BLD-Final | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | PEND |
Tony Young
|
|
|
Josh *screened* Phone #: ###-####557,, temp occupancy ok
|
BLD-Conference | 8/4/2020 | 8/5/2020 | 8/4/2020 | A | DONE |
Tony Young
|
|
|
Josh *screened* Phone #: ###-####557
|
BLD-Wall cover | 7/13/2020 | 7/14/2020 | 7/14/2020 | P | PART |
Tony Young
|
|
|
SCREENED // Josh Phone #: ###-####// temp occupancy ok.. pending trades on full occ.,, contractor will deliver final letters of ok from engineers for records
|
FIRE-Final Inspection | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Greg Ruxton
|
|
|
Fire Life Safety inspection passed. Building inspector to verify main entry doors panic hardware is code compliant for egress and over rides electric strike card reader once system is fully operational.
Josh *screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/30/2020 | 6/30/2020 | 6/30/2020 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####.. kitchen and restrooms ok
|
BLD-Aging Inspection | 6/18/2020 | 6/18/2020 | 6/24/2020 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 6/17/2020 | 6/17/2020 | 6/24/2020 | | PASS |
Tony Young
|
|
|
|
BLD-Ceiling Grid Inspection | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Dave Hannah
|
|
|
Josh *screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 3/30/2020 | 3/30/2020 | 3/30/2020 | P | PASS |
Jim Storey
|
|
|
Josh Phone #: ###-#### area b ok
|
BLD-Framing/Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####,, kitchen areas ok
|
BLD-Energy code compliance | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####// area C ok pending trades
|
FIRE-Conference | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | CANC |
Jim Page
|
|
|
Josh ###-####
|
FIRE-Conference | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | DONE |
Jim Page
|
|
|
Follow up conference scheduled for 16JAN2020 for question asked about attic sprinkler coverage, need further verification for sprinkler head coverage in question.
Josh Phone #: ###-####
|
BLD-Energy code compliance | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PART |
Dave Hannah
|
|
|
Josh Phone #: ###-#### ext walls west wing ok
|
BLD-Framing/Rough-in | 12/31/2019 | 12/31/2019 | 12/31/2019 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####// n/west area wing ok to insulate
|
BLD-Energy code compliance | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, east wing ok
|
BLD-Framing/Rough-in | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PART |
Dave Hannah
|
|
|
jOSH Phone #: ###-#### area ( B ) ok to insulate.
|
BLD-Conference | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, interior shear,, roof details, roof insulation,, extensive walk through,, Josh will note on plans
|
BLD-Other | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PART |
Tony Young
|
|
|
roof nailing // Josh Phone #: ###-####,, work in progress,, ok
|
BLD-Framing/Rough-in | 11/19/2019 | 11/20/2019 | 11/20/2019 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####// area C wall bracing ok
|
BLD-Other | 11/7/2019 | 11/8/2019 | 11/8/2019 | P | PART |
Tony Young
|
|
|
roof nailing // Josh Phone #: ###-####,, ok after re-nailing missed areas marked by paint,, north/west building
|
BLD-Wall Bracing | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PART |
Tony Young
|
|
|
north buildings // Josh Phone #: ###-####,, work in progress,, ok to cover after finishing
|
BLD-Other | 11/6/2019 | 11/7/2019 | 11/7/2019 | P | PART |
Tony Young
|
|
|
roof nailing // Josh Phone #: ###-####,, partial on area A,, need to redo some and finish upper areas
|
BLD-Other | 10/30/2019 | 10/31/2019 | 10/31/2019 | P | PART |
Tony Young
|
|
|
roof nailing // Josh Phone #: ###-####,, area B and the gym ok
|
BLD-Conference | 10/22/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Tony Young
|
|
|
Josh - Framing questions, wanted a consultation Phone #: ###-####,, fireblock ?s, bracing ?s
|
BLD-Foundation | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PEND |
Tony Young
|
|
|
rebar // Josh Phone #: ###-####,, pending special inspection
|
BLD-Other | 9/26/2019 | 9/27/2019 | 9/27/2019 | P | PEND |
Tony Young
|
|
|
2pm - grout and rebar // Josh Phone #: ###-####
|
BLD-Other | 9/23/2019 | 9/24/2019 | 9/24/2019 | A | PART |
Tony Young
|
|
|
grout // Josh Phone #: ###-####,, pending special inspection
|
BLD-Footing | 9/16/2019 | 9/17/2019 | 9/17/2019 | A | PART |
Tony Young
|
|
|
rebar // Josh Phone #: ###-####,, pending special inspection results
|
BLD-Foundation | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PART |
Tony Young
|
|
|
rebar // josh Phone #: ###-####,, pending special inspection
|
BLD-Footing | 9/6/2019 | 9/6/2019 | 9/6/2019 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, pending special inspection reports
|
BLD-Footing | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, area C
|
BLD-Footing | 8/28/2019 | 8/29/2019 | 8/29/2019 | P | PEND |
Tony Young
|
|
|
Josh- rebar inspection and footing wall Phone #: ###-####,, pending special inspection report
|
BLD-Foundation | 8/21/2019 | 8/22/2019 | 8/22/2019 | A | PEND |
Tony Young
|
|
|
wall rebar // Josh Phone #: ###-####,, special inspection
|
BLD-Concrete | 8/20/2019 | 8/20/2019 | 8/20/2019 | P | PART |
Tony Young
|
|
|
rebar-Josh Phone #: ###-####
|
BLD-Foundation | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PART |
Tony Young
|
|
|
foundation insulation // Josh Phone #: ###-####,, work oin progress,, special inspector reports
|
BLD-Foundation | 8/14/2019 | 8/15/2019 | 8/15/2019 | P | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, stem wall,, pending special inspection reports
|
BLD-Foundation | 8/8/2019 | 8/9/2019 | 8/9/2019 | A | PEND |
Tony Young
|
|
|
rebar // Izaak Phone #: ###-####,, pending S, I. report
|
BLD-Footing | 8/6/2019 | 8/7/2019 | 8/8/2019 | P | PART |
Tony Young
|
|
|
rebar // Issac Phone #: ###-####.. special inspector to be on site
|
BLD-Foundation | 8/6/2019 | 8/6/2019 | 8/6/2019 | P | PART |
Tony Young
|
|
|
rebar // Issac Phone #: ###-####,, pending special inspection report,, not pouring until Thursday
|
BLD-Foundation | 7/31/2019 | 8/1/2019 | 8/1/2019 | P | PART |
Tony Young
|
|
|
rebar // Josh Phone #: ###-####,, grid L and 3,, s/w gym area, deep footings,, pending special reports,, MTI
|