Permit Information
Permit NumberBLD19-01141
StatusFinaled
Name IMCO GENERAL CONSTRUCTION INC
Site Address 519 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReviewYes
Description
(DARIGOLD) To construct a 606 sq. ft. single story equipment building plus a 1,810 sq. ft. equalization storage tank and related site improvements. Approval is contingent upon adhering to the approved plans on file, DRH19-00208, attached engineering and plan review report. Scope of work includes: site work, removal of a shed, construction of concrete foundations, slab on grade concrete, 8” CMU exterior walls, pre-engineered wood truss roof system, new pre-engineered storage tank, electrical work, mechanical work and plumbing work. Note: Special inspection is required, see attached 310 form. This building is Not fully Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/23/20201/23/20201/23/2020PPASS
DetailsMike Jordan
Alex Phone #: ###-####
DOC - Permit Finaled1/23/20201/23/20201/23/2020PPASS
DetailsMike Jordan
Recieved 3rd party inspection final letter. No issues were noted. ok for final.
BLD-Final1/15/20201/16/20201/16/2020APEND
DetailsMike Jordan
Alex Phone #: ###-####. everything ok, need final letter from 3rd. party inspection firm.
BLD-Final1/13/20201/15/20201/15/2020PCANC
DetailsMike Jordan
Alex Phone #: ###-####. Moved to thursday 1-16-20 for am inspection.
FIRE-Final Inspection1/13/20201/15/20201/15/2020APASS
DetailsTroy Cobbley
Life safety passed. Alex Phone #: ###-####
BLD-Energy code compliance11/15/201911/18/201911/18/2019PPASS
DetailsMike Jordan
Alex Phone #: ###-####
BLD-Framing/Rough-in11/8/201911/12/201911/12/2019APASS
DetailsMike Jordan
Alex Phone #: ###-####. Roof framing for pump house ok.
BLD-Framing/Rough-in10/10/201910/14/201910/14/2019ADEFR
DetailsMike Jordan
masion- Alex Phone #: ###-####. Ok pending special inspection.
BLD-Other10/7/201910/9/201910/10/2019PPEND
DetailsDave Hannah
pour is at 1pm // grout for masonry walls // Jake Phone #: ###-#### ok after spec insp sign offs
BLD-Wall Bracing10/9/201910/10/201910/10/2019ACANC
DetailsDave Hannah
jake Phone #: ###-####
BLD-Foundation9/19/20199/23/20199/23/2019APASS
DetailsMike Jordan
Alex- stem wall Phone #: ###-####
BLD-Footing9/13/20199/17/20199/17/2019APASS
DetailsMike Jordan
Alex Phone #: ###-####
BLD-Foundation9/4/20199/6/20199/6/2019PPEND
DetailsBrandon Shaw
Pending Special inspection...
BLD-Concrete8/26/20198/29/20198/29/2019APASS
DetailsMike Jordan
pour at 11 // Alex Phone #: ###-####. outer ring footing ok.