BLD-Final | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner. Ok for perm occ.
|
BLD-Conference | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Final | 5/4/2020 | 5/4/2020 | 5/4/2020 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
FIRE-Final Inspection | 5/4/2020 | 5/4/2020 | 5/4/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
FIRE-Final Inspection | 4/29/2020 | 4/30/2020 | 4/30/2020 | P | FAIL |
Troy Cobbley
|
|
|
Permit can be finaled when the project related fire alarm permit and the Grading permit have been finaled. Jared Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/25/2020 | 3/26/2020 | 3/26/2020 | P | PASS |
Mike Jordan
|
|
|
2nd floor 3 west offices for ceiling cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Ceiling Grid Inspection | 3/20/2020 | 3/20/2020 | 3/20/2020 | P | PART |
Mike Jordan
|
|
|
2nd floor ceiling grid for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. Grid ok pending electrical and mech. rough in inspection.
|
BLD-Ceiling Grid Inspection | 3/16/2020 | 3/17/2020 | 3/17/2020 | P | PASS |
Mike Jordan
|
|
|
First floor ceiling grid Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Framing/Rough-in | 3/4/2020 | 3/4/2020 | 3/4/2020 | P | PASS |
Mike Jordan
|
|
|
2nd floor cloud ceiling framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Wall Bracing | 2/17/2020 | 2/18/2020 | 2/18/2020 | A | FAIL |
Mike Jordan
|
|
|
Ist floor west exterior wall interior shear Phone #: ###-#### Inspection requested via web by Jared Waggoner. Engineer of record to provide alternate attachment details for areas that are inaccessable to provide attachments.
|
BLD-Framing/Rough-in | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Mike Jordan
|
|
|
First floor suspended GWB ceiling and 2 exterior canopies for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Wall Bracing | 2/10/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Mike Jordan
|
|
|
2nd floor east interior shear wall Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Energy code compliance | 2/10/2020 | 2/10/2020 | 2/10/2020 | A | PASS |
Mike Jordan
|
|
|
2nd floor E/W/S exterior wall insulation Phone #: ###-#### Inspection requested via web by Jared Waggoner. Remainder of 2nd floor exterior walls ok.
|
BLD-Energy code compliance | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Mike Jordan
|
|
|
Foreman Phone #: ###-####. North exterior wall only ok.
|
BLD-Framing/Rough-in | 2/6/2020 | 2/6/2020 | 2/6/2020 | P | PASS |
Mike Jordan
|
|
|
2nd floor walls and ceilings for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Framing/Rough-in | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PART |
Tony Young
|
|
|
Framing inspection for 1 side at interior 2nd floor walls Phone #: ###-#### Inspection requested via web by Jared Waggoner/// ok to one side from 10' up pending trades
|
BLD-Energy code compliance | 1/23/2020 | 1/24/2020 | 1/24/2020 | A | PASS |
Jim Storey
|
|
|
First floor wall insulation Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Framing/Rough-in | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | PASS |
Mike Jordan
|
|
|
First floor rough framing for cover Phone #: ###-#### Inspection requested via web by Jared Waggoner. 1st. floor i nterior steel stud framed walls ok. hardlids ok pending mech. rough in inspection.
|
BLD-Wall Bracing | 1/13/2020 | 1/13/2020 | 1/13/2020 | P | PASS |
Mike Jordan
|
|
|
90% exterior sheet metal shear inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Concrete | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PART |
Mike Jordan
|
|
|
2nd floor slab on deck reinforcement Phone #: ###-#### Inspection requested via web by Jared Waggoner. 2nd. floor slab on deck. work in progress. Needs to install perimeter #4 bar and splice 15ft. at re-enterant corners. Special inspection to verify.
|
BLD-Other | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | DEFR |
Mike Jordan
|
|
|
8" CMU grout at east patio walls at 2:30 pm 12''-16'', will have special inspection. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Other | 10/31/2019 | 11/1/2019 | 11/1/2019 | P | PEND |
Mike Jordan
|
|
|
CMU grout from 8''-12'' at 1pm, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner. PEnding special inspection.
|
BLD-Other | 10/30/2019 | 10/31/2019 | 10/31/2019 | P | PART |
Mike Jordan
|
|
|
4''-8'' CMU grout at 3pm, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner. 4ft. to 8ft. elevation for CMU wall at patio.
|
BLD-Other | 10/30/2019 | 10/31/2019 | 10/31/2019 | A | DEFR |
Mike Jordan
|
|
|
0-4'' CMU grout at 10am, will have special inspection Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Concrete | 10/16/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Mike Jordan
|
|
|
Slab on Grade Reinforcement Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
BLD-Foundation | 9/27/2019 | 9/27/2019 | 9/27/2019 | P | PASS |
Brandon Shaw
|
|
|
Ok to place concrete pending special inspection.
|
BLD-Footing | 9/18/2019 | 9/18/2019 | 9/18/2019 | P | PART |
Mike Jordan
|
|
|
Call 30 minutes ahead // Jerrod Phone #: ###-####. Perimeter footings, column pad footings, interior footings and elevator and trash enclosure footings. Noted clearance issues in some areas. Special inspection agency to verify clearane issues have been repaired prior to conc. placement. Ok to place concrete pending special inspection.
|