearing, partition walls; new interior non-rated, non-bearing partition walls and doors in office area; replacement of existing light fixtures with new LED fixtures; interior finishes including replacement of plumbing fixtures; new flooring and other new interior finishes in compliance with Ch. 8 of the 2015 IBC. Certificate of completion to be issued upon completion of work. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/9/20199/10/20199/10/2019APASS
DetailsMike Jordan
Brandon Phone #: ###-####
DOC - Permit Finaled9/10/20199/10/20199/10/2019PPASS
DetailsMike Jordan
FIRE-Final Inspection9/4/20199/4/20199/4/2019PPASS
DetailsTroy Cobbley
Life safety passed. Card signed. Brandon Phone #: ###-####
BLD-Framing/Rough-in8/29/20198/30/20198/30/2019APASS
DetailsMike Jordan
Brandon Phone #: ###-####. Beyween noon and two. All issues regarding through penetrations for new tub drains has been resolved.
BLD-Conference8/28/20198/29/20198/29/2019ACANC
DetailsMike Jordan
Brandon Phone #: ###-####. Moved to friday 8-30.
BLD-Final7/25/20197/26/20197/26/2019APART
DetailsTell Riley
Brandon Phone #: ###-####//temp occupancy for offices behind lobby area//
FIRE-Final Inspection7/24/20197/25/20197/25/2019PPART
DetailsTroy Cobbley
Life safety is being given a partial for the remodeled office area behind the new check-in counter. Brandon Phone #: ###-####
BLD-Final7/24/20197/25/20197/25/2019APART
DetailsTell Riley
Brandon ###-####//need to verify with Troy for temp occupancy for lobby area only//ok for temp occupancy for reception area//do not occupy office areas and back room until all inspections complete//
BLD-Final7/23/20197/24/20197/24/2019PCANC
DetailsTell Riley
Brandon Phone #: ###-####
FIRE-Final Inspection7/24/20197/25/20197/24/2019APART
DetailsTroy Cobbley
Life safety is passed for the Lobby area but not the back office area. Per discussion emergency lighting will be required for the existing lobby prior to a final sign off just as it is being required at the bottom of both stairwells.

Brandon Phone #: ###-####
BLD-Ceiling Grid Inspection7/1/20197/2/20197/2/2019APASS
DetailsMike Jordan
Uri Phone #: ###-####
BLD-Final7/2/20197/3/20197/2/2019PCANC
DetailsMike Jordan
cancel per Yuiry Yuriy Phone #: ###-####
FIRE-Final Inspection7/2/20197/3/20197/2/2019ACANC
DetailsTroy Cobbley
cancel per Yuiry Yuriy Phone #: ###-####
BLD-Framing/Rough-in6/26/20196/26/20196/26/2019PPASS
DetailsMike Jordan
2 layers of 5/8 type X rock for previously unprotected beam ok for cover.
BLD-Framing/Rough-in6/25/20196/26/20196/26/2019PCANC
DetailsMike Jordan
yurry Phone #: ###-####.
BLD-Final6/19/20196/20/20196/20/2019PPART
DetailsMike Jordan
Yury-1st floor minus the front desk and back office Phone #: ###-####. Ok to occupy 1st. floor except for main lobby area.
FIRE-Final Inspection6/19/20196/20/20196/20/2019APART
DetailsTroy Cobbley
Life safety for the first floor, except for the Main Lobby and associated back office passed.

Yury-1st floor minus the front desk and back office Phone #: ###-####
BLD-Conference6/12/20196/13/20196/13/2019ADONE
DetailsMike Jordan
Eri Phone #: ###-####
BLD-Framing/Rough-in5/30/20195/31/20195/31/2019AFAIL
DetailsJim Storey
Yurri Phone #: ###-#### II a const. beam in lobby unprotected. sub mit to planreview as to how to address.
BLD-Framing/Rough-in5/29/20195/30/20195/30/2019APART
DetailsMike Jordan
Jery Phone #: ###-####. Interior steel stud framed walls in lobby area only ok. Needs t patch sheetrock at floor ceiling assemblies and fircaulk all penetrations. A mech permit is also required for the new duct work that was added in drop down ceiling area. A plan mod or a seperate building permit is also required for the repair of the porte cochere. A correction notice was issued.
BLD-Framing/Rough-in5/23/20195/23/20195/24/2019PNR
DetailsDave Hannah
reception area // Yuri Phone #: ###-####
BLD-Conference4/29/20194/29/20194/29/2019PDONE
DetailsMike Jordan
The correct fire caulking on 1st. floor has now been used.
BLD-Conference4/29/20194/29/20194/29/2019AFAIL
DetailsMike Jordan
Noted that caulking used is a fire block and not a UL listed fire stop. Contractor to insatll correct materials and will reinspect this afternoon. A correction notice was also issued to fire stop all tub drains and plumbing penetrations for new lavs on the 3rd and 4th floors, to maintain the exisiting fire protection.
BLD-Conference4/25/20194/26/20194/26/2019ACANC
DetailsMike Jordan
BLD-Conference4/25/20194/25/20194/25/2019PDONE
DetailsMike Jordan
BLD-Final4/19/20194/24/20194/24/2019ACANC
DetailsMike Jordan
1st, 2nd and 3rd // Yuriy Phone #: ###-####
BLD-Conference4/24/20194/24/20194/24/2019ADONE
DetailsMike Jordan
1st, 2nd and 3rd // Yuriy Phone #: ###-####
BLD-Final4/17/20194/18/20194/18/2019PPART
DetailsMike Jordan
Steve Phone #: ###-####. OPK to occupy 2nf. floor.
BLD-Final4/16/20194/17/20194/17/2019PNR
DetailsMike Jordan
2nd floor // Steve Phone #: ###-####. Needs electrical final.
FIRE-Final Inspection4/16/20194/17/20194/17/2019APART
DetailsTroy Cobbley
Life safety for the 2nd floor passed.// Steve Phone #: ###-####
BLD-Final2/21/20192/22/20192/22/2019PPART
DetailsMike Jordan
3rd floor // Steve Phone #: ###-####. Ok to occupy 3rd floor.
FIRE-Final Inspection2/21/20192/22/20192/22/2019APART
DetailsTroy Cobbley
Temp for life safety on 3rd floor. Contractor had to remove the new LED bulbs from the emergency lights and re-install the old bulbs for them to work on battery back up. // Steve Phone #: ###-####
BLD-Final2/14/20192/15/20192/15/2019PPART
DetailsJim Sly
Steve- wants partial on the 4th floor for a temp c of o Phone #: ###-####
Temp OK for 4th floor ........Only.
FIRE-Final Inspection2/15/20192/15/20192/15/2019PPART
DetailsJim Page
Life fire safety inspection for level 4 complete. Stairwells to remain clear with no storage once TCO is authorized.
FIRE-Final Inspection2/14/20192/15/20192/15/2019AFAIL
DetailsJim Page
Left a voicemail with point of contact provided, waited for 30 minutes to recieve a return call, no return call was made, proceeded to next inspection, this request will need to be rescheduled.

Steve- wants partial on the 4th floor for a temp c of o Phone #: ###-####
BLD-Conference8/15/20198/16/2019 A 
DetailsMike Jordan
Brandon Hout Phone #: ###-####
BLD-Conference4/26/20194/26/2019 P 
DetailsMike Jordan