BLD-Final | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Mike Jordan
|
|
|
Alex Phone #: ###-####
|
DOC - Permit Finaled | 1/23/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Mike Jordan
|
|
|
Recieved 3rd party inspection final letter. No issues were noted. ok for final.
|
BLD-Final | 1/15/2020 | 1/16/2020 | 1/16/2020 | A | PEND |
Mike Jordan
|
|
|
Alex Phone #: ###-####. everything ok, need final letter from 3rd. party inspection firm.
|
BLD-Final | 1/13/2020 | 1/15/2020 | 1/15/2020 | P | CANC |
Mike Jordan
|
|
|
Alex Phone #: ###-####. Moved to thursday 1-16-20 for am inspection.
|
FIRE-Final Inspection | 1/13/2020 | 1/15/2020 | 1/15/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Alex Phone #: ###-####
|
BLD-Energy code compliance | 11/15/2019 | 11/18/2019 | 11/18/2019 | P | PASS |
Mike Jordan
|
|
|
Alex Phone #: ###-####
|
BLD-Framing/Rough-in | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | PASS |
Mike Jordan
|
|
|
Alex Phone #: ###-####. Roof framing for pump house ok.
|
BLD-Framing/Rough-in | 10/10/2019 | 10/14/2019 | 10/14/2019 | A | DEFR |
Mike Jordan
|
|
|
masion- Alex Phone #: ###-####. Ok pending special inspection.
|
BLD-Other | 10/7/2019 | 10/9/2019 | 10/10/2019 | P | PEND |
Dave Hannah
|
|
|
pour is at 1pm // grout for masonry walls // Jake Phone #: ###-#### ok after spec insp sign offs
|
BLD-Wall Bracing | 10/9/2019 | 10/10/2019 | 10/10/2019 | A | CANC |
Dave Hannah
|
|
|
jake Phone #: ###-####
|
BLD-Foundation | 9/19/2019 | 9/23/2019 | 9/23/2019 | A | PASS |
Mike Jordan
|
|
|
Alex- stem wall Phone #: ###-####
|
BLD-Footing | 9/13/2019 | 9/17/2019 | 9/17/2019 | A | PASS |
Mike Jordan
|
|
|
Alex Phone #: ###-####
|
BLD-Foundation | 9/4/2019 | 9/6/2019 | 9/6/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending Special inspection...
|
BLD-Concrete | 8/26/2019 | 8/29/2019 | 8/29/2019 | A | PASS |
Mike Jordan
|
|
|
pour at 11 // Alex Phone #: ###-####. outer ring footing ok.
|