(HIGHLANDS ELEMENTARY SCHOOL) (Project Management Ron Hill) **WUI ZONE A REQUIREMENTS** **DEFERRED SUBMITTAL FOR BLEACHERS** Permit for the construction of a new single-story, 42,775 sq. ft. elementary school to replace the existing 26,247 sq ft school that is to be demolished. Work will include demolishing the existing building, removing existing modular classrooms, general site work, utilities and construction of the new building per the approved plans, attached engineering and any comments. Building includes 3,512 sq ft of equipment platform; NO storage is permitted in this area. Special inspections required per attached Form 310. This is a fully fire sprinklered and alarmed building for E fire area over 12,000 sq. ft. and building area increase. *JAR*
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/4/20208/5/20208/5/2020APEND
DetailsTony Young
Josh *screened* Phone #: ###-####557,, temp occupancy ok
BLD-Conference8/4/20208/5/20208/4/2020ADONE
DetailsTony Young
Josh *screened* Phone #: ###-####557
BLD-Wall cover7/13/20207/14/20207/14/2020PPART
DetailsTony Young
SCREENED // Josh Phone #: ###-####// temp occupancy ok.. pending trades on full occ.,, contractor will deliver final letters of ok from engineers for records
FIRE-Final Inspection7/7/20207/8/20207/8/2020APASS
DetailsGreg Ruxton
Fire Life Safety inspection passed. Building inspector to verify main entry doors panic hardware is code compliant for egress and over rides electric strike card reader once system is fully operational.

Josh *screened* Phone #: ###-####
BLD-Ceiling Grid Inspection6/30/20206/30/20206/30/2020PPASS
DetailsTony Young
Josh Phone #: ###-####.. kitchen and restrooms ok
BLD-Aging Inspection6/18/20206/18/20206/24/2020 PASS
DetailsTony Young
BLD-Aging Inspection6/17/20206/17/20206/24/2020 PASS
DetailsTony Young
BLD-Ceiling Grid Inspection5/11/20205/11/20205/11/2020PPASS
DetailsDave Hannah
Josh *screened* Phone #: ###-####
BLD-Ceiling Grid Inspection4/1/20204/2/20204/2/2020APASS
DetailsTony Young
Josh Phone #: ###-####
BLD-Ceiling Grid Inspection3/30/20203/30/20203/30/2020PPASS
DetailsJim Storey
Josh Phone #: ###-#### area b ok
BLD-Framing/Rough-in2/3/20202/4/20202/4/2020APASS
DetailsTony Young
Josh Phone #: ###-####,, kitchen areas ok
BLD-Energy code compliance1/21/20201/21/20201/21/2020PPART
DetailsTony Young
Josh Phone #: ###-####// area C ok pending trades
FIRE-Conference1/15/20201/16/20201/16/2020ACANC
DetailsJim Page
Josh ###-####
FIRE-Conference1/15/20201/15/20201/15/2020PDONE
DetailsJim Page
Follow up conference scheduled for 16JAN2020 for question asked about attic sprinkler coverage, need further verification for sprinkler head coverage in question.

Josh Phone #: ###-####
BLD-Energy code compliance1/7/20201/7/20201/7/2020PPART
DetailsDave Hannah
Josh Phone #: ###-#### ext walls west wing ok
BLD-Framing/Rough-in12/31/201912/31/201912/31/2019PPART
DetailsTony Young
Josh Phone #: ###-####// n/west area wing ok to insulate
BLD-Energy code compliance12/26/201912/27/201912/27/2019APART
DetailsTony Young
Josh Phone #: ###-####,, east wing ok
BLD-Framing/Rough-in12/20/201912/20/201912/20/2019PPART
DetailsDave Hannah
jOSH Phone #: ###-#### area ( B ) ok to insulate.
BLD-Conference12/10/201912/10/201912/10/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, interior shear,, roof details, roof insulation,, extensive walk through,, Josh will note on plans
BLD-Other11/22/201911/22/201911/22/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, work in progress,, ok
BLD-Framing/Rough-in11/19/201911/20/201911/20/2019PPART
DetailsTony Young
Josh Phone #: ###-####// area C wall bracing ok
BLD-Other11/7/201911/8/201911/8/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, ok after re-nailing missed areas marked by paint,, north/west building
BLD-Wall Bracing11/7/201911/8/201911/8/2019APART
DetailsTony Young
north buildings // Josh Phone #: ###-####,, work in progress,, ok to cover after finishing
BLD-Other11/6/201911/7/201911/7/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, partial on area A,, need to redo some and finish upper areas
BLD-Other10/30/201910/31/201910/31/2019PPART
DetailsTony Young
roof nailing // Josh Phone #: ###-####,, area B and the gym ok
BLD-Conference10/22/201910/22/201910/22/2019PPASS
DetailsTony Young
Josh - Framing questions, wanted a consultation Phone #: ###-####,, fireblock ?s, bracing ?s
BLD-Foundation10/1/201910/1/201910/1/2019PPEND
DetailsTony Young
rebar // Josh Phone #: ###-####,, pending special inspection
BLD-Other9/26/20199/27/20199/27/2019PPEND
DetailsTony Young
2pm - grout and rebar // Josh Phone #: ###-####
BLD-Other9/23/20199/24/20199/24/2019APART
DetailsTony Young
grout // Josh Phone #: ###-####,, pending special inspection
BLD-Footing9/16/20199/17/20199/17/2019APART
DetailsTony Young
rebar // Josh Phone #: ###-####,, pending special inspection results
BLD-Foundation9/11/20199/11/20199/11/2019PPART
DetailsTony Young
rebar // josh Phone #: ###-####,, pending special inspection
BLD-Footing9/6/20199/6/20199/6/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, pending special inspection reports
BLD-Footing9/5/20199/6/20199/6/2019APART
DetailsTony Young
Josh Phone #: ###-####,, area C
BLD-Footing8/28/20198/29/20198/29/2019PPEND
DetailsTony Young
Josh- rebar inspection and footing wall Phone #: ###-####,, pending special inspection report
BLD-Foundation8/21/20198/22/20198/22/2019APEND
DetailsTony Young
wall rebar // Josh Phone #: ###-####,, special inspection
BLD-Concrete8/20/20198/20/20198/20/2019PPART
DetailsTony Young
rebar-Josh Phone #: ###-####
BLD-Foundation8/19/20198/20/20198/20/2019APART
DetailsTony Young
foundation insulation // Josh Phone #: ###-####,, work oin progress,, special inspector reports
BLD-Foundation8/14/20198/15/20198/15/2019PPART
DetailsTony Young
Josh Phone #: ###-####,, stem wall,, pending special inspection reports
BLD-Foundation8/8/20198/9/20198/9/2019APEND
DetailsTony Young
rebar // Izaak Phone #: ###-####,, pending S, I. report
BLD-Footing8/6/20198/7/20198/8/2019PPART
DetailsTony Young
rebar // Issac Phone #: ###-####.. special inspector to be on site
BLD-Foundation8/6/20198/6/20198/6/2019PPART
DetailsTony Young
rebar // Issac Phone #: ###-####,, pending special inspection report,, not pouring until Thursday
BLD-Foundation7/31/20198/1/20198/1/2019PPART
DetailsTony Young
rebar // Josh Phone #: ###-####,, grid L and 3,, s/w gym area, deep footings,, pending special reports,, MTI