BLD-Final | 3/26/2020 | 3/27/2020 | 3/27/2020 | A | PASS |
Mike Jordan
|
|
|
Call when in route please. Thank you. Entry Code 4646 Phone #: ###-#### Inspection requested via web by Chris Laraway
|
DOC - Permit Finaled | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Mike Jordan
|
|
|
All issues have been resolved. Ok for perm occ.
|
BLD-Final | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PEND |
Mike Jordan
|
|
|
Final Fire inspection is pending. Bldg Corrections addressed. Please call Brad when on site. Garage Code 4646. Phone #: ###-#### Inspection requested via web by Chris Laraway. All issues on building portion resolved. Still needs to resolve fire sprinkler issues.
|
BLD-Final | 2/28/2020 | 2/28/2020 | 2/28/2020 | P | FAIL |
Tell Riley
|
|
|
Fire Sprinkler Final this morning. Blower door test complete. Plans on Counter. Code 4646. Please Call Brad with status when complete. Thank you Phone #: ###-#### Inspection requested via web by Chris Laraway//corection notice posted--left with approved plans//
|
BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Mike Jordan
|
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Energy code compliance | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Mike Jordan
|
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Framing/Rough-in | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PASS |
Mike Jordan
|
|
|
Fire Sprinkler to re-inspect in the am. for Cover approval. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
FIRE-Sprinkler Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Troy Cobbley
|
|
|
Tenting inspection for the fire sprinklers passed. Piping can be covered. Call Brad before/during inspection. Thank you, Phone #: ###-#### Inspection requested via web by Chris Laraway
|
FIRE-Supply Line Cover | 12/5/2019 | 12/5/2019 | 12/5/2019 | P | FAIL |
Troy Cobbley
|
|
|
Tenting needs repaired in the second floor bedroom and I need access to the area above the ceiling in the garage room.
Shilo Sprinkler installed system, Marv''s Insulation Tented the lines. Please call Brad if there are any questions or issues to be addressed. Thank you.. Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/5/2019 | A | CANC |
Mike Jordan
|
|
|
Sprinkler tenting inspection Thurs Afternoon. Cancel this inspection if Fire does not pass in the system. Please call Brad if there are any questions or other issues to be addressed. Thank you.. Phone #: ###-#### >> Inspection requested via web by Chris Laraway Inspection cancelled from web by: Chris Laraway
|
BLD-Framing/Rough-in | 12/3/2019 | 12/4/2019 | 12/4/2019 | A | NR |
Mike Jordan
|
|
|
Framing Correction have been made. Insulation installed today. 3rd party Energy inspection tomorrow. We are Holding for cover approval. Call Brad with any missed corrections or items of concern. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway. A tenting inspection is still required for the fire sprinkler.
|
BLD-Framing/Rough-in | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | FAIL |
Mike Jordan
|
|
|
Framing/Energy inspection requested. All Subs have passed. Call Brad if there are questions or concerns. Thank you. Phone #: ###-#### Inspection requested via web by Chris Laraway. Complete lateral bracing on BG2, B13, b08, B07 trusses. Missed bearing on BG1 truss. Fireblock garage wall at fir down(plumbing chase). Provide two 2x under D10 2ply truss. Nail bottom chord of D10 2 ply per the engineering. Tempered glazing required in window in upstairs bathroom. Correction notice posted. Ok to insulate.
|
BLD-Wall Bracing | 11/1/2019 | 11/1/2019 | 11/4/2019 | P | PART |
Dave Hannah
|
|
|
Plans on Site Phone #: ###-#### Inspection requested via web by Chris Laraway ok to cover ext but needs to install hold downs at rv garagr opennings
|
BLD-Wall Bracing | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Chris Laraway
|
BLD-Foundation | 8/27/2019 | 8/28/2019 | 8/28/2019 | A | PART |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 8/23/2019 | 8/26/2019 | 8/26/2019 | A | PART |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 8/23/2019 | 8/23/2019 | 8/23/2019 | P | NR |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | CANC |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 8/22/2019 | 8/22/2019 | 8/22/2019 | P | CANC |
Mike Jordan
|
|
|
chris Phone #: ###-####-Chris cancelled insp will reschedule
|
BLD-Footing | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | CANC |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|